Q3 Financial Outturn Report 2025-26 - Amendment to General Fund Capital Programme

Approved Committee 2 papers

AI summaryThurrock Council approved a £17.080m net increase to the 2025/26 General Fund Capital Programme, taking the revised programme to £118.481m, mainly funded by Government Grant linked to the Freeport.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevised 2025/26 General Fund Capital Programme now £118.481m
Money£17.080m net increase, revised total £118.481mSchemes mainly funded through Government Grant related to the Freeport
What happens nextIndividual scheme details in Appendix 1Any further changes made at Cabinet to be reported to Council
Who it affectsAll wards and all service areasAffects every Council budget holder

What was decided

Council approved a net increase of £17.080m to the 2025/26 General Fund Capital Programme through the addition of schemes, mainly funded by Government Grant related to the Freeport, taking the revised programme to £118.481m. Report P12, P14

Details of the individual schemes being added are set out in Appendix 1 to the report. Report P12, P10, 4.3

Why

The Cabinet considered the Q3 Financial Outturn Report on 18th February and recommended the change to the size of the capital programme, which full Council must approve under the Constitution because budget decisions are not delegated. Report P11, P36

The Commissioners noted slippage in the General Fund capital programme against revised budgets and called for stronger governance, stricter oversight of complex capital schemes and effective stakeholder engagement to improve delivery, and were content for the report to proceed. Report P13

What happens next

Any changes made at Cabinet on 18th February will be reported in a supplementary report to Council. Report P11

The Council will continue monthly and quarterly budget monitoring, and Communities and Equality Impact Assessments will be completed where individual projects may have equality implications. Report P25, 10.1, P24

The money

  • £17.080m Net increase in the General Fund capital programme from added schemes Report P12, P14
  • £118.481m Revised 2025/26 General Fund Capital Programme total Report P12, P14, P16, P18
  • 56.701 Forecast Out-turn for total General Fund capital expenditure at March 2026 (£m) Report P16, P18
  • -61.780 Forecast variance against current budget for total General Fund capital expenditure (£m) Report P16, P18
  • 86.584 Current budget for Government Grants funding the General Fund capital programme (£m) Report P18
  • 24.616 Current budget for External Borrowing funding the General Fund capital programme (£m) Report P18
  • 4.459 Current budget for Developer Contributions (S106) funding the General Fund capital programme (£m) Report P18
  • 62.839 Current budget for the Place directorate within the General Fund capital programme (£m) Report P16

Options considered

  • Chosen: Approve the £17.080m net increase to the General Fund Capital Programme. Cabinet recommended the change to full Council, which is required to approve changes to the size of the capital programme Report P11, P12, P36
  • Rejected: Alternative options considered. The report states that no alternative options were considered Report P20

Implications

  • Financial: The report is primarily financial in nature and financial implications are set out within it and Appendix 1. Report P21
  • Legal: The Local Government Finance Act 1992 requires the Council to set a balanced budget each year, with statutory duties on the Section 151 Officer under section 114; section 28 of the Local Government Act 2003 requires periodic budget monitoring. Under the Constitution, approving or adopting the budget is reserved to full Council and is not delegated. Report P35, P36
  • Risk: Identified risks cover demand-led service pressures, pay and inflation, savings delivery, insurance and claims, fraud, and changes in government policy and funding; most are rated Amber and are reviewed monthly. Report P25, P26, P27, P28, P29, P30, P32, P24
  • Equalities: The report does not itself introduce direct equality implications, but Communities and Equality Impact Assessments (CEIAs) will be completed as individual projects progress where there may be impacts on specific groups. Report 10.1, P40
  • Other: The Commissioners highlighted ongoing slippage in the General Fund capital programme and the need for stronger governance and stakeholder engagement on complex schemes to improve delivery. Report P13

Who and where

  • All wards within Thurrock Report P7
  • All Council service areas and budget holders Report P44
  • Specific groups who may be affected by individual capital projects (subject to future CEIAs) Report 10.1

