Thurrock Council
Cabinet, Wednesday 12 July 2023 at 7.00pm

Housing Capital Programme Contract Modifications (Decision: 110656)

Approved Executive 1 paper

Cabinet approved this item on Wednesday 12 July 2023. Below is the council's own wording, with the papers it was decided on.

Item150

Resolved

1.1 Approve the Modification to Contract to increase the contract sum by £1,757,471.74 to the total of £5,272,415. 1.2 Approve the Modification to increase the Contract term for the Refurbishment of Non-Traditional Construction Properties to April 2024. 1.3 That Cabinet agrees to delegate authority to the Corporate Director of Adults, Housing and Health in conjunction with the Portfolio Holder and Section 151 Officer, to sign the contract variation. Reason for the decision: as outlined in the report This decision is subject to Call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Executive summary

This report sets out a recommendation for the Contract Modification to the Refurbishment of Non-Traditional Construction Properties contract awarded to Wates Property Services.

The original term of the contract ran until 30 April 2023. An extension is required to increase the length of the contract term and value of the overall contract sum.

The requested increase to the value of the contract sum and timeframe is due to the following factors:

• Increased scope of work due to additional structural requirements • Incorporation of new retrofit standards (PAS 2035) • Inflationary price changes (beyond predicted levels) • Availability of accredited supply chain

By law, councils must have a balanced budget. If a council cannot find a way to finance its budget, it must issue a 'Section 114' notice. On 19 December 2022, the Council issued the ‘Section 114’ notice. This puts strict limits on what the Council can spend.

The Section 114 notice was necessary as the Council was unable to balance its budgets for the financial years of 2022/23 and 2023/24.

In September 2022, Directions issued to the Council by the Government required us to put in place an Improvement and Recovery Plan to the satisfaction of Commissioners. The plan has 5 main themes: • financial sustainability • governance and scrutiny • strategic direction • place leadership and growth • leadership and culture

These recommendations fit within the objectives of the Thurrock Improvement and Recovery Plan 2022 for a financially sustainable council.

Previous reports Procurement of Housing Capital Programme Delivery, Cabinet 10th March 2021 item 121.

Commissioner Commentary

1. Recommendation(s)

1.1Approve the Modification to Contract to increase the contract sum by £1,757,471.74 to the total of £5,272,415.

1.2Approve the Modification to increase the Contract term for the Refurbishment of Non-Traditional Construction Properties to April 2024.

1.3That Cabinet agrees to delegate authority to the Corporate Director of Adults, Housing and Health in conjunction with the Portfolio Holder and Section 151 Officer, to sign the contract variation.

2. Introduction and Background

2.1Non-traditional construction generally refers to prefabricated building systems, frames and construction methods that known as Prefabricated Reinforced Concrete (PRC) properties. They were mostly constructed post-war up between 1945 and 1951 and were only envisaged to last 10 years, but such was the durability that many are still standing today. Within the Thurrock housing stock we have over 200 of these non-traditionally constructed properties all of which are tenanted family sized homes. These properties are designated defective within the meaning of the Housing Defects Act 1984, now part of the Housing Act 1985, because they have the potential for corrosion of the embedded steel reinforcements and are generally considered by lending institutions not to be mortgageable.

2.2The refurbishment of these properties will make them both structurally safe and achieve improved standards of thermal comfort and energy efficiency. Improvements are tailored to the different build types of which the level of refurbishment required varies. It incorporates measures such as new external wall insulation, new windows and doors, sustainable heating systems and sustainable energy sources. These will both improve the energy efficiency ratings of the properties providing more comfortable and economical homes for our residents, in line with the Councils climate change agenda.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Capital Programme Contract Modifications (Decision: 110656)Decisions 138 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
AJ
Councillor Andrew JefferiesChair, present
DA
Councillor Deborah ArnoldDeputy Chair, present
AC
Councillor Adam CarterCommittee Member, present
BJ
Councillor Barry JohnsonCommittee Member, present
BM
Councillor Ben ManeyCommittee Member, present
GC
Councillor George CoxshallCommittee Member, present
GS
Councillor Graham SnellCommittee Member, present
JB
Jo BroadbentOfficer, expected
MB
Mark BradburyOfficer, expected
AH
Asmat HussainOfficer, expected
SM
Steven MairOfficer, expected
DS
Dr Dave SmithPublic, expected

All 15 on the meeting page

On this subject at Thurrock

Search all
  1. Housing Capital Programme Contract Modifications (Decision: 110656)This decision
  2. Procurement of Housing Capital Programme DeliveryApproved
  3. Procurement Of Housing Capital Programme DeliveryDecided
  4. Procurement of Housing Capital Programme DeliveryApproved
  5. Procurement of Housing Capital Programme DeliveryNoted
  6. Procurement of Housing Capital Programme Delivery (Decision 01104430)Approved

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies