AI summaryThurrock Council approved its Treasury Management Strategy for 2026/27, setting a £1.4bn Authorised Limit and approving borrowing, MRP and investment policies to manage ongoing financial recovery.
The Council's overall financial position and essential services Report P10
Timeline
12 February 2025: Previous Treasury Management Strategy approved by Council Report P11
18 February 2025: Cabinet reviewed the strategy (as stated in report) Report P9
22 July 2025: 2024/25 annual treasury management report approved by Cabinet Report P12
November 2025: Treasury management training organised for members Report P14
17 December 2025: Mid-year treasury management report approved by Cabinet Report P12
25 February 2026: Council meeting approving the strategy Report P2
31 March 2027: End of 2026/27 financial year covered by the strategy Report P11
1 April 2028: Capital expenditure during 2026/27 first subject to MRP charge Report P23
Plain English for the jargon
CIPFA: Chartered Institute of Public Finance and Accountancy
MRP: Minimum Revenue Provision, an annual revenue charge to repay capital debt
CFR: Capital Financing Requirement, the Council's overall capital indebtedness
CD: Capitalisation Direction, exceptional Government support to fund revenue deficit
PWLB: Public Works Loans Board, government lender to local authorities
HRA: Housing Revenue Account, ringfenced landlord account for council housing
EFS: Exceptional Financial Support from Government
LGR: Local Government Reorganisation
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item61
Resolved
RESOLVED The council approved: 2.1 The proposed Treasury Management Strategy and prudential indicators for 2026/27, 2027/28 and 2028/29 in 11.1, 12.4, 15.6, 15.8, 15.9, 16.16 and 17.2. 2.2 The approval of a £1.4bn Authorised Limit in 2026/27 and the following two years, as set out in Section 15.10. 2.3 The proposed MRP Policy for 2026/27 as set out in Section 13. 2.4 The proposed Borrowing Strategy as set out in Section 15. 2.5 The proposed investment policy as set out in Section 16.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Council Report Title Annual Treasury Management Strategy 2026/27
Date of Meeting Wednesday, 25 February 2026
Report Author Richard Dunlop – Interim Accountant
Corporate Director Chief Financial Officer S151
Lead Cabinet Member(s) Cabinet Member for Resources
Why is this a key 1. Expenditure over £500K yes / no decision? 2. Significant impact on 2 or more wards yes /no
Wards Affected All Wards
Is report Urgent? No Appendices (if any) None
1. Executive Summary 1.1 The Council is required to approve a Treasury Management Strategy before the start of each financial year to comply with the Chartered Institute of Public Finance and Accountancy (CIPFA) - Code of Practice on Treasury Management 2021, the CIPFA Prudential Code 2021 and the current MHCLG statutory guidance on both Investments and Minimum Revenue Provision (MRP). 1.2 The Council’s Treasury Management Strategy sets out the parameters for the planned treasury management activity during 2026/27 and so sets out the expected borrowing and investment activity and any restrictions under which the Council’s treasury management team will manage this activity. The strategy reflects the treasury management implications of the Council’s proposed Capital Programme 2026/27 to 2028/29 as set out in a separate report on this agenda. 1.3 Cabinet reviewed this strategy on 18 February 2025 and propose Council approve the recommendations. Any changes made at Cabinet at that meeting will be reported via a supplementary report to Full Council. 2. Recommendations The Council approve: 2.1 The proposed Treasury Management Strategy and prudential indicators for 2026/27, 2027/28 and 2028/29 in 11.1, 12.4, 15.6, 15.8, 15.9, 16.16 and 17.2. 2.2 The approval of a £1.4bn Authorised Limit in 2026/27 and the following two years, as set out in Section 15.10. 2.3 the proposed MRP Policy for 2026/27 as set out in Section 13. 2.4 the proposed Borrowing Strategy as set out in Section 15. 2.5 the proposed investment policy as set out in Section 16.
3. Commissioner’s Comments 3.1 This report is central to the Council’s financial strategy and ongoing recovery. By addressing significant interest rate risks and controlling debt servicing costs, the strategy secures the financial sustainability and liquidity necessary to protect essential services. It balances cashflow optimisation with a rigorous approach to minimising investment losses. 3.2 Commissioners have been consulted and are content for the report to be considered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.