London Borough of Tower Hamlets
Cabinet, Tuesday 24 March 2026

Harriott, Apsley & Pattison (HAP) Houses Regeneration Scheme – Development Agreement & Contract Award

Agreed Executive 3 papers

AI summaryCabinet authorises the Corporate Director of Housing and Regeneration to sign a Development Agreement with Vistry Group to deliver 407 new homes and a community centre at the HAP estate.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeAgreedcovers delivery of 407 new homes and a community centre
MoneyNot stated
What happens nextPhase 1 construction contract awardVistry Group leads delivery; council appoints consultants
Who it affectsHAP estate residents and new residentsseven existing blocks replaced with 407 new homes

What was decided

Cabinet authorised the Corporate Director of Housing and Regeneration, in consultation with the Mayor, to enter into a Development Agreement and sign the Phase 1 construction contract with Vistry Group, following a successful Second Stage tender via a Pre-Construction Services Agreement.

Cabinet delegated authority to the same officer to appoint any necessary consultants, to proceed with site remediation works for Phase 1 under the existing Minor Works Contract, and to enter into the ESCo agreement and relevant leases, in consultation with the Mayor where stated.

Cabinet noted that the Development Agreement covers the full project across Phase 1 and Phase 2, and that the ESCo agreement is performance-based, with a specialised firm financing the upfront costs and guaranteeing that savings will cover the investment.

Why

The scheme will deliver 407 new homes and a new community centre on council-owned land currently occupied by seven housing blocks of between four and eight storeys (Harriott House, Apsley House and Pattison House), comprising 68 flats, 32 maisonettes and 2 community buildings.

A resident ballot between 18 March and 9 April 2020 saw 123 of 132 eligible voters cast a vote, a 93% turnout, with 121 residents (98.4%) voting in favour of regeneration and 2 (1.6%) voting against.

Of the 407 homes, 59 are replacement homes and 116 are additional affordable homes (50 in Phase 1 and 66 in Phase 2), with 22 of the additional affordable homes identified for hidden households on the estate. The overall mix is 43% affordable (175 homes) and 57% open market (232 homes).

What happens next

Vistry Group will lead construction delivery for both phases in consultation with the council.

Site remediation works for Phase 1 will proceed under the existing Minor Works Contract.

The Corporate Director of Housing and Regeneration will enter into the ESCo agreement and relevant leases, in consultation with the Mayor.

Implications

  • Legal: Wide delegation of authority to the Corporate Director of Housing and Regeneration, with Mayor consultation on key decisions.
  • Financial: The ESCo agreement is performance-based: the firm finances upfront costs and guarantees that savings will cover the investment.
  • Equalities: 22 of the additional affordable homes are identified for hidden households on the estate to address localised overcrowding.
  • Risk: New homes will replace blocks with ongoing damp issues and repair costs, providing improved fire safety, higher thermal performance, lower energy use, balconies for every home, and new communal and community garden spaces.

Who and where

  • Existing residents of Harriott House, Apsley House and Pattison House, who will receive replacement homes
  • New residents moving into the 116 additional affordable homes and 232 open market homes
  • 22 hidden households on the estate identified for new affordable homes

Timeline

  • 18 March to 9 April 2020: Resident ballot on regeneration held
  • 24 March 2026: Cabinet decision taken

Plain English for the jargon

  • HAP: Harriott, Apsley and Pattison Houses, the three existing housing blocks on the estate
  • ESCo: Energy Service Company: a firm that implements energy-efficiency projects, finances the upfront costs and guarantees that savings will cover the investment
  • Vistry Group: The development partner, formerly referred to in earlier stages as the development partner
  • Pre-Construction Services Agreement: An agreement under which a contractor undertakes early design and pre-construction work ahead of a Second Stage tender
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6.9