Timeline

  • 6th February 2026: Equality implications verified by the Team Manager for Community Development Report P40
  • 9th February 2026: Financial, risk and legal implications verified by named officers; report dated for submission Report P22, P23, P33, P34, P37
  • 18th February 2026: Cabinet considered the Q3 Financial Outturn Report and recommended the change to the size of the capital programme Report P11
  • Wednesday, 25th February 2026: Council meeting at which the amendment to the General Fund Capital Programme was approved Report P2

Plain English for the jargon

  • General Fund Capital Programme: The Council's main capital spending plan, covering spending on assets and infrastructure funded from sources other than the Housing Revenue Account.
  • S151 Officer: The officer designated under section 151 of the Local Government Act 1972 as responsible for the proper administration of the Council's financial affairs.
  • Freeport: A government-designated tax and customs site intended to attract investment, employment and regeneration; Government Grant referenced in the report is linked to this status.
  • S106: Planning obligations under section 106 of the Town and Country Planning Act 1990, where developers contribute to local infrastructure.
  • CEIA: Communities and Equality Impact Assessment, used to assess the impact of proposed changes on specific groups.
  • MTFS: Medium Term Financial Strategy, the Council's forward planning framework for income and spending.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item62

Resolved

RESOLVED 2.1 Council approved the following adjustment to the 2025/26 Capital Programme. 2.2 A net increase of £17.080m in the General Fund programme as set out in paragraph 4.1 through the addition of schemes totalling £17.080m mainly funded through Government Grant related to the Freeport. The revised 2025/26 general fund Capital Programme is £118.481m. 2.3 Details of the individual schemes are included at Appendix 1.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Council

Report to Council Report Title Q3 Financial Outturn Report 2025-26 – Amendment to General Fund Capital Programme

Date of Meeting Wednesday, 25th February 2026

Report Author Dave McNamara, Assistant Director Strategic & Corporate Finance (Deputy S151)

Corporate Director Chief Financial Officer S151

Lead Cabinet Member(s) Cabinet Member for Resources

Why is this a key 1. Expenditure over £500K yes decision? 2. Significant impact on 2 or more wards yes

Wards Affected (All Wards);

Identify exempt information and N/A exemption category

Is report Urgent? No

Appendices (if any) Appendix1: Adjustments to the 2025/26 General Fund Capital Programme

1 1. Executive Summary 1.1. Responsibility for setting the Capital Programme and agreeing changes in the size of the programme sits with full council and is not delegated to Cabinet. On 18th February Cabinet considered the Q3 Financial Outturn Report. Included in the report is a recommendation to change the size of the 2025/26 Capital Programme. 1.2. This report includes relevant extracts from the Cabinet report. Any changes made at Cabinet will be reported in a supplementary report to Council

2. Recommendation 2.1. Council approves the following adjustment to the 2025/26 Capital Programme: 2.2. A net increase of £17.080m in the General Fund programme as set out in para 4.1 through the addition of schemes totalling £17.080m mainly funded through Government Grant related to the Freeport. The revised 2025/26 general fund Capital Programme is £118.481m. 2.3. Details of the individual schemes are included at Appendix 1.

3. Commissioners Comments 3.1. The General Fund capital programme slippage against the revised budgets, signals ongoing challenges resulting in potential delay in infrastructure improvements. Stronger governance, stricter oversight on complex capital schemes and effective stakeholder engagement will be essential to improve delivery. 3.2. The Commissioners are content for this report to be considered.

4. Capital Programme Monitoring – General Fund 4.1. The revised general fund Capital Programme for 2025/26 is summarised below including financing assumptions. The table assumes Council approval to amend the total GF Capital Programme through the addition of schemes totalling £17.080m mainly funded through Government Grant related to the Freeport, taking the revised 2025/26 general fund Capital Programme to £118.481m. 4.2. The following tables summarise the General Fund Capital Programme and how it is to be financed.

