Resolved
That the application be granted permission subject to the completion of a deed of variation to the existing s.106 legal agreement.
Planning Committee agreed this item on Thursday 3 September 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the application be granted permission subject to the completion of a deed of variation to the existing s.106 legal agreement.
Planning Committee 03 September 2015 Application Reference: 15/00661/CV
Reference: Site: 15/00661/CV London Gateway Port The Manorway Stanford Le Hope Essex
Ward: Proposal: Corringham and Application for removal or variation of a condition(s) following Fobbing the grant of planning permission: Variation to Schedule 6 (6) / (7) / (8) / (11b) / (14(1)(c)(i)(dd) / (14)(1)(c)(ii) and (14)(e)(i) of the London Gateway Port Harbour Empowerment Order 2008.
Plan Number(s): Reference Name Received Sheet 207 Limits of deviation of all works except dredging and 12th June 2015 Rev. C amelioration works Sheet 208 Limits of amelioration works 12th June 2015 Rev. C
The application is also accompanied by:
Planning Statement
Applicant: Validated: London Gateway Port Limited 15th June 2015 Date of expiry: 14th September 2015 Recommendation: Grant permission subject to the completion of a deed of variation to the existing s.106 legal agreement.
1.0DESCRIPTION OF PROPOSAL
1.1The London Gateway Harbour Empowerment Order (HEO) 2008 came into force in May 2008 and authorises the construction and operation of London Gateway Port, as well as establishing a new Harbour Authority for the Port. The first berth at the Port became operational in November 2013 and construction of the third berth is due to commence shortly.
1.2Schedule 6 of the HEO provides a number of provisions “for the protection of Thurrock Council and others” which principally relate to the mitigation of traffic impacts on the highway network. Paragraph 20 of Schedule 6 Application of Town and Country Planning legislation) states that: Planning Committee 03 September 2015 Application Reference: 15/00661/CV
“the provisions of this Schedule (6) shall be deemed to be conditions subject to which a planning permission was granted under section 70 of the 1990 (Town and Country Planning) Act and, accordingly, they shall be subject to the provisions of that Act and all associated legislation and in particular they may be varied in accordance with sections 73, 73A and 97 that Act and the Town and Country Planning (General Development Procedure) Order 1995”.
1.3This application, submitted pursuant to section 73 of the Town and Country Planning Act 1990, seeks a number of amendments to a number of provisions within Schedule 6 and (as described by the applicant) permission is sought to:
“Continue development of the London Gateway Port pursuant to the London Gateway Port Harbour Empowerment Order (2008 No. 1261) without compliance with protective provisions previously attached pursuant to Schedule 6 of that Order but subject to revised protective provisions.”
The wording of the current Schedule 6 provisions together with the proposed amendments and a commentary are provided below.
1.4Schedule 6 (6) – Pegasus Crossing:
Existing Wording:
No more than the following combinations of B1(b), B1(c), B2 and B8 floorspace set out in column (1) of the table and the corresponding number of berths forming part of the authorised works set out in column (2) of that table shall be first occupied or brought into beneficial use prior to the completion of the new access road as a single carriageway road together with a cycleway, footway and alongside the carriageway the provision for appropriate emergency stacking space for lorries accessing the authorised works and including a Pegasus crossing where the access road crosses the diverted Footpath 190
(1) (2) Floorspace Number of berths 377,000m2 Either the Ro-Ro or 1 berth without the Ro-Ro 324,000m2 Either the Ro-Ro and 1 berth or 2 berths without the Ro-Ro 271,000m2 Either the Ro-Ro and 2 berth or 3 berths without the Ro-Ro Planning Committee 03 September 2015 Application Reference: 15/00661/CV
Proposed Wording:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
15/00661/CV: London Gateway Port, The Manorway, Stanford Le Hope, EssexReport | 1.9 MB | DownloadRead as text |
Follow Planning Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Apr 2025 | 25/00010/FUL 360 Ashley CloseRESOLVED Approve application subject to conditions and informative (in relation to Land Ownership matters) to be agre... | Approved | Open |
| 8 Aug 2024 | Item of Urgent BusinessIt was agreed this would be heard after Item 10 on the Agenda . | Agreed | Open |
| 8 Aug 2024 | 16/01232/OUT Land for Development, Muckingford Road, LinfordMembers agreed to not defend reason of refusal 8. 2. Members agreed to delegate authority to the Chief Planning Offic... | Agreed | Open |
| 9 Jul 2024 | 24/00111/FUL Teviot AvenueRESOLVED : Application approved, subject to conditions . | Approved | Open |
| 8 Feb 2024 | London Gateway Logistics Park: Consideration of Habitat Regulation Assessment (HRA) for Local Development Order 1.5That the Planning Committee 1.1 Note the content of the “Report to Inform a Habitats Regulations Assessment London Ga... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.