Resolved

DECISION ; 1. AUTHORISED the Corporate Director of Housing and Regeneration in consultation with the Mayor to enter into a Development Agreement and execute the Phase 1 construction contract with Vistry Group following the successful completion of the Second Stage tender via a Pre-Construction Services Agreement. Under the terms of the Development Agreement and in consultation with the Council, Vistry Group (formerly known as the development partner) shall lead on the construction delivery of Phase 1 & 2. 2. DELEGATE Authority to the Corporate Director of Housing and Regeneration in consultation with the Mayor, the authority to appoint any necessary consultants required to assist the Council in the delivery of the project. 3. Noted the Development Agreement shall include the delivery of the complete project including Phase 1 & Phase 2. 4. DELEGATED Authority to the Corporate Director of Housing and Regeneration, the authority to proceed with site remediation works, required to deliver Phase 1, under the existing Minor Works Contract. 5. DELEGATED Authority to the Corporate Director of Housing and Regeneration in consultation with the Mayor, the authority to enter into the ESCo (Energy Service Company) Agreement and relevant leases relating to the regeneration. 6. Noted the ESCo agreement is a performance-based contract where a specialised firm implements energy-efficiency projects, financing the upfront costs and guaranteeing that savings will cover the investment. Reasons for the decision • The decisions sought in this report are to enable the delivery of 407 new homes and a new community centre, on council-owned land currently occupied by seven housing blocks between 4 and 8 stories (known collectively as Harriott House, Apsley House and Pattison House), comprising 68 flats, 32 maisonettes, and 2 community buildings. • A Resident Ballot was held between 18th March and 9th April 2020. Of the 132 eligible voters, 123 votes were cast, a turnout of 93%. 121 residents voted in favour of regeneration (98.4%) and 2 (1.6%) residents voted to reject the council’s proposal, demonstrating strong community support. • Of the 407 homes to be delivered by the scheme, 59 are allocated as replacement homes; a further 116 additional affordable homes will be delivered within the scheme (50 under Phase 1 and 66 under Phase 2), housing new residents to the estate, as well as helping to address overcrowding within the existing homes. 22 of these homes have been identified for hidden households across the estate, ensuring that the scheme tackles the localised overcrowding in the community, as well as serving the borough’s wider affordable housing needs. • The scheme delivers policy-compliant 43% (175 no.) affordable housing alongside 57% (232 no.) open market homes, meeting strategic targets with substantial net affordable housing gain. The affordable housing mix is comprised of social rent, shared ownership, and shared equity homes. • The new homes will replace older blocks with ongoing damp issues and repair costs, instead providing homes with: greatly improved fire safety measures, high thermal performance and the lower energy use this enables, large balconies for every home, new communal place spaces and community gardens, secure ...
Word for word from the decision Tower Hamlets published for this meeting. Source: democracy.towerhamlets.gov.uk

Follow this further

Built from Tower Hamlets's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix. 1 for Harriott, Apsley & Pattison (HAP) Houses Regeneration Scheme: Development Agreement & Contract AwardAppendix 60 KB Copy on its way
PDF
Appendix. 2 for Harriott, Apsley & Pattison (HAP) Houses Regeneration Scheme: Development Agreement & Contract AwardAppendix 68 KB Copy on its way
PDF
Harriott, Apsley & Pattison (HAP) Houses Regeneration Scheme: Development Agreement & Contract AwardReport 215 KB Copy on its way

At this meeting

Whole meeting

On this subject at Tower Hamlets

Search all
  1. Harriott, Apsley & Pattison (HAP) Houses Regeneration Scheme – Development Agreement & Contract AwardThis decision
  2. Harriott, Apsley & Pattison (HAP) Houses Regeneration Scheme - Resolution to make a Compulsory Purchase OrderAgreed
  3. Harriott, Apsley & Pattison (HAP) Houses Regeneration Scheme - Two Stage Tender NegotiationNoted
  4. Harriott, Apsley, Pattison (HAP) Houses Regeneration Scheme UpdateApproved
  5. Harriott, Apsley & Pattison (HAP) Houses Regeneration SchemeNoted

More from Tower Hamlets Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 6th Floor of Town Hall LettingDECISION: 1. Grant permission for a 15 years lease to London Air Ambulance 2. To delegate authority to the Corporate ... Agreed Open
23 Sep 2026 Cressy PlaceDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Caxton GroveDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Brunton Wharf housing schemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open
23 Sep 2026 Copenhagen Place SchemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies