Highways Term Maintenance and Street Lighting Contract Procurement
NotedPlanning1 paper
Planning, Transport, Regeneration Overview and Scrutiny Committee noted this item on Tuesday 7 December 2021. Below is the council's own wording, with the papers it was decided on.
That Planning, Transport & Regeneration Overview and Scrutiny Committee: 1.1 Noted the contents contained within the report and; 1.2 Provided Cabinet with any relevant observations or comments to aid their consideration of the proposals contained within this report. Due to the unresolved technical issues, the Committee agreed to postponed this meeting and defer the rest of the items to the next meeting.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
The current Term Maintenance Contract which expires on the 31st March 2023, provides a delivery method for works derived from the Highways Infrastructure and Transport Development Teams within the Public Realm Directorate.
This report sets out the proposed way forward for procuring a new Term Maintenance Contract for the delivery of highway works and a separate Street Lighting Maintenance Contract to deliver revenue and capital works over an 8 year period commencing 1st April 2023.
Recommendations
That Planning, Transport & Regeneration Overview and Scrutiny Committee:
1.1Note the contents contained within the report and;
1.2Provide Cabinet with any relevant observations or comments to aid their consideration of the proposals contained within this report.
2. Introduction and Background
2.1The current Term Maintenance Contract which expires on the 31st March 2023 provides a delivery method for works derived from the Highways Infrastructure and Transport Development teams within the Public Realm Directorate.
2.2These works programmes consist of the Department for Transport (DfT) Maintenance Block Allocation, DfT Integrated Transport Programme, Highways Infrastructure Revenue Allocation, Section 106 contributions and internal and external bid awards.
2.3The current contract allows the highways and transportation services within the Public Realm directorate to gain efficiencies on reduced administration and procurement costs. There are also efficiencies in scale which can be achieved for the service provider resulting in reduced costs being passed down through competitive rates for the Authority.
2.4This approach has allowed the Authority to demonstrate good practice with respects to efficient highway service delivery and meeting the objectives set out in the Incentive Fund application via the DfT Highways Maintenance Efficiency Programme (HMEP) and the Authority obtaining level Band 3 funding which is the maximum achievable.
2.5Historically all work types have been combined with all work streams being delivered via the Term Maintenance Contract and whilst across the board it provides good competitive value, it is considered that as street lighting is a specialist area this service area would attract better value as a standalone contract. The justification for this is that there are a large number of street lighting only contractors that historically haven’t submitted a tender for this service as they have been unable to fulfil the other requirements of the specification for service delivery. It is therefore considered for street lighting only, that better value would be obtained if this area of work was procured via a standalone contract over an 8 year period to match the Term Maintenance Contract.
2.6Street lighting, on average, has a £500,000 per annum revenue allocation which is then matched with a variable annual capital allocation of approximately £750,000. Therefore, over the 8 year period the contract value could be in the region of £10,000,000. This contract enables us to fulfil our statutory duty under the 1980 Highways Act with respects to the maintenance of street lighting assets.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.