AI summaryCabinet noted progress on the £19 million replacement of Angel Leisure Centre in Tonbridge and asked the Town Centre Programme Board to consider using any proceeds from the current site to offset borrowing. A fully costed business case will come to Members before final construction approval.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFully costed business case to follow before approval
Money£19m estimated costDown from earlier £23m estimate
What happens nextBusiness case to MembersBefore final construction approval
Who it affectsTonbridge leisure centre users and residentsLargest capital investment by the Council to date
What was decided
The Tonbridge Town Centre Programme Board will consider how any proceeds from redeveloping the current Angel Centre site could be used to offset borrowing for the new centre.
Cabinet noted the intention to present a fully costed business case to Members in advance of seeking approval for the final construction of the replacement centre.
Cabinet noted the progress being made on the replacement project.
Why
The replacement is described as the largest capital investment by the Council to date, with the estimated cost now £19 million, down from a previous £23 million. Report 3.2, 7.1
A refurbishment of the existing centre was previously estimated at up to £15 million but was not considered viable by Cabinet in January 2024 because it would not meet the project's objectives. Report 6.1, 6.2
Officers view a new facility as offering a longer building life, avoiding a significant loss of income during works and retaining market share. Report 6.3
What happens next
A public engagement survey of over 750 responses closed on 24 September 2025, with results to be collated and a verbal update given at the meeting. Report 4.1, 4.2
A full day of interviews with shortlisted building contractors will involve the Cabinet Members for Infrastructure and Tonbridge Regeneration and Finance, Waste and Technical Services. Report 4.4
Subject to Council approval, construction is planned to begin in June 2026 with handover in March 2028, and a final design and cost plan will return to Members after RIBA Stage 4. Report 8.2, 11.1
The money
£19m Estimated cost of replacement facility including build, fees, equipment, contingency and build inflation Report 3.2, 7.1
£23m Previous project cost estimate given at the All Member Presentation Report 3.2
up to £15m Earlier estimate to refurbish the existing Angel Centre Report 6.2, 7.1
£9.15m Balance in the earmarked reserve at the time of writing Report 7.2
around 6.49% PWLB rate quoted for a 40 year loan at the time of writing Report 7.3
Options considered
Chosen: Replace the existing Angel Leisure Centre with a new facility on the Sovereign Way Mid car park. Cabinet considered refurbishment unviable; new build meets project objectives and offers longer life Report 5.1, 6.1, 6.3
Rejected: Refurbish the existing Angel Leisure Centre. Not considered viable by Cabinet at its meeting on 10 January 2024 and would not meet the project's objectives Report 6.1, 6.2
Chosen: Use proceeds from redeveloping the current Angel Centre site to offset borrowing for the new centre. Referred to the Town Centre Programme Board for consideration as part of funding the project
Implications
Financial: Funding is envisaged as a mix of reserves, a Leisure Trust contribution, developer contributions and external borrowing, with PWLB 40 year rates around 6.49%. Report 7.2, 7.3
Financial: Using the Council's own reserve to reduce borrowing would cut investment income receipts and would need to be reflected in the Medium Term Financial Strategy. Report 7.7
Risk: If the Council decides not to proceed after RIBA Stage 4, costs incurred to date would be sunk costs chargeable to revenue. Report 7.6
Risk: Key risks include local government reorganisation and any Government restrictions on Council spending, the Council being unable to fund cost increases, and delays in planning or decision making. Report 8.1, P32, P33, P34, P36
Equalities: The decisions are judged to have a remote or low relevance to the Equality Act, with full equalities, diversity and accessibility consideration to follow through design. Report 12.2
Climate: The Council's Climate Change Officer has been engaged on the Stage 1 Feasibility Study and will continue to be consulted, with sustainability a key aspect of the scheme. Report 12.1, P45
Legal: Advice is being taken from Legal Services and the Mid Kent Procurement Partnership, with procurement guidance ensuring compliance with legislation. Report 9.1, 12.3
Other: The current Angel Leisure Centre will remain operational until the new facility is complete and will then be demolished and considered within the wider town centre master plan. Report 6.3, 12.3
Who and where
Users of Angel Leisure Centre in Tonbridge Report 6.3, 12.3
Tonbridge residents and the local community Report 4.1, 12.3
The Leisure Trust operating the centre Report 3.3, 6.3, 7.3
Alliance Leisure, the Council's development partner Report 3.3, 4.4
The Council's earmarked reserve and revenue budget Report 7.2, 7.7
Timeline
December 2023: Project to replace Angel Leisure Centre began progressing Report 3.1
10 January 2024: Cabinet considered refurbishment not viable Report 6.1
1st September 2025: Presentation made to Tonbridge Community Forum Report 4.2
11 September 2025: Overview and Scrutiny Committee meeting whose recommendations are before Cabinet Report P2
24th September 2025: Public engagement survey closed after a 6 week period Report 4.1
14 October 2025: Cabinet decision
June 2026: Planned construction commencement, subject to Council approval Report 11.1
March 2028: Planned handover of the new facility to the Council Report 11.1
Plain English for the jargon
RIBA Stage 2: The second stage of the Royal Institute of British Architects' plan of work, covering concept design, currently the stage of the Angel Centre project.