2 Table 1: General Fund Capital Programme Monitoring Q3

Agreed Latest Forecast Forecast Current Budget Agreed Out-turn Outturn Year Directorate Feb-25 Budget March-26 Variance Spend £m £m £m £m £m Adults and Health 2.137 2.218 0.797 -1.421 0.217 Children’s Service 22.924 25.069 3.872 -21.197 2.645 Chief Executives 0 25.000 25.000 0 4.587 Corporate 2.663 3.355 2.298 -1.057 0.570 Place 52.927 62.839 24.734 -38.105 10.074 Total 80.651 118.481 56.701 -61.780 18.093 Expenditure

Table 2: Financing the General Fund Capital Programme Monitoring Q3

Forecast Forecast Original Current Out-turn Outturn Funding Type Budget Budget March-26 Variance £m £m £m £m External Borrowing 21.737 24.616 9.517 -15.099 Capital Receipts 2.498 2.276 1.752 -0.524 Reserves 0 0 0 0 Revenue Contribution to Capital 0 0 0 0 Government Grants 54.449 86.584 44.104 -42.480 Other Grants 0.287 0.546 0.083 -0.463 Developer Contributions (S106) 1.680 4.459 1.245 -3.214 Total Financing 80.651 118.481 56.701 -61.780

4.3Appendix1: Adjustments to the 2025/26 General Fund Capital Programme includes the proposed adjustment to individual schemes.

5. Alternative options considered 5.1. Not applicable

6 Financial Implications 6.1 The attached report is primarily financial in nature and the financial implications of the issues raised have been included in the report and its associated appendices.

Implications verified by: Dawn Calvert, Chief Financial Officer S151

Date: 9th February 2026

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme AmendmentsAppendix 1 206 KB Download
PDF
Q3 Financial Outturn Report 2025-26: Amendment to General Fund Capital ProgrammeReport 156 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

42 of 63 attended
SS
Councillor Sue ShinnickMayor, present
SL
Councillor Steve LiddiardDeputy Mayor, present
QA
Councillor Qaisar AbbasCommittee Member, present
NA
Councillor Ngozi AlikeCommittee Member, present
JA
Councillor John AllenCommittee Member, present
AA
Councillor Alex AndersonCommittee Member, present
DA
Councillor Deborah ArnoldCommittee Member, apologies
PA
Councillor Paul ArnoldCommittee Member, apologies
AB
Councillor Alan BensonCommittee Member, present
GB
Councillor Gary ByrneCommittee Member, present
RB
Councillor Ross ByrneCommittee Member, apologies
JC
Councillor John CecilCommittee Member, present

All 63 on the meeting page

On this subject at Thurrock

Search all
  1. Q3 Financial Outturn Report 2025-26 - Amendment to General Fund Capital ProgrammeThis decision
  2. Q1 Financial Outturn 2026/27Noted
  3. Q4 Financial Outturn 2025/26Noted
  4. Q3 Financial Outturn Report 2025-26Noted
  5. Q2 Financial Outturn 2025/26 and Draft Revenue Budget 2026/27 & Medium-Term Financial Strategy 2026/27-2028/29Agreed
  6. Q1 Financial Outturn 2025/26Noted

More from Thurrock Council

All decisions
MeetingDecisionOutcome
30 Sep 2026 Revised Political BalanceRESOLVED Agreed the political balance and allocation of seats, as set out in Appendix 1. Agreed Open
30 Sep 2026 Councillors’ Code of Conduct - Appointment of Independent Persons under s.28 of the Localism Act 2011RESOLVED Authorised the monitoring officer to commence the recruitment of up to three independent persons under s.28 ... Noted Open
30 Sep 2026 Corporate Parenting Committee Annual Report 2025-2026RESOLVED That the contents of the Corporate Parenting Annual Report 2025/2026 were noted. Noted Open
30 Sep 2026 Constitution Review: Key Decision ThresholdRESOLVED For the reasons set out in this report, Full Council is recommended to agree: 2.1 To adopt the amendments to... Agreed Open
30 Sep 2026 Constitution Review: Council and Executive Rules and ProceduresRESOLVED 2.1 For the reasons set out in this report, Full Council is recommended to approve the following re-drafted ... Approved Open