Resolved
That the of the meeting of the Cabinet held on 2 September 2025 be approved as a correct record and signed by the Chairman.
Cabinet approved this item on Tuesday 14 October 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the of the meeting of the Cabinet held on 2 September 2025 be approved as a correct record and signed by the Chairman.
TONBRIDGE AND MALLING BOROUGH COUNCIL
CABINET
MINUTES
Tuesday, 2nd September, 2025
Present: Cllr M D Boughton (Chair), Cllr R P Betts, Cllr M A Coffin, Cllr D Keers, Cllr A Mehmet and Cllr M Taylor
*Virtual: Cllrs L Athwal, [name removed], S Crisp, D Harman, [name removed], M R Rhodes and K B Tanner were also present pursuant to Access to Information Rule No 23.
(*participated via MS Teams)
PART 1 - PUBLIC
CB 25/91 DECLARATIONS OF INTEREST
There were no declarations of interest made in accordance with the Code of Conduct.
CB 25/92 MINUTES
RESOLVED: That the Minutes of the ordinary and extraordinary meetings of the Cabinet held on 30 June and 29 July 2025 respectively be approved as a correct record and signed by the Chairman.
MATTERS FOR RECOMMENDATION TO THE COUNCIL
CB 25/93 REPLACEMENT OF SHALLOWS BRIDGE, HAYSDEN COUNTRY PARK
Consideration was given to a List C Capital Plan Evaluation (attached at Annex 1) for the replacement of the Shallows Bridge in Haysden Country Park.
The proposal was to remove the existing Shallows Bridge, which had been condemned by a structural engineer, and to replace it with a new bridge that met the needs of park users and would be compliant with the Disability Discrimination Act.
Due regard was given to the financial and value for money considerations and it was estimated that the replacement of the bridge would be circa £265,000. The potential to utilise developer contributions to meet just over half of the costs was welcomed. As the works were
1 CABINET 2 September 2025
required for health and safety reasons the balance of £112,000 would need to be provided from the Revenue Reserve for Capital Schemes.
Attention was drawn to the potential risk of increased costs arising from an inspection and assessment of the existing abutments by a structural engineer once the existing bridge was removed. It was hoped that the existing abutments would be fit for purpose but if not a full reconstruction could cost in the region of £45,000. In this scenario, Cabinet would be asked to determine if the project was cost prohibitive.
Finally, it was confirmed that the replacement bridge would be stainless steel to increase longevity. It was also reported that the only other option would be not to replace the bridge as a repair was not possible and remove the existing structure.
On the grounds that the replacement bridge would maintain access for users of the Country Park, Cllr Keers proposed, Cllr Taylor seconded and Cabinet
*RECOMMENDED: That
(1) the scheme to replace the Shallows Bridge, Haysden Country Park be transferred to List A of the Capital Plan; and
(2) subject to an assessment of the abutments, the replacement bridge be constructed in the current financial year.
*Recommended to Council
CB 25/94 PROPOSAL FOR MONTHLY MEMBER BRIEFING SESSIONS ON PRE-APPLICATION DEVELOPMENT PROPOSALS
Consideration was given to the recommendations of the Housing and Planning Scrutiny Committee in respect of establishing regular, officer- chaired briefing sessions for Members on pre-application development proposals.
The aim was to enhance Member engagement whilst maintaining confidentiality and integrity of the planning process.
Due regard was given to the views of the Scrutiny Select Committee, the financial and value for money considerations, the assessment of risk and the legal implications. A new charge would be introduced as part of the pre-application charging schedule as detailed in Annex 1. This was reviewed annually to ensure that costs were recovered effectively.
Cabinet welcomed the introduction of early engagement giving Members an opportunity to raise key planning issues and highlight local sensitivities. It was also recognised that the effectiveness of these
2 CABINET 2 September 2025
sessions relied on Members participating and that low attendance could undermine the value of the service.
On the grounds of improving communication and engagement between Members and developers, Cllr Taylor proposed, Cllr Mehmet seconded and Cabinet
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 273 KB | DownloadRead as text |
Follow Cabinet at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | MinutesThat the of the meeting of the Cabinet held on 30 June 2026 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 1 Sep 2026 | Local Government Reorganisation - Establishment of West Kent Joint CommitteeRESOLVED : That (1) the Secretary of State’s decision to proceed with four unitary councils for Kent and Medway, as s... | Noted | Open |
| 1 Sep 2026 | Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro... | Noted | Open |
| 1 Sep 2026 | Risk ManagementRESOLVED : That (1) the updates to the Strategic Risk Register since the last iteration, with particular emphasis on ... | Noted | Open |
| 1 Sep 2026 | Artificial Intelligence Governance Framework PolicyRESOLVED : That (1) the , attached at Annex 1, be approved for adoption and implementation; (2) the establishment and... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.