RESOLVED that Cabinet: 1. Approved the process set out in the report to commence the procurement of a combined domestic and commercial gas servicing, breakdown, repair and installation contract for a period of three years with the option to extend for a further two years in any period combination. 2. Agreed delegated authority for the award of the contract to the Corporate Director of Adults, Housing and Health in consultation with the Portfolio Holder for Housing. Reason for Decision – as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report sets out the proposals for the procurement of both the domestic and commercial gas servicing, breakdown & repair and new installation contracts which are due to expire on the 31 March 2019. As a landlord we have a statutory obligation to ensure each domestic and commercial dwelling has a safe gas supply and therefore, we carry out an annual gas safety check of every relevant property.
We are proposing to amalgamate the two contracts into one contract with a single contractor maintaining the whole of the council’s stock. This is to ensure continuity of the management of the contracts and obtain the best possible value for money for our residents.
1. Recommendation(s)
Cabinet is recommended to:
1.1Approve the process set out in this report to commence procurement of a combined domestic and commercial gas servicing, breakdown, repair and installation contract for a period of three (3) years with the option to extend for a further two (2) years in any period combination,
1.2Agree delegated authority for the award of the contract to the Corporate Director of Adults, Housing and Health in consultation with the Portfolio Holder for Housing. 2. Introduction and Background
2.1The current domestic gas contract is based on a price per property for the annual servicing and repair of approximately 8,700 council owned properties with three levels of priority based on severity of problem and vulnerability of the dwelling occupants. The current contract is approximately £1.3m per year comprising £915k servicing and included repairs, £57k excluded repairs and £330k installation of new boiler and central heating systems.
2.2The price per property contract covers general operating components of the boiler, however, more serious repairs fall outside of the price per property scope and are classified as exclusions. These items are carried out under fixed rates contained within the contract.
2.3The current contract is a 3 year fixed term with the option to extend for a further 2 years, the original commencement date of the contract was 1 April 2015.
2.4Commercial gas servicing and repair services are currently split into two elements, and includes Council buildings across the borough, including the Civic Offices and Thameside Complex. Officers consider that this much smaller element, valued at c. £25k per annum would be more effectively delivered as part of a “one stop shop” for gas services, and therefore the contract will be combined with the domestic component.
2.5In accordance with the terms of the original contract, a twelve month extension was awarded to our incumbent contractors which took effect from the 1 April 2018. This twelve month extension was awarded to allow the Council to undertake a procurement exercise for the tendering and award of a new domestic and commercial gas services and repairs contract. The planned commencement of the new contract will be the 1 April 2019.
3. Issues, Options and Analysis of Options
3.1The harsh winter weather resulted in an overload on all gas servicing contractors but it highlighted a number of concerns with the council’s current contractor. These included difficulty contacting them through their call centre, failings in completing repair works on first visit and missing agreed response times. Members have reported that their constituents have experienced poor levels of service and although any cases where the contractor has failed to undertake the work properly are promptly addressed the retendering of the gas contract will give us an opportunity to build in higher quality standards and greater penalties for poor performance in future.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.