PWLB: Public Works Loan Board, a UK government body that lends money to local authorities.
Latent demand: Potential future use of a facility that is not currently being captured, used in the draft business case to model income scenarios.
Sunk costs: Expenditure that has already been incurred and cannot be recovered, which would be chargeable to revenue if the Council did not proceed after RIBA Stage 4.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCB 25/114
Resolved
RESOLVED : That (1) the Tonbridge Town Centre Programme Board give consideration to potential options around how any proceeds arising from the redevelopment of the current Angel Centre site could be used to offset any debt incurred in relation to the provision of the new leisure centre; (2) the intention to present a fully costed business case to Members in advance of seeking approval for the final construction of the Angel Leisure Centre replacement be noted; and (3) the progress being made on the replacement of the Angel Leisure Centre, Tonbridge be noted.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
2.1Members of the Committee are asked to comment on the project and make any recommendations or comments to Cabinet.
3 Introduction and Background
3.1The project to replace the existing Angel Leisure Centre has been progressing since December 2023 and is currently in the RIBA Stage 2 design stage. The slides of the recent All Member Presentation are attached (Annex 1) for information, which gives a comprehensive summary of progress with the project to date. Members of the Committee will recall that all aspects of the project were
OSC - RTCab P1-Public 11 September 2025 2
covered by the presentation including the background, objectives, decision making, timeline, update on current position, costs and finances, public consultation and the way forward.
3.2Members of the Council welcomed the presentation on a project which will represent the largest capital investment made by this Council to date. Members made a range of comments, and a number of changes were made to the public engagement exercise to make the accessibility of the questionnaire as widely available as possible. This included the ability to complete questionnaires at the Angel Leisure Centre and Tonbridge Castle by hand and a presentation at Tonbridge Community Forum. Members noted that the project was now estimated to cost £19m, having previously been estimated to cost £23m. Members particularly welcomed the potential inclusion of new facilities in the design such as soft play and dedicated spin studio.
3.3At the All Member Presentation the full Project Team attended including Officers, Alliance Leisure (the Council’s development partner), the project architect and the CEO of the Leisure Trust. In order for Members of this Committee to ask any questions or raise any issues on the project it is again the intention to have the full team present at the meeting.
4 Progress
4.1Since the All Member presentation good progress has been made with the project as part of the RIBA Stage 2. Most notably the public engagement exercise has commenced. At the time of writing this report over 750 responses have already been received reflecting a strong public interest in the project. The survey is for a 6 week period so will close on 24th September 2025 following which the results will be collated.
4.2A presentation on the replacement Angel Leisure Centre was made to the meeting of Tonbridge Community Forum on 1st September 2025 and a verbal update will be made at this meeting on any issues raised.
4.3Site visits are being planned to other leisure facilities offering the same potential facility mix proposed for the replacement Angel Leisure Centre. This will be invaluable in assisting with determining proposed future operational arrangements including financial performance and market demand.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.