2.1 Cabinet agreed the key changes to the scheme identified within the value engineering process and the revised delivery strategy as set out in paragraph 4.8 of this report. 2.2 Cabinet authorised the Executive Director of Place to enter into all contractual agreements to deliver the scheme. Decisions will be made in consultation with the S151 officer and Portfolio Holder of Good Growth. Reason for the decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Stanford Le Hope Station Delivery Strategy
Date of Meeting Wednesday 7 May 2025
Report Author George McCullough – Head of Regeneration and Place Corporate Director Claire Demmel, Executive Director of Place
Lead Cabinet Member(s) Cllr Lee Watson, Portfolio Holder for Good Growth
Why is this a key 1. Expenditure over £500K yes decision? 2. Significant impact on 2 or more wards yes
Wards Affected Borough wide affect
Identify exempt N/A information and exemption category
Is report Urgent? Yes Reasons for urgency Funding deadline (only where applicable)
Appendices (if any) 1. October 2023 Cabinet report – project background information
1. Executive Summary 1.1 The redevelopment of Stanford Le Hope station has faced considerable delay and challenge since it began in 2017. The project aims to improve rail service and promote sustainable travel to the surrounding economic and housing growth areas. 1.2 Cabinet agreed a delivery strategy in October 2023. A revised cost plan in 2024, estimated that the total project cost had increased to £36m, inclusive of spend to date. This would require Council borrowing of £17.6m to fund the viability gap. 1.3 The project was placed on hold in Q2 2024 to undertake a value engineering exercise with key stakeholders C2C and Network Rail. The stakeholders have agreed a revised delivery strategy focused on delivering the core station requirements, acceleration of construction and reduction of the Council’s cost to fund the project. 1.4 The key changes to the scheme include simplification of Phase 2 (transport interchange) by relocating the shuttle bus stop to the road, reducing project impact on the railway infrastructure and agreeing to value engineer the station building during the final technical design phase 1.5 Stakeholders agree that there is significant benefit in appointing a contractor at this stage, to complete the technical design phase. The Council will appoint a Contractor through the Eastern Highways framework to alter the current design within funding envelope and deliver the scheme. 1.6 The project will be delivered in 3 phases: • Phase 1 – Infrastructure and design (9 months) • Phase 2 – Station construction (15 months) • Phase 3 – Bridge works 1.7 The stakeholders have agreed to set a fixed budget for the project of £10m inclusive of professional fees. In addition, the Council will retain a budget of £2m as contingency and to pay Network Rail fees and employ a project manager to oversee the project. The project will be funded by £11m of Council funding and £1m Freeport Seed funding. 1.8 Cabinet is asked to approve the revised delivery strategy for the Stanford Le Hope Project and authorise the decision makers identified to enter contractual agreements to deliver the project.
2. Recommendations For the reasons set out in this report, the Cabinet is recommended to: 2.1 Agree the key changes to the scheme identified within the value engineering process and the revised delivery strategy as set out in paragraph 4.8 of this report. 2.2 Authorise the Executive Director of Place to enter into all contractual agreements to deliver the scheme. Decisions will be made in consultation with the S151 officer and Portfolio Holder of Good Growth.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.