AI summaryThurrock Cabinet noted its divestment programme has recovered £661m so far, about 63% of its original £1bn investment portfolio, and renewed officer delegations to keep selling and litigating to recover more.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted recovery and fees, kept existing delegations
Money£661m recovered, £5.3m fees to dateForecast total recovery c.£800m, total fees c.£10.6m
What happens nextWind farm sales in progressTail investments to be exited or restructured
Who it affectsAll wardsCouncil-wide financial recovery programme
What was decided
Cabinet noted the divestment programme progress and its impact on the Council's Capitalisation Direction, including £661m recovered to date against an original portfolio of c.£1bn. Report P11, P25
Cabinet noted professional advisory fees of £5.3m to date, with total forecast fees of c.£10.6m up to the end of FY 28/29, funded from the Treasury Equalisation Reserve. Report P11, 5.4
Cabinet approved the continuation of the September 2023 delegations to enable the implementation of the divestment strategy for FY 26/27.
Why
The programme supports the Secretary of State's 2022 Direction requiring the Council to reduce its investment debt and borrowing costs, and to demonstrate best value on disposals. Report 4.3, P11
Continued delegation is needed so officers can respond quickly to market opportunities, progress litigation, and engage with administrators on creditor recoveries. Report 4.7
The Commissioner's view is that continuing implementation, including litigation, is essential to financial recovery, though it remains long-term and complex. Report P11, P12
What happens next
Continue to maximise creditor distributions from the Toucan and JLG/JCF administrations and progress related litigation claims where KC opinion supports action.
Review options on distressed tail investments including Safe As Houses and Redwood Bank in early 2026, and monitor Shard, Allied Care and Atlana positions for exit potential. Report P41, P42, P43, P44, P45, P46
The money
c.£1bn Original investment portfolio value at start of divestment programme Report P11
£661m Total recovered to date, about 63% of original portfolio Report P11
£525m Toucan recoveries to date Report P29
£92m CCLA Funds recoveries Report P30
£130m+ Further forecast recoveries over coming years (excluding litigation) Report P11
c.£800m Total estimated recovery Report P11
£5.3m Professional advisory fees to date, from FY 23/24 to date Report P11
£10.6m Total estimated professional fees up to end of FY 28/29 Report P11
£135.5m Capitalisation Direction forecast capital receipts FY 25/26 to 29/30 Report P11
£133.3m Latest forecast capital receipts, a £2.2m variance Report P11
£35m Estimated annual borrowing interest saving on £670m of debt Report 5.4
Options considered
Chosen: Continue divestment programme under existing September 2023 delegations. Delegations have worked effectively and are needed to maintain momentum and respond to the market Report 4.7
Chosen: Sell minority wind farm stakes via appointed sales agents. Aim to reduce portfolio to under five investments in 2026 Report P40, P49
Chosen: Pursue litigation against Liam Kavanagh, Rockfire Capital and Laven LLP/Bedford Row. Based on positive KC opinion and cost-benefit assessment Report P49
Implications
Financial: Recoveries of £661m to date have been used to reduce borrowing and associated interest costs, estimated at c.£35m per year on £670m of debt. Report 5.4
Financial: CD forecast capital receipts of £133.3m for FY 25/26 to 29/30 carry a £2.2m variance against the £135.5m assumption. Report P11
Financial: Treasury Equalisation Reserve has sufficient headroom to fund estimated programme costs; reviewed quarterly. Report P11
Legal: Litigation claims have been issued against individuals and firms in respect of Toucan and JLG/JCF investments, with KC opinion required to support any action.
Risk: Key risks flagged red include delays to forecast receipts, litigation outcomes, and further reputational impact from investigations or unfavourable outcomes. Report P52
Equalities: No specific diversity and equality implications identified for this update report. Report P55
Who and where
All Thurrock Council wards, given the council-wide nature of the financial recovery Report P8, P7
Creditors of the Toucan and JLG/JCF administrations
Counterparties to the remaining tail investments including wind farm sales process, Safe As Houses, Redwood Bank, Shard, Allied Care and Atlana/PSSIF Report P40, P41, P42, P44, P45, P46
Defendants in ongoing litigation, including Liam Kavanagh, Rockfire Capital, and Laven LLP/Bedford Row
Timeline
2 September 2022: Secretary of State issued Direction to the Council requiring debt reduction and sustainable treasury strategy
2 September 2023: Cabinet agreed divestment hurdle rate of 12% and approved delegations to deliver the programme Report 4.7, P18
February 2024: £510m received from sale of Toucan solar farm assets
October 2025: Cost assumptions for the divestment programme updated Report P52
FY 25/26 to 29/30: Capitalisation Direction period for forecast capital receipts of £133.3m
Spring 2026: Indicative timing for review and decision on Safe As Houses restructure options Report P41
End of FY 25/26: Target to decide on potential offer for Redwood Bank equity stake Report P42
End of FY 28/29: Forecast end of total professional fees of c.£10.6m Report P11
Plain English for the jargon
Capitalisation Direction (CD): Government permission allowing the Council to treat certain revenue costs as capital, smoothing the impact on the revenue budget
Capital Financing Requirement (CFR): The Council's underlying need to borrow to fund its capital spending
MRP: Minimum Revenue Provision, the minimum amount the Council must set aside each year to repay debt
PWLB: Public Works Loan Board, the government body that lends to local authorities
Treasury Equalisation Reserve: A council reserve used to fund treasury and divestment-related fees and asset disposal costs
KC: King's Counsel, a senior barrister whose opinion supports the merits of a legal claim
LGR: Local Government Reorganisation, referenced in the report as a factor for residual investment decisions
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item305
Resolved
2.1 Cabinet noted the divestment programme progress and the impact on the Council’s CD; (Section 5 ); 2.2 Cabinet noted the professional advisory fees incurred to date and forecast fees (Section 6 ); 2.3 Cabinet approved the continuation of the delegations previously agreed by Cabinet to enable the implementation of the divestment strategy (Section 4.8); and 2.4 Cabinet noted the decisions taken to deliver the programme to date (Section 6.8).
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Divestment Update Report
Date of Meeting Wednesday 21 January 2026
Report Author Carmel Booth, Commercial Advisor
Corporate Director Chief Financial Officer Section 151
Lead Cabinet Member(s) Cabinet Member for Resources
Why is this a key decision? 1. Expenditure over £500K yes
2. Significant impact on 2 or more wards yes
Wards Affected (All Wards);
Identify exempt information Appendix 1 plus accompanying Appendices A, B and exemption category and C are exempt for the following reason 3. Information relating to the financial or business affairs of any particular person (including the authority holding that information) Schedule 12A of the Local Government Act 1972
Is report Urgent? No Reasons for urgency (only N/A where applicable) Appendices (if any) All Exempt: Appendix 1 - Divestment Update Report Appendix A - Litigation Update Appendix B – Investment Level Update Appendix C - Professional Fees Summary
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.