Resolved
That the Planning, Transport, Regeneration Overview and Scrutiny Committee received an update on the roll-out of Thurrock Cycle Infrastructure Programme and provide comments to inform subsequent phases of the programme.
Planning, Transport, Regeneration Overview and Scrutiny Committee decided this item on Tuesday 8 November 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Planning, Transport, Regeneration Overview and Scrutiny Committee received an update on the roll-out of Thurrock Cycle Infrastructure Programme and provide comments to inform subsequent phases of the programme.
In July 2014 Thurrock was awarded £5 million towards cycle route improvements to be delivered across the Borough by 2019. The Council is committed to enhancing Thurrock's cycle network; making it easier and safer to get around the Borough by bike, connecting routes, providing access to key employment and residential centres; offering an attractive alternative to using the car.
This report provides an update on progress with the implementation of the Thurrock Cycle Infrastructure plan since the award of the growth fund monies in April 2016 with the first phase of £1.6m schemes planned of construction in spring and summer of 2017-18.
1. Recommendation(s)
1.1That the Planning, Transport, Regeneration Overview and Scrutiny Committee receive an update on the roll-out of Thurrock Cycle Infrastructure Programme and provide comments to inform subsequent phases of the programme.
2. Introduction and Background
2.1In July 2014, as part of the South East Local Enterprise Partnership’s Growth Deal with government, Thurrock was awarded £5m for delivering of Cycle Infrastructure Projects between 2016 and 2019.
2.2To develop Thurrock routes and to improve access to employment, growth hubs, areas of regeneration and provide sustainable alternative in already congested corridors, the project proposed a network of cycling and walking facilities.
2.3In 2015, a cycle audit was completed across the borough to review existing routes and identify missing links and barriers to cycling, as well as new routes that would lead to increased uptake in cycling. The schemes were prioritised for their potential to bring about modal shift in more congested areas, particularly on the home to work or school journey and focussed in areas where access to housing, jobs and future growth is vitally important.
2.4The results of this audit fed into the production of a Cycle Infrastructure Delivery Plan (referred to hereafter as cycle plan) to support the business case for economic growth in the borough. The cycle plan identified a rational network of cycle routes, incorporating existing facilities alongside potential routes from known popular origins and destinations.
2.5Each scheme was scored against a matrix to understand the maximum benefits that each measure could achieve. The scoring matrix consisted of a number of factors such as scheme cost, safety benefit, access to facilities and deliverability etc. Thus, more than 35km of new and improved cycle facilities have been identified across the borough including a total of 46 missing links and opportunities.
3. Issues, Options and Analysis of Options
3.1Since award of funding in 2014, a procurement exercise was undertaken to appoint specialist consultants to undertake a feasibility assessment and subsequent detailed designs of the chosen schemes. Feasibility designs and outline costings have been completed and the scheme was broken down into 3 tranches.
3.2As endorsed by January 2016 Cabinet (Decision 01104343), the final business case was submitted to the South East Local Enterprise Partnership’s Accountability Board which was followed by a programme entry funding allocation in April 2016 of £5m with £1.6m for tranche 1 implementation commencing in early 2017.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cycling Infrastructure Plan UpdateReport | 71 KB | DownloadRead as text |
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Feb 2024 | ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... | Agreed | Open |
| 21 Feb 2024 | Tilbury and Grays Towns Fund Update - to follow1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbu... | Decided | Open |
| 21 Feb 2024 | Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... | Decided | Open |
| 17 Oct 2023 | Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... | Decided | Open |
| 17 Oct 2023 | East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.