That Cabinet: 1. Agreed to progress the re-procurement of a four-year Agency Staff Contract using the ESPO MSTAR3 Framework with a new contract to commence on 15 December 2019 2. Approved the delegation to award to the Director of HR, OD & Transformation in consultation with the Portfolio Holder in order to ensure maximum lead in time for service transfer as necessary Reason for decision – as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report sets out the options around, and recommendations for, the rprocurement of the Temporary (Agency) Worker Contract.
The current contract with Matrix SCM expires on 15 December 2019 and therefore the Council needs to ensure there is a new arrangement in place by this date to ensure that suitable quality and cost effective provision can be made for contingent labour needs where this applies.
The performance of the current contract has been good and has provided consistent pricing, notable savings and helpful management information; demonstrating performance and compliance across all Council directorates.
The current service model of “neutral vendor” provides the best mix of cost certainty, ability to include local agencies and tier specialist providers for hard to recruit positions. The most suitable model will be chosen by the project group that is established as part of this re-procurement exercise.
The value and nature of this contract requires full compliance with EU Procurement Directives which therefore impacts on process and timescale for re-procurement. As set out in the report, it is therefore proposed that the Cabinet agrees that officers progress a mini competition through the ESPO (Eastern Shires Purchasing Organisation) framework MSTAR3. 1. Recommendation(s):
1.1Agree to progress the re-procurement of a four year Agency Staff Contract using the ESPO MSTAR3 Framework with a new contract to commence on 15 December 2019.
1.2Approve delegation to award to the Director of HR, OD & Transformation in consultation with the Portfolio holder in order to ensure maximum lead in time for service transfer as necessary.
2. Introduction and Background
2.1The Council currently contracts with Matrix SCM “the Managed Service Provider” for the supply of contingent labour which expires on 15 December 2019. The contract will have been in place for four years and was awarded following a mini-competition undertaken through the Eastern Shires Purchasing Organisation (ESPO).
2.2Provision of cost and quality effective contingent labour from recruitment agencies are key to effective use of resources for Thurrock alongside the mix of permanent and contracted staff.
2.3The current arrangement cannot be extended further and therefore it is necessary to embark on a re-commissioning exercise to put in place a new contract for December 2019.
2.4Whilst agency spend overall remains significant, latest spend figures indicate a steady reduction in the use of agency staff. Total spend for July to September 2018 was £2,259,609 which amounts to a decrease from the previous quarter of £47,010 and a reduction to the same quarter in the previous year of £120,179. Annual spend is currently in excess of £9 Million.
2.5The majority of cost to provision of Agency Workers is the direct pay and on costs element (National Insurance, holiday pay and pension), with the Managed Service Provider, Agency Profit and Overheads and ESPO framework charge amounting to approximately 7% of the total spend each financial year.
2.6The use of Agency Workers has decreased due to efforts being made to control and reduce the usage through permanent recruitment and the provision of internal bank staff arrangements. However, there will still be a need for an agency arrangement to meet peaks and troughs in demand as well as for time limited projects where it is not possible to secure staff through a fixed term contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.