Revenue Capital Budget Monitoring Report Q2 2024-25

Noted Scrutiny 6 papers

Corporate Overview and Scrutiny Committee noted this item on Tuesday 14 January 2025. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

The Committee: 2.1 Noted the council’s Service position and forecast overspend position as at quarter 2 of £2.722m, representing a reduction of £0.348m on the position presented at quarter 1. 2.2 Noted the council’s overall position and forecast overspend position at quarter 2 of £1.896m, representing a reduction of £0.209m on the position presented at quarter 1. 2.3 Noted the approval of the transfer of £1.381m reserves to a MTFS Delivery Reserve and £1.5m to an Adult Social Care & Children’s Social Care Demographic Risk Reserve (as per section 14 of Appendix 1 and 4.7 below) approved at Cabinet 11 th December 2024 . 2.4 Noted the progress made on delivery against the savings target for 2024/25 and the remaining red (unachievable) rated savings. 2.5 Further to an in-depth review and re-profiling of the General fund capital projects, the Committee noted and commented on the capital programme, and the anticipated General Fund Capital Programme slippage of £30.627m and £10.157m HRA Capital Programme slippage projected in the report. 2.6 Noted the approval of the addition of the DEFRA grant funding in the capital programme (as per section 16 of Appendix 1 and 4.12 below) approved at Cabinet 11th December 2024.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Corporate Overview and Scrutiny Committee

Report to Committee Report Title Q2 Forecast Revenue and Capital Outturn Report Date of Meeting Tuesday, 14 January 2025

Report Author Sima Khiroya, Assistant Director Financial Management & Procurement Corporate Director Chief Financial Officer S151

Lead Cabinet Member(s) Cabinet Member for Resources

Wards Affected (All Wards);

Identify exempt Choose an item. information and n/a exemption category

Appendices (if any) 1. Revenue and Capital Monitoring Report as at 30th September 2024 (Quarter 2) 2.1 General Fund Earmarked Reserves 2024/25 2.2 HRA Earmarked Reserves 2024/25 2. Savings Tracker 2024/25 4.1 General Fund Capital Budget & Forecast 2024/25 4.2 HRA Capital Budget & Forecast 2024/25

1. Executive Summary 1.1 This report sets out the estimated forecast revenue outturn position for 2024-25 for the General Fund, Housing Revenue Account (HRA) and Dedicated Schools Grant (DSG) and provides an update on delivery against the savings target for 2024-25 at quarter 2.

1.2The total service position is showing a £2.722m net overspend position against a general fund budget of £172.398m at the end of quarter 2 (Period 6) for 2024/25. The overall position is showing significant pressures in Place (£1.919m overspend) and Corporate Services (£1.181m overspend). The movement between quarter 1 and quarter 2 is a reduction in net service expenditure of £0.348m.

1.3The actual reduction in gross expenditure for services between quarter 1 and quarter 2 is £0.741m, however, there has also been a reduction in the projected transfer from reserves by £0.393m, resulting in the net position reducing by £0.348m.

1.4The 2024/25 budget was set assuming exceptional financial support being required from central government in the amount of £68.570m. The position at quarter 2 shows a forecast additional pressure of £1.896m against this funding. There is an imperative that this pressure is managed by the end of the financial year.

1.5Services have been asked to take action to mitigate their pressures within the current financial year, where possible. Pressures that are ongoing into the next financial year, will be reflected in the MTFS Budget Setting process for 2025/26.

1.6For the financial year 2020/21, the government introduced a one-off income loss scheme, the Covid Sales, Fees and Charges Scheme (SFC). This was intended to compensate local authorities for irrecoverable and unavoidable losses from sales, fees and charging income, generated in the delivery of services, that was impacted due to the Covid-19 pandemic. This covered loss of income in areas such as the registrars service, Grangewaters outdoor education centre, nurseries, parking charges etc. The compensation for income loss claims during the financial year 2020/21 were based on what was happening at the time, and as the financial year progressed, other corresponding reductions in expenditure and the impact of other funding released by the Government to compensate for loss of income and expenditure (such as the cultural grant for the Theatre and funding for staff on Furlough), meant we were in a position where we had overclaimed. The total value of claims that had been submitted during the financial year, based on the estimated income losses made at the time of the claims, amounted to £2.270m. After a full reconciliation as part of the financial year-end accounts, the total income loss that should have been claimed was calculated as £1.069m, resulting in an overclaimed amount of £1.202m. This amount has been provided for within available funding.

1.7The budget forecast at this stage in the financial year projects a total transfer from reserves to services of £12.024m (including £5.246m Transformation funding). In addition, an amount of £0.965m from previously received Contain Outbreak Management Fund Grant is being held in reserves and will be utilised to offset the overspend on Homelessness Services in the Place Directorate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 2 Budget Monitoring Report 2024-25Appendix 1 1.1 MB Download
PDF
.1: GF Earmarked Reserves Quarter 2Appendix 2 153 KB Download
PDF
.2: HRA Earmarked Reserves Quarter 2Appendix 2 117 KB Download
PDF
MTFS Savings Tracker Quarter 2Appendix 3 168 KB Download
PDF
.1: GF Capital Monitoring Report Quarter 2Appendix 4 340 KB Download
PDF
Revenue Capital Budget Monitoring Report Q2 2024-25Report 148 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 22 attended
BM
Councillor Ben ManeyChair, present
JF
Councillor John FoxVice-Chair, present
QA
Councillor Qaisar AbbasCommittee Member, present
MF
Councillor Michael FletcherCommittee Member, present
AG
Councillor Aaron GreenCommittee Member, apologies
JH
Councillor James HaldenCommittee Member, present
CH
Councillor Clifford HollowayCommittee Member, apologies, sent representative
RJ
Councillor Roy JonesCommittee Member, present
CK
Councillor Cathy KentCommittee Member, present
MK
Councillor Martin KerinCommittee Member, present
JC
Councillor John CecilSubstitute, present as substitute
SB
Sarah BrownOfficer, in attendance

All 22 on the meeting page

On this subject at Thurrock

Search all
  1. Revenue Capital Budget Monitoring Report Q2 2024-25This decision
  2. Q3 Forecast Revenue and Capital Outturn Report- Place Directorate ServicesNoted
  3. Q3 Revenue and Capital ReportNoted
  4. Q3 Revenue and Capital ReportNoted
  5. Quarter 2 Forecast Revenue and Capital Outturn ReportNoted
  6. Q1 Forecast Revenue and Capital Outturn ReportNoted

More from Thurrock Corporate Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
5 Mar 2026 Members’ App Pilot UpdateRESOLVED This item be deferred until the new municipal year due to upcoming elections and the possibility of a high t... Deferred Open
5 Mar 2026 Corporate and Improvement Plan – 2025/26 Q3 Corporate Performance ReportRESOLVED for the reasons set out in this report, the Corporate Overview and Scrutiny: Note and make recommendations t... Decided Open
5 Mar 2026 Local Government Reorganisation & Devolution UpdateRESOLVED The Corporate Overview and Scrutiny Committee note the briefing note on Local Government Reorganisation & De... Noted Open
20 Jan 2026 Q2 Financial Outturn 2025/26 and Draft Revenue Budget 2026/27 & Medium-Term Financial Strategy 2026/27-2028/29It was agreed to take both items at the same time. The reports were presented by the Cabinet Member for Resources who... Agreed Open
9 Oct 2025 Q1 2025/26 Finance ReportCorporate Overview and Scrutiny are to note the following: Note: The Qtr 1 forecast position for the general fund, Ho... Noted Open