That Cabinet agrees: 1. To note that the General Fund capital programme is projected to have unused resources of £20.766m as at 31 March 2016. This funding will be carried forward to 2016/17 to fund schemes currently under development. 2. To note the progress on the schools capital programme including the use of temporary accommodation and the remodelling of school accommodation to meet the increase in demand for pupil places from January 2016. 3. To approve the virements within the Children’s service, totalling £0.2m, which will realign project budgets with projected costs; 4. To note that the Housing Revenue Account capital programme is projected to have no unused resources in 2015/16. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
At its meeting on 11 February 2015, Cabinet agreed the 2015/16 capital programme.
Since the 1st April 2015, additional projects have been added to the programme, along with the associated funding. Budget carry forwards from 2014/15 have also been added to the programme.
This report reflects these changes and sets out the latest forecasted outturn position and a detailed summary of the current position on the school capital programme.
1. Recommendation(s)
That Cabinet agrees:
1.1To note that the General Fund capital programme is projected to have unused resources of £20.766m as at 31 March 2016. This funding will be carried forward to 2016/17 to fund schemes currently under development.
1.2To note the progress on the schools capital programme including the use of temporary accommodation and the remodelling of school accommodation to meet the increase in demand for pupil places from January 2016.
1.3To approve the virements within the Children’s service, totalling £0.2m, which will realign project budgets with projected costs; 1.4 To note that the Housing Revenue Account capital programme is projected to have no unused resources in 2015/16.
2. Introduction and Background
2.1This report provides an update to Cabinet on the financial position of the capital programme and highlights significant variances. It is the first monitoring report for 2015/16 and is based on expenditure to the end of month 6 (1st April to 30th September 2015) and projected expenditure for the remainder of the year.
2.2Capital schemes and resources are identified in two specific categories:
Mainstream schemes – capital expenditure that is funded by supported or unsupported (prudential) borrowing, by capital receipts, from the revenue budget or from earmarked capital reserves.
Specific schemes – capital expenditure that is funded by external funding sources, for example, government grants and Section 106 monies that can only be spent on specific projects.
3. Issues, Options and Analysis of Options
General Fund Schemes
3.1Appendix 1 sets out the capital programme at month 6 showing the movement since the start of the financial year and the resources that are available to finance the programme.
3.2The current position for General Fund schemes for 2015/16 is summarised in Table 1.
Table 1: Capital Programme – Projected Outturn as at Month 6 Latest Projected Variance Agreed Outturn against Budget to budget 31/03/2016 £000’s £000’s £000’s Expenditure: Children’s Service (Note: the schools capital budget is designed around academic years 13,203 11,648 (1,555) and officers are confident that this will be defrayed in full within the current academic year). Adult Social Care 128 128 0 Environment 5,990 4,071 (1,919) Planning and Transportation 14,053 8,319 (5,734) Latest Projected Variance Agreed Outturn against Budget to budget 31/03/2016 £000’s £000’s £000’s Housing General Fund 1,387 1,474 87 Commercial Services 443 443 0 Transformation 8,420 7,340 (1,080) Chief Executive Delivery Unit 21,435 10,870 (10,565)
Total Expenditure 65,059 44,293 (20,766)
Resources: Mainstream (46,409) (25,924) 20,485 Specific (18,650) (18,369) 281
Total Resources (65,059) (44,293) 20,766
Forecast Deficit in Resources 0 0 0
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.