Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
The Council is committed to following best practice guidance to obtain maximum added value for investment in highway asset. Following on from the Local Government Association strategic review which was completed in January 2015 the Council has invested in new software to make better use of its highway asset information sets. The integrated data sets will inform the refresh of Council’s policies which will determine priorities for the 2016-17 Highway Capital Programme.
1. Recommendation(s)
That the Planning, Transport, Regeneration Overview and Scrutiny Committee:
1.1Notes the improvements being made in the Transportation & Highways department to make better use of the available information.
1.2Agrees to receive a report including a draft 2016-17 Highway Capital Programme of capital investment priorities at its January 2016 meeting.
2. Introduction and Background
2.1The Council, as Local Highway Authority, is responsible for maintaining Thurrock’s highway network including:
2.2All of the above are used by Thurrock’s residents, businesses and visitors. As Thurrock grows and evolves it is important to continue to maintain its existing highway asset as well as new infrastructure to accommodate new developments.
2.3As the Local Highway Authority the Council has statutory responsibilities for highway maintenance and the safety of the road users. This includes the obligation to inspect and maintain the highway to a reasonable condition.
2.4Historically, the Council has relied upon its Department for Transport (DfT) capital funding allocation for providing capital improvements to its highway infrastructure. Over the years, funding restrictions have had the effect of increasing the number of reactive repairs putting increasing pressures on existing revenue budgets.
2.5In 2014-15 the Council, in recognition of the infrastructure deficit was able to allocate £10m of capital funding towards reducing this deficit.
2.6The DfT has developed a range of initiatives designed to assist Local Highway Authorities to use best practice measures to maximise the value gained from limited highway maintenance budgets. This includes the establishment of the Highway Maintenance Efficiency Programme (HMEP), geared to sharing best practice and providing support to Local Highway Authorities in improving the efficiency of their operations.
2.7In October 2014, the Council secured the funding support to allow a Local Government Association strategic HMEP review.
2.8The DfT has changed their method of providing highway capital funding. This is now split into three categories. One category is, as before, based on the size and needs of the network. A new category Incentive Funding will be allocated to Local Highway Authorities who can demonstrate compliance with HMEP recommendations and operational standards. The third category is Capital Challenge funding which will be allocated on the basis of competitive maintenance bids. The emphasis on the Incentive Fund and Capital Challenge will increase through the funding period up to 2019. This funding arrangement is intended to incentivise all Local Highway Authorities to embrace evolving best practice. It is recognised that this process will require continual improvements over a number of years. Clearly, it is in Thurrock’s interest to develop working practices to allow us to make best advantage of the new funding arrangements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.