That Cabinet: 1. Approve the carrying out of a procurement process to identify a new MFD provider; 2. On the basis of Option 2 as set out within this report, delegate authority to Director of Planning and Transportation to agree & award a new contract. 3. Authorise the Director of Planning and Transportation to award a contract to a provider for a Discovery Assessment, should it be necessary to contract separately for such an assessment. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
The Council currently has various lease agreements with Canon under a Crown Commercial Services Framework In total 80 devices have been drawn down under this agreement covering 18 council locations. Annual spend for financial year 2014/2015 for Lease and Usage charges was £200k, plus Serco ICT ongoing charges of £16.5k per annum.
A procurement exercise needs to be undertaken to identify a provider to supply the Council with replacement MFD units when the existing units come to the end of their contracted terms. In the case of Print Room devices this is July 2016 and Fleet devices located within office areas from October 2016 onwards.
1. Recommendation(s)
That Cabinet
1.1Approve the carrying out of a procurement process to identify a new MFD provider;
1.2On the basis of Option 2 as set out within this report, delegate authority to Director of Planning and Transportation to agree & award a new contract
1.3Authorise the Director of Planning and Transportation to award a contract to a provider for a Discovery Assessment, should it be necessary to contract separately for such an assessment 2. Introduction and Background
2.1The lease agreements were signed after a procurement exercise to replace traditional printers by centralised MFD devices.
2.2The current agreement with Canon (UK) Ltd covers 80 devices with a combination of models, manufacturers and capabilities.
2.3The leases for the 80 MFD units have a set term of 60 months (5 years), on an individual or group order basis. This means that leases will come to the end of their terms at different times.
3. Issues, Options and Analysis of Options
3.1Option 1: Continue with current solution beyond 5 year terms
Will result in a reduction in the ongoing charges for a short period as the units switch from ‘lease & usage’ charges to just ‘usage’ charges.
Benefit - will create short term cost savings as units come to the end of their initial lease terms.
Risks – increasing reliability issues, spare parts and hardware/software support service level issues as majority of the devices are not Canon units, and the key software application used for follow-me printing is 3rd party
3.2Option 2: Procure new MFD agreement
As part of the reprocurement exercise a Discovery Assessment would be run using external support to evaluate total print requirements existing in the Council and inform the shape of the tender specification for either a mini- tender under framework or full tender exercise.
This assessment may have a cost element depending on the options pursued and level of internal ICT support required. However, it should be noted that many manufacturers provide these assessments for free as part of their business opportunity development activities.
The timing of the replacements programme would start at the end of the original phase 1 period in December 2016; this will have some cost offset through the reduction in the lease charges on the current devices . It should be noted however that a capital cost element will exist for the purchase of additional server capacity during this stage estimated at £16k.
Benefits include Allowing additional sites requirements to be included in the tender specification. Ensuring that MFD units are right-sized to the operational area requirements. i.e. page per minutes, optional features Providing a protected operational position by ensuring continuous print capability at all times during the transition to the new agreement
Risks
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.