1.1 Cabinet approve the commencement of the procurement of a Contract for EV charging for a 15 year period , [NJ1] [WP2] commencing April 2025, which will be compliant with national legislation and the Councils Contract Procedure Rules. 1.2 That delegated authority be given to the Interim Chief Operations Lead, in consultation with the Portfolio Holder for Place and the Environment to decide the appropriate procurement route EV charging using LEVI funding for a 15 year period, subject to performance, commencing April 2025. 1.3 That delegated authority be given to the Interim Executive Director - Place, in consultation with the Portfolio Holder for Place and the Environment, to award the contract referred to above. @Wright, Peter Why a straight 15 years? Would it not be better to do a lesser time with +2 +2? [NJ1] [WP2] Yes it’s in the Heads of Terms as part of funding agreement. I will add something in body of report to firm this up.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report sets out the proposals for the procurement of a Contract to facilitate the provision of Electric Vehicle (EV) charging facilities for on-street residential charging across Thurrock on the adopted highway.
The report seeks approval for the procurement of a new Contract utilising the funding received from the Department for Transport via the Local Electric Vehicle Infrastructure (LEVI) fund for the installation of new on-street charging facilities across Thurrock. The procurement option that will be applied will allow the Council to have a long-term and appropriate contract in place to ensure installation of new charging sites and the expansion of on-street residential EV charging infrastructure within a contractual period of 15 years.
This report is broadly based on the paper submitted to Members on 8th December 2020 covering the On-Street Residential Chargepoint Scheme (ORCS) funded EV Charging programme and procurement options.
This paper is focused upon the LEVI funding opportunity for Thurrock Council and how an appropriate EV Charging operator needs to be identified and commissioned to support emerging and future EV Charging in Thurrock, the strategy for implementation of which will be developed prior to the commencement of contract award.
Commissioner Comment:
The Commissioners have seen the report and made no further comments.
1. Recommendation(s)
1.1That Cabinet approve the commencement of the procurement of a Contract for EV charging for a 15 year period, commencing April 2025, which will be compliant with national legislation and the Councils Contract Procedure Rules. 1.2 That delegated authority be given to the Interim Chief Operations Lead, in consultation with the Portfolio Holder for Place and the Environment to decide the appropriate procurement route EV charging using LEVI funding for a 15 year period, subject to performance, commencing April 2025.
1.3That delegated authority be given to the Interim Executive Director - Place, in consultation with the Portfolio Holder for Place and the Environment, to award the contract referred to above.
2. Introduction and Background
2.1Thurrock has received funding from the Department for Transport (DfT) released through the LEVI Fund. LEVI Fund supports local authorities in England to plan and deliver charging infrastructure for residents without off-street parking.
The fund comprises:
• capital funding to support charge point delivery, • capability funding to ensure that local authorities have the staff and capability to plan and deliver charging infrastructure.
2.2The LEVI Fund has 2 main objectives:
• deliver a step-change in the deployment of local, primarily low power, on-street charging infrastructure across England, • accelerate the commercialisation of and investment in, the local charging infrastructure sector.
2.3Thurrock Council has been successful in the securing funding for the roll out of charging points to fulfil the requirements of the LEVI and it is currently in the process of recruiting to posts to lead on the production an EV Strategy and identification of site. The funding of these posts has previously been secured through the first tranche of LEVI funding.
2.4To enable Thurrock to roll out additional charging points throughout the Borough, a procurement activity needs to be undertaken to align the Authority with a provider. The funding requirement stipulates certain conditions around the award of the Contract such as durations and locations of charge points. These are set out within the Heads of Terms document (Appendix 1).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.