Gas Servicing, Repair and Renewal (Decision 110474)

Approved Executive 1 paper

Cabinet approved this item on Wednesday 11 July 2018. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

RESOLVED that Cabinet: 1. Approved the process set out in the report to commence the procurement of a combined domestic and commercial gas servicing, breakdown, repair and installation contract for a period of three years with the option to extend for a further two years in any period combination. 2. Agreed delegated authority for the award of the contract to the Corporate Director of Adults, Housing and Health in consultation with the Portfolio Holder for Housing. Reason for Decision – as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Executive summary

This report sets out the proposals for the procurement of both the domestic and commercial gas servicing, breakdown & repair and new installation contracts which are due to expire on the 31 March 2019. As a landlord we have a statutory obligation to ensure each domestic and commercial dwelling has a safe gas supply and therefore, we carry out an annual gas safety check of every relevant property.

We are proposing to amalgamate the two contracts into one contract with a single contractor maintaining the whole of the council’s stock. This is to ensure continuity of the management of the contracts and obtain the best possible value for money for our residents.

1. Recommendation(s)

Cabinet is recommended to:

1.1Approve the process set out in this report to commence procurement of a combined domestic and commercial gas servicing, breakdown, repair and installation contract for a period of three (3) years with the option to extend for a further two (2) years in any period combination,

1.2Agree delegated authority for the award of the contract to the Corporate Director of Adults, Housing and Health in consultation with the Portfolio Holder for Housing. 2. Introduction and Background

2.1The current domestic gas contract is based on a price per property for the annual servicing and repair of approximately 8,700 council owned properties with three levels of priority based on severity of problem and vulnerability of the dwelling occupants. The current contract is approximately £1.3m per year comprising £915k servicing and included repairs, £57k excluded repairs and £330k installation of new boiler and central heating systems.

2.2The price per property contract covers general operating components of the boiler, however, more serious repairs fall outside of the price per property scope and are classified as exclusions. These items are carried out under fixed rates contained within the contract.

2.3The current contract is a 3 year fixed term with the option to extend for a further 2 years, the original commencement date of the contract was 1 April 2015.

2.4Commercial gas servicing and repair services are currently split into two elements, and includes Council buildings across the borough, including the Civic Offices and Thameside Complex. Officers consider that this much smaller element, valued at c. £25k per annum would be more effectively delivered as part of a “one stop shop” for gas services, and therefore the contract will be combined with the domestic component.

2.5In accordance with the terms of the original contract, a twelve month extension was awarded to our incumbent contractors which took effect from the 1 April 2018. This twelve month extension was awarded to allow the Council to undertake a procurement exercise for the tendering and award of a new domestic and commercial gas services and repairs contract. The planned commencement of the new contract will be the 1 April 2019.

3. Issues, Options and Analysis of Options

3.1The harsh winter weather resulted in an overload on all gas servicing contractors but it highlighted a number of concerns with the council’s current contractor. These included difficulty contacting them through their call centre, failings in completing repair works on first visit and missing agreed response times. Members have reported that their constituents have experienced poor levels of service and although any cases where the contractor has failed to undertake the work properly are promptly addressed the retendering of the gas contract will give us an opportunity to build in higher quality standards and greater penalties for poor performance in future.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gas Servicing, Repair and Renewal (Decision 110474)Decisions 73 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
RG
Councillor Rob GledhillChair, present
SH
Councillor Shane HebbDeputy Chair, present
GC
Councillor Gary CollinsCommittee Member, present
MC
Councillor Mark CoxshallCommittee Member, present
JH
Councillor James HaldenCommittee Member, present
DH
Councillor Deborah HuelinCommittee Member, present
BJ
Councillor Barry JohnsonCommittee Member, present
SL
Councillor Susan LittleCommittee Member, apologies
AW
Councillor Aaron WatkinsCommittee Member, present
LC
Lyn CarpenterOfficer, in attendance
SC
Steve CoxOfficer, in attendance

On this subject at Thurrock

Search all
  1. Gas Servicing, Repair and Renewal (Decision 110474)This decision
  2. Procurement and Award of Contract for Gas Servicing, Breakdown and Repair for HousingApproved
  3. Gas Servicing, Repair and RenewalDecided

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open