Thurrock Council
Cabinet, Wednesday 7 May 2025 at 7.00pm

Stanford-le-Hope Station Options

Agreed Executive 2 papers

Cabinet agreed this item on Wednesday 7 May 2025. Below is the council's own wording, with the papers it was decided on.

Item188

Resolved

2.1 Cabinet agreed the key changes to the scheme identified within the value engineering process and the revised delivery strategy as set out in paragraph 4.8 of this report. 2.2 Cabinet authorised the Executive Director of Place to enter into all contractual agreements to deliver the scheme. Decisions will be made in consultation with the S151 officer and Portfolio Holder of Good Growth. Reason for the decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Report to Cabinet Report Title Stanford Le Hope Station Delivery Strategy

Date of Meeting Wednesday 7 May 2025

Report Author George McCullough – Head of Regeneration and Place Corporate Director Claire Demmel, Executive Director of Place

Lead Cabinet Member(s) Cllr Lee Watson, Portfolio Holder for Good Growth

Why is this a key 1. Expenditure over £500K yes decision? 2. Significant impact on 2 or more wards yes

Wards Affected Borough wide affect

Identify exempt N/A information and exemption category

Is report Urgent? Yes Reasons for urgency Funding deadline (only where applicable)

Appendices (if any) 1. October 2023 Cabinet report – project background information

1. Executive Summary 1.1 The redevelopment of Stanford Le Hope station has faced considerable delay and challenge since it began in 2017. The project aims to improve rail service and promote sustainable travel to the surrounding economic and housing growth areas. 1.2 Cabinet agreed a delivery strategy in October 2023. A revised cost plan in 2024, estimated that the total project cost had increased to £36m, inclusive of spend to date. This would require Council borrowing of £17.6m to fund the viability gap. 1.3 The project was placed on hold in Q2 2024 to undertake a value engineering exercise with key stakeholders C2C and Network Rail. The stakeholders have agreed a revised delivery strategy focused on delivering the core station requirements, acceleration of construction and reduction of the Council’s cost to fund the project. 1.4 The key changes to the scheme include simplification of Phase 2 (transport interchange) by relocating the shuttle bus stop to the road, reducing project impact on the railway infrastructure and agreeing to value engineer the station building during the final technical design phase 1.5 Stakeholders agree that there is significant benefit in appointing a contractor at this stage, to complete the technical design phase. The Council will appoint a Contractor through the Eastern Highways framework to alter the current design within funding envelope and deliver the scheme. 1.6 The project will be delivered in 3 phases: • Phase 1 – Infrastructure and design (9 months) • Phase 2 – Station construction (15 months) • Phase 3 – Bridge works 1.7 The stakeholders have agreed to set a fixed budget for the project of £10m inclusive of professional fees. In addition, the Council will retain a budget of £2m as contingency and to pay Network Rail fees and employ a project manager to oversee the project. The project will be funded by £11m of Council funding and £1m Freeport Seed funding. 1.8 Cabinet is asked to approve the revised delivery strategy for the Stanford Le Hope Project and authorise the decision makers identified to enter contractual agreements to deliver the project.

2. Recommendations For the reasons set out in this report, the Cabinet is recommended to: 2.1 Agree the key changes to the scheme identified within the value engineering process and the revised delivery strategy as set out in paragraph 4.8 of this report. 2.2 Authorise the Executive Director of Place to enter into all contractual agreements to deliver the scheme. Decisions will be made in consultation with the S151 officer and Portfolio Holder of Good Growth.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Stanford-le-Hope Station Interchange Update Report Decision 110674Appendix 1 152 KB Download
PDF
Stanford-le-Hope Station OptionsReport 173 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 19 attended
JK
Councillor John KentChair, present
LW
Councillor Lynn WorrallVice-Chair, present
VH
Councillor Vikki HartsteanCommittee Member, present
VH
Councillor Victoria HollowayCommittee Member, present
MH
Councillor Mark HooperCommittee Member, present
VM
Councillor Valerie Morris-CookCommittee Member, apologies
SM
Councillor Sara MuldowneyCommittee Member, present
LW
Councillor Lee WatsonCommittee Member, present
AB
Ashley BaldwinOfficer, in attendance
DC
Dawn CalvertOfficer, in attendance
CD
Claire DemmelOfficer, in attendance
MD
Michael DineenOfficer, in attendance

All 19 on the meeting page

On this subject at Thurrock

Search all
  1. Stanford-le-Hope Station OptionsThis decision
  2. Stanford-le-Hope (SLH) Station/ Interchange Update Report (Decision: 110674)Noted
  3. Stanford-le-Hope (SLH) Station / Interchange UpdateNoted
  4. Stanford-le-Hope Interchange ProjectDecided
  5. Stanford-le-Hope Interchange ReportDecided
  6. Stanford-le-Hope Interchange ReportNoted

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies