That Cabinet: 1. Approved the increase to the contract value for the Term Partnering Agreement for Responsive Repairs, Voids and Related Works awarded to Mears Ltd by £22,828,000.00 for the remaining term of the Contract to 28February 2025. 2. Noted that any financial commitment from the Housing Revenue Account (HRA) to match fund works from the Social Housing Decarbonisation Fund is subject to a separate formal decision and in consultation and approval from the s151 officer and new financial governance procedures. Reason for decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report sets out the recommendation for the Contract Modification to the Term Partnering Agreement for Responsive Repairs, Voids and Related Works awarded to Mears Ltd for the remaining term of the Contract to 28th Feb 2025. The Contract Modification request is to increase the value of the contract spend for the remaining contract term.
The requested increase to the value of contract spend is due to the following factors:
• Increased volumes of work • Incorporation of new legislative changes (Building and Fire Safe safety) • Inflationary Price Changes (beyond predicted levels) • Additional works to Housing assets such as fire safety, voids and temporary accommodation and energy efficiency works.
1. Recommendation(s)
1.1That Cabinet approve the increase to the contract value for the Term Partnering Agreement for Responsive Repairs, Voids and Related Works awarded to Mears Ltd by £22,828,000.00 for the remaining term of the Contract to 28th Feb 2025.
1.2That Cabinet note that any financial commitment from the Housing Revenue Account (HRA) to match fund works from the Social Housing Decarbonisation Fund is subject to a separate formal decision and in consultation and approval from the s151 officer and new financial governance procedures. 2. Introduction and Background
2.1The Council entered a Term Partnering Contract with Mears Ltd in 2014 for the delivery of the responsive repairs and planned maintenance works to its housing stock. The contract was awarded for an initial five-year term with an extension period of a further five-year period.
2.2The Contract was extended after the initial five-year period in March 2020 and this will expire in 28th February 2025. This extension in Mar 2020 delivered a commercial benefit to the Council over the next 5-year contract term of approx. £523,677 based on discounted rates on certain scope items, service improvements, and continued social value commitments. No further extensions beyond this period are possible. The process for the delivery of the repairs and planned maintenance works from February 2025 will commence in 2023 and Cabinet will receive a report detailing and seeking approval for this process.
2.3The contract is based on price per property (PPP) which equate to Mears attending on average 3 repairs per council housing property per year. The contract is an inclusion and exclusion contract; all inclusions are set within the price per property model. Exclusions are repairs that are required but are not within the contracted PPP model. These exclusion works are mainly complete renewals of various items within the property, such as new baths, toilets or asbestos removal. All exclusions are listed within the contract and are based on a national schedule of rates. The Contractor is entitled to an annual inflationary uplift to the contract price and this process is detailed in para 2.11 and para 2.12 of this report.
2.4The contract spent for the full ten-year term (initial five years plus five-year extension) was set at £60,000,000. By the end of this current financial year the contract spend will reach £57.4m. For the first 3 years between 2014-2017 the contract was delivered in line with the initial tender values and job volumes. The number of repairs undertaken within the price per property model and the exclusion works prices outside of this model remained consistent.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.