1.1 Approve the Modification to Contract to increase the contract sum by £1,757,471.74 to the total of £5,272,415. 1.2 Approve the Modification to increase the Contract term for the Refurbishment of Non-Traditional Construction Properties to April 2024. 1.3 That Cabinet agrees to delegate authority to the Corporate Director of Adults, Housing and Health in conjunction with the Portfolio Holder and Section 151 Officer, to sign the contract variation. Reason for the decision: as outlined in the report This decision is subject to Call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report sets out a recommendation for the Contract Modification to the Refurbishment of Non-Traditional Construction Properties contract awarded to Wates Property Services.
The original term of the contract ran until 30 April 2023. An extension is required to increase the length of the contract term and value of the overall contract sum.
The requested increase to the value of the contract sum and timeframe is due to the following factors:
• Increased scope of work due to additional structural requirements • Incorporation of new retrofit standards (PAS 2035) • Inflationary price changes (beyond predicted levels) • Availability of accredited supply chain
By law, councils must have a balanced budget. If a council cannot find a way to finance its budget, it must issue a 'Section 114' notice. On 19 December 2022, the Council issued the ‘Section 114’ notice. This puts strict limits on what the Council can spend.
The Section 114 notice was necessary as the Council was unable to balance its budgets for the financial years of 2022/23 and 2023/24.
In September 2022, Directions issued to the Council by the Government required us to put in place an Improvement and Recovery Plan to the satisfaction of Commissioners. The plan has 5 main themes: • financial sustainability • governance and scrutiny • strategic direction • place leadership and growth • leadership and culture
These recommendations fit within the objectives of the Thurrock Improvement and Recovery Plan 2022 for a financially sustainable council.
Previous reports Procurement of Housing Capital Programme Delivery, Cabinet 10th March 2021 item 121.
Commissioner Commentary
1. Recommendation(s)
1.1Approve the Modification to Contract to increase the contract sum by £1,757,471.74 to the total of £5,272,415.
1.2Approve the Modification to increase the Contract term for the Refurbishment of Non-Traditional Construction Properties to April 2024.
1.3That Cabinet agrees to delegate authority to the Corporate Director of Adults, Housing and Health in conjunction with the Portfolio Holder and Section 151 Officer, to sign the contract variation.
2. Introduction and Background
2.1Non-traditional construction generally refers to prefabricated building systems, frames and construction methods that known as Prefabricated Reinforced Concrete (PRC) properties. They were mostly constructed post-war up between 1945 and 1951 and were only envisaged to last 10 years, but such was the durability that many are still standing today. Within the Thurrock housing stock we have over 200 of these non-traditionally constructed properties all of which are tenanted family sized homes. These properties are designated defective within the meaning of the Housing Defects Act 1984, now part of the Housing Act 1985, because they have the potential for corrosion of the embedded steel reinforcements and are generally considered by lending institutions not to be mortgageable.
2.2The refurbishment of these properties will make them both structurally safe and achieve improved standards of thermal comfort and energy efficiency. Improvements are tailored to the different build types of which the level of refurbishment required varies. It incorporates measures such as new external wall insulation, new windows and doors, sustainable heating systems and sustainable energy sources. These will both improve the energy efficiency ratings of the properties providing more comfortable and economical homes for our residents, in line with the Councils climate change agenda.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.