Planning, Transport, Regeneration Overview and Scrutiny Committee decided this item on Tuesday 11 September 2018. Below is the council's own wording, with the papers it was decided on.
RESOLVED The Planning, Transport and Regeneration Overview and Scrutiny Committee notes the procurement of a new bus shelter contract. The Planning, Transport and Regeneration Overview and Scrutiny Committee notes delegated authority to award a contract will be sought from cabinet.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
The Councils current agreement for Bus Shelters is reaching end of life. The existing contract was originally for a term of 15 years, with the option to extend for up to 5 years; of which 2+2 years of extension have been agreed bringing the contract expiration to the 30th June 2019.
As such, the council needs to undertake a procurement exercise to source a new provider of Bus Shelter units including maintenance and cleaning; as the majority of the existing Bus Shelter units are owned by the current provider and in principal would be removed post contract expiration.
Funding for this procurement has already been agreed under the capital budgets approved at February Council 2018.
1 Recommendation(s)
1.1The Planning, Transport and Regeneration - Overview and Scrutiny Committee notes the procurement of a new Bus Shelter contract
1.2That Planning, Transport and Regeneration - Overview and Scrutiny Committee notes delegated authority to award contract will be sought from Cabinet. 2. Introduction and Background
2.1The current agreement for Bus Shelters and associated advertising is reaching end of life. This contract was originally signed for a 15 year term. With the option for up to 5 years extension, of which 2 years plus 2 years have been agreed bringing the contract expiration to 30th June 2019.
2.2Under this agreement the existing provider owns 147 of the 170 shelters, and performs all cleaning and maintenance works on all 170 shelters; in return they also manage all advertising and retain all income from advertising.
2.3Soft-market testing with main industry players and bus shelter manufacturers’ in 2017 highlighted a lack of industry appetite for providing capital funding as part of a commercial agreement. Therefore, capital funding was applied for and agreed by Full Council February 2018 for replacement of the existing Bus Shelters.
2.4As such, in working with Communications and Passenger Transport services, the approach taken has been to split this into 2 procurement streams: - Bus Shelters including maintenance and cleaning - Advertising
2.5It should be noted that the Passenger Transport Team has no revenue funding for the maintenance of bus shelters; and that income from advertising would be used to fund this activity.
2.6Of these shelters, 50 have operational Real Time Information (RTI) displays for bus arrivals, of which 9 are the newer TFT display type and 41 are the traditional 3 line dot-matrix style. These are normally on locations which also support advertising; with these shelters being owned by the existing provider.
3. Issues, Options and Analysis of Options
3.1Option 1 – Purchase existing shelters
3.1.1. Under the existing agreement, the Council could seek to acquire the existing shelter assets from the existing provider; but that in principal the incumbent could remove them for use on other contracts or for spare parts.
3.1.2 Under the existing agreement, the incumbent would be responsible for all removal costs and making good the areas when they remove their shelters. It should be noted that the current contract requires the incumbent to agree a removal plan with the Council upon contract termination over a period up to 24 months.
3.1.3 The acquisition option was discussed with the incumbent in Q1/17 who indicated an asset valuation of circa £3k per location to transfer the existing assets to council ownership. This does not correctly reflect the assets ages, conditions, depreciated values or costs for incumbent to remove and make good the locations. This would mean that the council would require circa £440k just retaining the existing legacy assets.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.