London Borough of Tower Hamlets
Cabinet, Tuesday 24 March 2026

Whitechapel Leisure Centre - Redevelopment

Approved Executive 2 papers

AI summaryTower Hamlets Cabinet approves a budget to appoint a design team for the Whitechapel Leisure Centre redevelopment, with the cost split 70% leisure and 30% housing.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedFor Whitechapel Leisure Centre redevelopment
MoneySpecific figure not statedSplit 70% Leisure, 30% Housing
What happens nextDesign development to RIBA 3Then planning application
Who it affectsWhitechapel area residents and usersSite combines leisure and housing

What was decided

Approved a budget to procure and appoint a design team and all associated professional services and surveys, including internal project management, required to prepare and submit a planning application for the Whitechapel Leisure Centre redevelopment.

The cost will be met from the CIL feasibility and HRA feasibility budgets for 2026/27, proportionately split 70% leisure and 30% housing.

Engagement with TfL and other stakeholders will begin, public consultation on the redevelopment proposals will be carried out, and authority to appoint the design team is delegated to the Corporate Director of Housing and Regeneration in consultation with the Mayor.

Why

The decision enables design development to RIBA stage 3, with more detailed survey information intended to reduce risk before a planning application.

The Strategic Leisure Needs Assessment records a 1,723 sqm water space deficit in 2023, rising to 1,845 sqm by 2038, and over 12,000 swims per week displaced outside the borough.

The existing centre is ageing and below modern standards, and forecast population growth of 26% by 2038 requires expanded capacity.

What happens next

Cabinet will return to the project once more detailed feasibility work has been carried out.

Public consultation on the redevelopment proposals will be carried out.

Gateway approval processes will operate at the end of each RIBA design stage: feasibility, concept design, and coordinated design.

Options considered

  • Chosen: Full redevelopment with housing. Delivers the SLNA's recommended new pool and modern leisure provision, supports housing delivery, health outcomes and long-term financial sustainability.
  • Rejected: Do nothing. Fails to address a strategic gap in swimming provision at a priority site identified for a new 6 lane pool.
  • Rejected: Retain and refurbish the existing centre. Cannot deliver the required new 6 lane x 25m pool and learner pool, and the existing structure cannot accommodate a swimming facility.
  • Rejected: Remove the housing element. Conflicts with the commitment to deliver 4,000 affordable rented homes and reduces scheme viability.

Implications

  • Financial: The 70/30 cost split between leisure and housing will be drawn from CIL feasibility and HRA feasibility budgets for 2026/27.
  • Governance: Authority to appoint the design team is delegated to the Corporate Director of Housing and Regeneration in consultation with the Mayor.
  • Other: Locating housing on the site is expected to support regeneration and help fund the leisure components.
  • Staffing: Internal project management is included within the design team procurement.

Who and where

  • Whitechapel Leisure Centre users
  • Borough residents, with over 12,000 swims per week currently displaced outside the borough
  • Future residents of new housing proposed for the site
  • TfL and other stakeholders involved in design engagement

Timeline

  • 2026/27: CIL feasibility and HRA feasibility budgets used for design team costs
  • Next stage: Design development to RIBA stage 3
  • After detailed feasibility: Cabinet return to the project
  • Future: Planning application submission for the redevelopment

Plain English for the jargon

  • RIBA: Royal Institute of British Architects; the design stages are feasibility, concept design and coordinated design
  • CIL: Community Infrastructure Levy, used here for the leisure share of feasibility costs
  • HRA: Housing Revenue Account, used here for the housing share of feasibility costs
  • SLNA: Strategic Leisure Needs Assessment, the evidence base for swimming and leisure demand
  • TfL: Transport for London, a stakeholder in design development
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6.11

Resolved

DECISION ; 1. APPROVED a budget set out in Appendix 1 to procure and appoint a design team and all associated professional services and surveys (including internal Project Management) required to progress the designs and prepare and submit a planning application for the redevelopment of the Whitechapel Leisure Centre. This cost will be met from the CIL feasibility and HRA feasibility (2026/27) budgets and will proportionately split 70% Leisure and 30% Housing 2. COMMENCED engagement with TFL and any other stakeholders to enable design development. 3. Carry out public consultation with regards the redevelopment proposals. 4. DELEGATED authority to the Corporate Director of Housing and Regeneration in consultation with the Mayor to proceed to appoint a design team and other professional services as required with appropriate “gateway” approval processes in place at the end of each RIBA design stage (feasibility, concept design and coordinated design). Reasons for the decision • The Mayor and Cabinet is recommended to approve budget set out in Appendix 1 to enable the next stage of design development for Whitechapel Leisure centre enabling design development to RIBA stage 3 which will incorporate more detailed survey information derisking project proposals ahead of a planning application. • Permission to proceed to the next stage of the project development and come back to cabinet once more detailed feasibility in carried out. Alternative options Option 1: Do Nothing – Not Viable • The SLNA evidences a borough-wide undersupply of swimming provision, with a 1,723 sqm water space deficit in 2023, increasing to 1,845 sqm by 2038. • Over 12,000 swims per week are displaced outside the borough. • Whitechapel is identified in the SLNA as a priority site for a new 6 lane pool; doing nothing fails to address this strategic gap. • The existing leisure centre is ageing and below modern standards, requiring major reinvestment. Option 2: Retain and Refurbish Existing Centre – Not Recommended • Refurbishment cannot deliver the new 6 lane x 25m pool and learner pool required to meet demand. • The existing structure cannot accommodate a swimming facility. • Population growth of 26% by 2038 requires expanded capacity, which refurbishment cannot provide. • Refurbishment maintains an ageing asset with high lifecycle costs and fails to meet inclusivity, accessibility, and energy-efficiency targets. Option 3: Remove Housing – Not Recommended • Tower Hamlets has one of the highest housing needs nationally, including commitments to deliver 4,000 affordable rented homes. • Whitechapel North and South are strategic growth sites identified in the Local Plan. • Removing housing conflicts with housing targets and reduces scheme viability. • Housing co-location supports regeneration and helps fund the leisure components. Preferred Option : Full Redevelopment with Housing • Delivers the SLNA's recommended new pool and modern leisure provision. • Supports growth, health outcomes, affordable housing delivery, and long-term financial sustainability. Action by: CORPORATE DIRECTOR FOR HOUSING & REGENERATION (D. JOYCE)
Word for word from the decision Tower Hamlets published for this meeting. Source: democracy.towerhamlets.gov.uk

Follow this further

Built from Tower Hamlets's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Finance BreakdownAppendix 1 49 KB Copy on its way
PDF
Whitechapel Leisure Centre: RedevelopmentReport 204 KB Copy on its way

More from Tower Hamlets Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 6th Floor of Town Hall LettingDECISION: 1. Grant permission for a 15 years lease to London Air Ambulance 2. To delegate authority to the Corporate ... Agreed Open
23 Sep 2026 Cressy PlaceDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Caxton GroveDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Brunton Wharf housing schemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open
23 Sep 2026 Copenhagen Place SchemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies