Housing Overview and Scrutiny Committee, Tuesday 11 February 2020 at 7.00pm

Procurement of Housing Capital Programme Delivery

Noted Scrutiny 1 paper

Housing Overview and Scrutiny Committee noted this item on Tuesday 11 February 2020. Below is the council's own wording, with the papers it was decided on.

Item32

Resolved

RESOLVED the Housing Overview and Scrutiny Members were requested to note and comment upon: 1. The procurement of two major works contract packages for the delivery of the Housing Capital work programme as set out in the report 2. The procurement of two contract packages to provide strategic support and cost management of the Housing Capital Programme as set out in the report 3. Authority being delegated for the awarding of the above contracts to the Corporate Director of Adults, Housing and Health in consultation with the Portfolio Holder for Housing.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Housing Overview and Scrutiny Committee

Executive summary

This report sets out the proposals for the procurement and contract packages to ensure the successful delivery of the Housing Capital Programme from 2020/21 to 2025/26.

The Housing Capital Programme invests to secure the long-term integrity of the Council’s asset and brings significant improvements to the health and wellbeing of our local residents through improvement to their living conditions and provision of employment opportunities.

The key priorities for the Housing Capital Programme for next 5 years are the continuation of the property refurbishment through the Transforming Homes programme and the external refurbishment of 9 tower blocks in Grays.

This report details options for the procurement of these contract packages using pre- approved public sector frameworks in order to generate cost efficiency and resource time savings.

1. Recommendation(s)

Housing Overview and Scrutiny members are requested to note and comment upon:

1.1The procurement of two major works contract packages for the delivery of the Housing Capital work programme as set out in the report 1.2 The procurement of two contract packages to provide strategic support and cost management of the Housing Capital Programme as set out in the report

1.3Authority being delegated for the awarding of the above contracts to the Corporate Director of Adults, Housing and Health in consultation with the Portfolio Holder for Housing.

2. Introduction and Background

2.1There is an ongoing need to invest in our existing council stock to ensure the integrity of the asset is maintained and that the Council fulfils its duty to provide residents with warm homes with modern facilities.

Transforming Homes

2.2The Transforming Homes programme has been delivering a comprehensive internal and external refurbishment programme now for 7 years. Significant success has been achieved in the delivery this programme, both in the improvements made to living conditions for council tenants and through the added value these contracts have bought to the local economy.

2.3The priority works packages for the programme have been informed by the stock condition data held by the council which was refreshed with the stock condition survey undertaken in 2017.

2.4Currently both the refurbishment and cost management contracts for this programme were awarded on the basis of two years plus one year extension, by way of a mini-competition for commencement in July 2018 using pre- approved public sector frameworks.

 PS/2017/524 – Transforming Homes Refurbishments  PS/2017/523 – Transforming Homes Cost Consultancy

2.5The current contracts have a total value of £35.78m over the 3 year period. They are delivering well and meeting KPI targets. However they will expire in June 2021 and therefore to ensure continuity of programme, a re-procurement exercise needs to take place.

2.6Headline achievements to date include:

 8734 properties benefitting so far from the programme  51% of the construction value is spent in the local economy  45% of the local delivery team are Thurrock residents  50% of the supply chain is registered in Thurrock

2.7Customer satisfaction with the current programme delivery arrangements has been consistently above the target of 85%. Transforming Homes Satisfaction Summary 2019/20

Excellent Good Fair Poor Terrible

Satisfaction Rating

86.90%

Recent Customer Feedback Examples:

The bathroom is ten times better now than what we had previously. We were kept informed every step of the way – Resident in South Ockendon

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Housing Capital Programme DeliveryReport 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
LW
Councillor Lynn WorrallChair, present
CB
Councillor Chris BakerVice-Chair, present
QA
Councillor Qaisar AbbasCommittee Member, present
CC
Councillor Colin ChurchmanCommittee Member, present
JH
Councillor James HaldenCommittee Member, apologies, sent representative
JR
Councillor Joycelyn RedsellCommittee Member, present
TP
Councillor Terry PiccoloSubstitute, present as substitute
LM
Lynn Mansfield, Housing Tenant RepresentativeCo-Optee, in attendance
CH
Carol HinvestOfficer, in attendance
KH
Kenna-Victoria HealeyOfficer, in attendance

On this subject at Thurrock

Search all
  1. Procurement of Housing Capital Programme DeliveryThis decision
  2. Housing Works Procurement Delivery ModelAgreed
  3. Housing Works Procurement Delivery ModelApproved
  4. Procurement and Award of Contract for Gas Servicing, Breakdown and Repair for HousingApproved
  5. Update on Procurement of Strategic Delivery Partner for Housing WorksNoted
  6. Update on Procurement of Strategic Delivery Partner for Housing WorksNoted

More from Thurrock Housing Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
5 Mar 2024 Findings of Stock Condition Survey of Housing PortfolioThe Housing Overview and Scrutiny Committee reviewed and provided comment and challenge as above with regard to; i.) ... Decided Open
5 Mar 2024 Update on Procurement of Strategic Delivery Partner for Housing Works1.1 Members noted the contents of the report. Noted Open
5 Mar 2024 Housing Revenue Account Review - to follow1.1 Members noted the contents of this report. Noted Open
5 Mar 2024 Teviot Avenue Nos - 158 - 228 (evens) - Demolition and Redevelopment - to followThe Committee commented above on the following: 1.1 The proposed site area for the redevelopment of numbers 158 – 228... Decided Open
15 Feb 2024 Update on Procurement of Strategic Delivery Partner for Housing Works1.1 Members are requested to note and comment on the contents of this report. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies