Thurrock Council
Cabinet, Wednesday 7 May 2025 at 7.00pm

Housing Works Procurement Delivery Model

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 7 May 2025. Below is the council's own wording, with the papers it was decided on.

Item187

Resolved

Cabinet agreed to: 2.1 Abandon the previous procurement exercise started in January 2024. 2.2 Approve the commencement of procurement for: 2.2.1 A single main contractor for all reactive repairs, planned maintenance, voids works and major building works via an open market tender invitation or via a specialist framework. 2.2.2 If 2.2.1 is agreed that there is delegated authority for the award of contract for the single main contractor for a period five years (with an option to extend for a further five years) to the Executive Director of Place in consultation with the Leader, Portfolio Holder, Commissioners and Section 151 Officer. The option to exercise the extension of the contract for a further five years will be brought back to Cabinet for Approval. 2.2.3 Eight specialist contractors for the delivery of compliance related services for up to three years for each contractor with the option to extend a further two years. 2.2.4 If 2.2.3 is agreed delegated authority for the award of contracts for the delivery of compliance related services for a period of up to three years per contractor, with the option to extend for a further two years to the Executive Director of Place in consultation with the Leader, Portfolio Holder, Commissioners and Section 151 Officer. 2.2.5 A single specialist contractor for delivery of mechanical and electrical services and works for a period of five years with an option to extend by a further five years subject to performance and Council’s financial position. 2.2.6 If 2.2.5 is agreed delegate authority for the award of contracts for the delivery of mechanical and electrical works and services for a period of up to five years with an option to extend a further five years to the Executive Director of Place in consultation with the Leader, Portfolio Holder, Commissioners and Section 151 Officer. The option to exercise the extension of the contract for a further five years will be brought back to Cabinet for Approval. 2.2.7 A single specialist contractor for delivery of lift maintenance breakdown and renewal for a period of three years with an option to extend by a further two years subject to performance and Council’s financial position. The option to exercise the extension of the contract for a further two years will be brought back to Cabinet for Approval. 2.2.8 If 2.2.7 is agreed to delegate authority for the award of contracts for the delivery of lift maintenance breakdown and renewal for a period of three ... view the full minutes text for item 187.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Report to Cabinet Report Title Housing Works Procurement Delivery Model

Date of Meeting 7th May 2025

Report Author Mohammed Saheed Ullah, Head of Assets Repair & Compliance

Corporate Director Claire Demmel Executive Director Place

Lead Cabinet Member(s) Cllr Mark Hooper, Cabinet member for Health and Well-being & Housing Wards Affected (All Wards);

Identify exempt Choose an item. information and exemption category

Appendices (if any) None

1. Executive Summary 1.1 The Council currently has over thirty contracts for the delivery of housing repairs, planned maintenance, compliance works and major capital works to its Housing Revenue Account estate. These contracts are due for re- procurement within the next 18-24 months. 1.2 The Council embarked on a procurement exercise to streamline this position and establish a single strategic delivery partner in January 2024. This procurement was paused in June 2024 due to concerns associated with the Council committing to a single supplier, the term of the contract, the value of the proposed contract and the limited number of final bids submitted in response to the tender invitation.

1.3This report sets out the recommendation to abandon the previous procurement exercise and commence with a new procurement exercise with a new approach to procure a range of contractors to address the concerns identified with the previous exercise.

2. Recommendations For the reasons set out in this report, the Committee is recommended to: 2.1 Abandon the previous procurement exercise started in January 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Works Procurement Delivery ModelReport 175 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 19 attended
JK
Councillor John KentChair, present
LW
Councillor Lynn WorrallVice-Chair, present
VH
Councillor Vikki HartsteanCommittee Member, present
VH
Councillor Victoria HollowayCommittee Member, present
MH
Councillor Mark HooperCommittee Member, present
VM
Councillor Valerie Morris-CookCommittee Member, apologies
SM
Councillor Sara MuldowneyCommittee Member, present
LW
Councillor Lee WatsonCommittee Member, present
AB
Ashley BaldwinOfficer, in attendance
DC
Dawn CalvertOfficer, in attendance
CD
Claire DemmelOfficer, in attendance
MD
Michael DineenOfficer, in attendance

All 19 on the meeting page

On this subject at Thurrock

Search all
  1. Housing Works Procurement Delivery ModelThis decision
  2. Housing Works Procurement Delivery ModelApproved
  3. Update on Procurement of Strategic Delivery Partner for Housing WorksNoted
  4. Update on Procurement of Strategic Delivery Partner for Housing WorksNoted
  5. Update on Procurement of Strategic Delivery Partner for Housing WorksNoted
  6. Update on Procurement of Strategic Delivery Partner for Housing WorksNoted

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies