Planning, Transport, Regeneration Overview and Scrutiny Committee noted this item on Thursday 5 January 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED 1. That Planning Transport Regeneration Overview and Scrutiny Committee noted the revised fees and charges proposed including those no longer applicable. 2. That Planning Transport Regeneration Overview and Scrutiny Committee comment on the proposals currently being considered within the remit of this committee . Laura Last left the committee room at 8.15 pm.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
Local Authorities are involved in a wide range of services and the ability to charge for some of these services has always been a key funding source to Councils.
This report specifically sets out the charges in relation to services within the remit of this Overview and Scrutiny Committee. Charges will take effect from the 1 April 2017 unless otherwise stated.
In preparing the proposed fees and charges, Directorates have worked within the charging framework and principles set out in the report.
The full list of proposed charges is detailed in Appendix 1 to this report.
The proposed deletion of current fees and charges are detailed in Appendix 2 to this report.
Recommendations
1.1That Planning, Transport, Regeneration Overview and Scrutiny Committee note the revised fees and charges proposals including those no longer applicable
1.2That Planning, Transport, Regeneration Overview and Scrutiny Committee comment on the proposals currently being considered within the remit of this committee 2. Background
2.1The paper describes the fees and charges approach for the services within the Planning, Transport, Regeneration Scrutiny Committee remit for 2017/18 and will set a platform for certain pricing principles moving forward into future financial years.
2.2The paper provides narrative for the following areas:
Parking Highways Maintenance and Permitting Development Control Building Control Land Charges
2.3The fees & charges that are proposed are underpinned in some instances by a detailed sales and marketing plans for each area. This will ensure delivery of the income targets for 2017/8, for ease these are summarised below
Service: £000’s Actual 15/16 Budget 16/17 Budget 17/18
Parking 789 952 980 Highways Maintenance 119 192 197 Highways and Transportation Other 33 126 129 Development Control 960 896 923 Building Control 285 266 273 Land Charges 301 195 201 Commercial Hall Hire 24 22 23 TOTAL 2,511 2,649 2,726
3. Thurrock Charging Policy
3.1The strategic ambition for Thurrock is to adopt a policy on fees and charges that is aligned to the wider commercial strategy and ensures that all discretionary services cost recover.
3.2Furthermore, for future years, while reviewing charges, services will also consider the level of demand for the service, the market dynamics and how the charging policy helps to meet other service objectives.
3.3When considering the pricing strategy for 2017/18 some key questions were considered.
• Where can we apply a tiered/premium pricing structure • How sensitive are customers to price (are there areas where a price freeze is relevant ) • What new charges might we want to introduce for this financial year • How do our charges compare with neighbouring boroughs • How do our charges compare to neighbouring boroughs and private sector competitors (particularly in those instances where customers have choice) • How can we influence channel shift • Can we set charges to recover costs • What do our competitors charges • How sensitive is demand to price • Statutory services may have discretionary elements that we can influence • Do we take deposits, charge cancellation fees, charge an admin fee for duplicate services (e.g. lost certificates.)
4. Proposals and Issues
4.1The fees and charges for each service area have been considered and the main considerations are set out below.
4.2A council wide target of £0.350m has been proposed within the MTFS for additional income generation in respect of fees and charges income for 2017/18.
5. Parking
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.