Resolved
That Cabinet: 1. Approved the procurement proposal for a new bus shelter contract. 2. Granted delegated authority for award of contract to the Director of Environment and Highways, in conjunction with the Portfolio Holder.
Cabinet approved this item on Wednesday 10 October 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet: 1. Approved the procurement proposal for a new bus shelter contract. 2. Granted delegated authority for award of contract to the Director of Environment and Highways, in conjunction with the Portfolio Holder.
The Council’s current agreement for Bus Shelters is reaching end of life. The existing contract was originally for a term of 15 years, with the option to extend for up to 5 years; of which 2+2 years of extension have been agreed bringing the contract expiration to the 30 June 2019.
As such, the Council needs to undertake a procurement exercise to source a new provider of Bus Shelter units including maintenance and cleaning; as the majority of the existing Bus Shelter units are owned by the current provider and in principle would be removed post contract expiration.
Funding for this procurement has already been agreed under the capital budgets approved at February Council 2018, item 129 General Fund Budget Proposal.
1 Recommendation(s)
1.1That Cabinet approves the procurement proposal for a new Bus Shelter contract.
1.2That Cabinet grants delegated authority for award of contract to the Director of Environment and Highways in conjunction with the portfolio holder. 2. Introduction and Background
2.1The current agreement for Bus Shelters and associated advertising is reaching end of life. This contract was originally signed for a 15 year term. With the option for up to 5 years extension, 2 years plus 2 years have been agreed, thus bringing the contract expiration to 30 June 2019 with further 1 year extension option acting as a contingency.
2.2Under this agreement the existing provider owns 147 of the 170 shelters, and performs all cleaning and maintenance works on all 170 shelters; in return they also manage all advertising and retain all income from advertising. The nature of the current agreement does not allow the information on advertising revenue to be shared with the Council; therefore all future projections are best estimates based on general market knowledge.
2.3Soft-market testing with main industry players and bus shelter manufacturers’ in 2017 highlighted a lack of industry appetite for providing capital funding as part of a commercial agreement. Therefore, capital funding was applied for and agreed by Full Council February 2018 for replacement of the existing Bus Shelters.
2.4As such, in working with Communications and Passenger Transport services, the approach taken has been to split this into 2 procurement streams:
- Bus Shelters including maintenance and cleaning - Advertising
2.5It should be noted that the Passenger Transport Team has no revenue funding for the maintenance of bus shelters; and that income from advertising would be used to fund this activity.
2.6Of the current shelters, 50 have operational Real Time Information (RTI) displays for bus arrivals, of which 9 are the newer TFT display type and 41 are the traditional 3 line dot-matrix style. These are normally on locations which also support advertising; with these shelters being owned by the existing provider.
3. Issues, Options and Analysis of Options
3.1Option 1 – Purchase existing shelters
3.1.1. Under the existing agreement, the Council could seek to acquire the existing shelter assets from the incumbent provider; but the incumbent could remove them for use on other contracts or for spare parts, and has taken this approach with other councils.
3.1.2 The acquisition option was discussed with the incumbent in Q1/17 who indicated an asset valuation of circa £3k per location – c. £440K in total. This does not correctly reflect the assets’ ages, conditions or depreciated values, or costs for the incumbent to remove and make good the locations.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Bus Shelter Procurement (Decision 110481)Decisions | 83 KB | DownloadRead as text |
Follow Cabinet at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... | Noted | Open |
| 16 Sep 2026 | Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... | Approved | Open |
| 16 Sep 2026 | Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... | Approved | Open |
| 16 Sep 2026 | High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... | Agreed | Open |
| 16 Sep 2026 | Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.