Decision Notice D210023CAB Consideration of recommendations from the meeting of the Planning and Transportation Advisory Board of 11 November 2020 (as set out Minute Number PE 20/25). RESOLVED : That the updated Planning Performance Agreement Charging Schedule 2021/22 (attached at Annex 1 to the report) be adopted.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report of the Director of Planning, Housing and Environmental Health Part 1- Public
Matters for Recommendation to Cabinet - Key Decision
1 REVIEW OF THE PLANNING PERFORMANCE AGREEMENT PROTOCOL
Summary: This report provides a review of the planning performance agreement protocol and sets out the proposed new charges for 2021-2022. It is necessary to review the protocol every year in order to ensure the Council continues to provide a comprehensive, high quality service and that the evidence base remains up to date. The charging schedule should also be considered annually.
1.1Introduction
1.1.1 The current PPA protocol and charging regime was introduced on 01 April 2020 and officers undertook to build in an initial period of review (6 months) to establish how the protocol and associated charging schedule was working in practice.
1.1.2 Linked to this, Members will also be aware of the work ongoing to prepare a Planning Obligations Protocol and undertake the annual review of our pre- application advice service. These items are reported elsewhere on the agenda but it is important to remember that they should run concurrently in order to achieve the best positive outcomes for developer across the Borough.
1.2The current Protocol
1.2.1 The protocol and fee structure, introduced on 01 April 2020 identifies four main development types, as follows:
1) Small development: under 50 dwellings or up to 2,500 sq. m of commercial floor space.
2) Medium development: between 50 and 99 dwellings or 2,500 – 4,999 sq. m of commercial floor space.
3) Large development: between 100 and 249 dwellings or 5,000 – 9,999 sq. m of commercial floor space.
4) Strategic development: over 250 dwellings or 10,000 sq. m of commercial floor space.
P&TAB-KD-Part 1 Public 11 November 2020 2
1.2.2 The schedule then goes on to set out expectations for the number of meetings with officers and Member briefings provided for within the PPA.
1.3Review of current Protocol
1.3.1 To date, there has been reasonable uptake on the use of PPAs and officers are in negotiations with developers continually in order to promote them as a key project management tool, particularly for large and strategic development types. The intention is to utilise the fees collected to assist in resourcing the DM team to ensure the programmes agreed within PPAs can be met whilst continuing to meet and, wherever possible exceed, wider targets for decision making.
1.3.2 Feedback from officers and developers alike has centred on the fact that the protocol and template agreement need to be more explicit around expectations for payment of the fees for PPAs relative to pre-application advice being sought initially and this can be incorporated into a revised document in a straightforward way. Developers should equally be aware of how and when the Council expects payment to be made when they enter into a PPA, and again this will be made more overt through amendments to the protocol itself.
1.3.3 Concern has been raised amongst some officers that the fees for entering into a PPA, particularly for large and strategic developments may not be wholly reflective of the associated work involved. Broadly, it is considered that a longer period of review is needed to accurately capture what any amendments might be in this respect. However, it is already clear that the number of meetings enshrined within the fee charging schedule for strategic developments has been underestimated. Based on recent experiences since the PPA protocol was adopted, it is recommended that this be increased and that there be a fee uplift to reflect this. Furthermore, it would be prudent to also account for the likelihood that Members Site Inspections would be arranged for strategic developments too.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.