That Cabinet: 1. Approved the procurement of a single contract over a maximum period of 15 years. The initial contract period will be 10 years with an option to extend for one further period of 5 years (10+5). 2. Approved the creation of a policy to inform the roll out of the charging infrastructure, ... view the full minutes text for item 89.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Thurrock has one of the most significant growth-led regeneration agendas in the country. It is vital to ensure future growth is supported by the right transport infrastructure, providing sustainable travel options for our communities and businesses whilst addressing climate change, reducing congestion and improving air quality.
This report sets out the proposals for the provision of Electric Vehicle (EV) charging facilities, both off-street and on-street provision within Council owned assets and on the adopted highway.
The report identifies the budget requirement and the procurement options for the Council and sets out a recommended approach to secure the installation and expansion of EV charging infrastructure up to 2035.
Recommendations
That Cabinet approve the following recommendations:
1.1Approve the procurement of a single contract over a maximum period 15 years. The initial contract period will be 10 years with an option to extend for one further period of 5 years (10+5);
1.2Approve the creation of a policy to inform the roll out of the charging infrastructure, based upon a demand led approach for on-street and off- street parking provision and the upgrade/expansion of existing Council assets and in town centre locations and transport hubs; 1.3 Approve the budget and contract value for the full 15 year period to the value of up to £9m based on the following income areas:
a. Allocation of budget on the DfT Integrated Transport Block funding of minimum £75,000 per annum (total allocation over 15 year project life is estimated at being a minimum of £1.125m); b. Contributions secured pursuant to Section 106 of the T&CPA1990 (based on Local Plan projections for infrastructure improvements), and; c. Office for Low Emission Vehicle (OLEV) grant funding of up to 75% of the capital costs for installation of EV facilities.
1.4Approve the approach to delegated authority for awarding contract(s) to the Director of Place in consultation with the Portfolio Holder for Highways and Transport.
2.0Introduction and Background
2.1At present there are only 3 EV charging points (which are located in Grays and South Ockendon) and the Council does not have an established provider of charging points. The existing facilities are in excess of 8 years old and currently provide facilities via a combination of 3Kw 3-pin “household” and a 7Kw 7-pin “Mennekes” socket systems.
2.2EV technology has moved on over the last 10 years and is projected to continue into the future. This growth has resulted in the existing charging infrastructure becoming obsolete, with a requirement to provide alternative socket provision and increase Kw power outputs.
2.3It is vitally important that new housing and commercial growth in the borough is supported by the right forms of transport infrastructure and residents and business are provided the opportunities to use cleaner and more sustainable modes of transport. EV’s will play a key role in Thurrock Council’s ambition to archive net zero for its own carbon emission and in supporting local businesses and residents to do the same. It is also necessary to expand and improve the charging infrastructure within the borough to promote the use of EVs on the network as a cleaner and sustainable mode of transport.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.