Purfleet Centre Update

Decided Planning 3 papers

Planning, Transport, Regeneration Overview and Scrutiny Committee decided this item on Tuesday 16 January 2018. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

Members of Planning, Transport, Regeneration Overview and Scrutiny Committee were asked to comment on the recommendations to be ... view the full minutes text for item 28.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Planning, Transport, Regeneration Overview and Scrutiny Committee

Executive summary

The Purfleet Regeneration programme has been the subject of a number of Cabinet decisions since 2011. With the recent submission of the outline planning application for the masterplan the project is now moving into the delivery stage. This positive forward step has triggered the need for a new set of approvals to ensure that delivery can be progressed with the development partner Purfleet Centre Regeneration Ltd (“PCRL”) and that the Council is in a position to fulfil its obligations under the Development Agreement (the DA)

This report highlights recent progress on the project and considers the next steps required. Under the terms of the DA the Council is responsible for leading on the land assembly to secure the site for redevelopment. Considerable focus is therefore given to the Compulsory Purchase Order (CPO) process as this is a significant decision for the Council to make. Using CPO powers should not be taken lightly but in this scheme it is likely that use of the powers will be required to complete the land assembly process and at this stage it is thought that a compelling case in the public interest can be made. Cabinet will be asked to resolve as a matter of principle that the Council is prepared to use its CPO powers on the basis that more detailed reports will come forward at a later date when approval to make the order is required and further work on the relevant documentation has been completed. In the meantime the Council will continue to progress negotiations to secure remaining land parcels by private treaty.

The report also describes the good progress being made on securing an Integrated Medical Centre as part of the scheme and on wider project decisions that will be forthcoming in the coming months. 1. Recommendation(s).

1.1Members of Overview and Scrutiny committee are asked to comment on the recommendations to be presented to Cabinet (below) and give their thoughts on the use of Compulsory Purchase Powers to secure the delivery of this significant regeneration scheme.

1.2Cabinet will be asked to:

a) note progress on the Purfleet Centre Project;

b) agree these recommendations on the basis that a full Compulsory Purchase Order (CPO) can only be made by Cabinet at a future Cabinet meeting.

c) resolve as a matter of principle, that the Council is prepared to use its compulsory purchase powers pursuant to section 226(1)(a) of the Town and Country Planning Act 1990 to acquire land to deliver the comprehensive regeneration of Purfleet Centre;

d) note that the regeneration team is progressing negotiations to acquire the land and interests required by private treaty and to delegate authority to the Corporate Director, Place in consultation with the Portfolio Holder for Regeneration to approve and enter into agreements with the owners and/or occupiers of the land so as to facilitate its acquisition;

e) note the progress on the land referencing exercise and, if required, delegate authority to the Corporate Director, Place in consultation with the Portfolio Holder for Regeneration and Assistant Director of Law and Governance to issue requisitions for information pursuant to section 5A of the Acquisition of Land Act 1981 to persons who have a potential legal interest in or who occupy the area in respect of which compulsory purchase powers are proposed to be used;

f) authorise the regeneration team under the direction of the Corporate Director, Place to undertake the work needed to prepare for the making of a possible Compulsory Purchase Order(s)(CPO) together with the associated documentation;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site Location PlanAppendix 1 3.2 MB Download
PDF
Description of DevelopmentAppendix 2 43 KB Download
PDF
Purfleet Centre UpdateReport 141 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 8 attended
BR
Councillor Barbara RiceChair, apologies
JA
Councillor John AllenVice-Chair, in the Chair, present
OG
Councillor Oliver GerrishCommittee Member, present
TK
Councillor Tom KellyCommittee Member, present
TP
Councillor Terry PiccoloCommittee Member, apologies
PS
Councillor Peter SmithCommittee Member, present
ST
Stephen TaylorOfficer, in attendance
RE
Rebecca EllsmoreOfficer, in attendance

On this subject at Thurrock

Search all
  1. Purfleet Centre UpdateThis decision
  2. Purfleet Centre Regeneration (Decision: 110542)Noted
  3. Purfleet Centre RegenerationNoted
  4. Purfleet Centre Regeneration (Decision: 110525)Approved
  5. Purfleet Centre Update (Decision 0110468)Noted
  6. Purfleet Centre Regeneration Programme (Decision: 01104348)Noted

More from Thurrock Planning, Transport, Regeneration Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Feb 2024 ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... Agreed Open
21 Feb 2024 Tilbury and Grays Towns Fund Update - to follow1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbu... Decided Open
21 Feb 2024 Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... Decided Open
17 Oct 2023 Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... Decided Open
17 Oct 2023 East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies