Resolved
RESOLVED - That the works programmes associated with the allocation of capital funds for 2021/22 as outlined at Appendix A, B, C and D of the report be approved.
Executive approved this item on Monday 21 June 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the works programmes associated with the allocation of capital funds for 2021/22 as outlined at Appendix A, B, C and D of the report be approved.
This report seeks to update members in more detail of what schemes are being proposed as part of the current capital programme that includes
1. Updated list of highway capital works following a revised capital allocation via TfGM in February 2021. 2. Breakdown of works to be progressed as part of the parks and greenspace capital allocation. 3. Breakdown of works to be progressed as part of the traffic and transportation TfGM allocation.
Recommendation(s)
The Executive is recommended:
To approve the works programmes associated with the allocation of capital funds for 2021/22 as outlined at Appendix A, B, C and D of this Report.
Contact person for access to background papers and further information:
Name: Sharon Walls Email: [email protected]
Background Papers: None.
1 Implications:
Relationship to Policy Value for Money Framework/Corporate Priorities Relationship to GM Policy or Improved and safer facilities for road users Strategy Framework including cyclists aligns with the Greater Manchester Transport 2040 Strategy and complements work on the Mayor’s Challenge Fund Financial Planned capital expenditure over the next 12month period will be contained within available capital resources Legal Implications: None arising out of this report. Equality/Diversity Implications In approving the detail of schemes proposed through the capital programme the Council will need to ensure that any decisions are made fully in accordance with its Public Sector Equality Duty Sustainability Implications The indicative capital programme includes a number of proposals that will aid the Council in its environmental sustainability objectives, Resource Implications e.g. Staffing Improvement schemes are being undertaken in / ICT / Assets 2021/22 Risk Management Implications None directly arising Health & Wellbeing Implications The proposed capital programme includes a number of schemes that seeks to provide a positive impact on the Health and Wellbeing of Trafford’s residents, including improvements to play area infrastructure across the borough Health and Safety Implications A number of schemes are being undertaken on the grounds of health and safety including resurfacing roads Various budget proposals in the capital budgets Carbon Reduction support the carbon neutral action plan.
1.1The Executive and Council approved the council’s budget including capital allocations as contained in the report of 17 February 2021.
1.2Attached at Appendix A and B is a more detailed programme of works for the highways capital programme following a reduction in grant from the Dft via TfGM. This late change in funding of circa £1.2million allocation has altered the number and range of proposed schemes previously contained in the report of February 2021.
1.3Also attached at Appendix C is a more detailed programme for the Parks budget allocations including Play Area refurbishments, Parks Infrastructure and Parks and Open Space programmes that were not included in the report in February
1.4A more detailed programme of traffic and transportation works is attached at Appendix D that indicates sites that will be included in this area of work.
2 1.5 The list of schemes in Appendix A-D currently exceeds the total budget in recognition of further work being undertaken with GMCA to secure extra funding from existing and future central government funding initiatives.
2.0Approval of Capital Programmes
2.1Trafford Council approved its capital allocations in February 2021 however the detailed programme for some elements of the programme were not finalised hence is included within this report.
2.2The highways capital programme has had to be reviewed as a result of a late change in allocation of grant funding of circa £1.2m. This in effect was a 25% reduction in allocation for highway investment.
Other Options
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME 2021/22: SCHEME APPROVALSReport | 636 KB | DownloadRead as text |
Follow Executive at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... | Approved | Open |
| 21 Sep 2026 | Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... | Approved | Open |
| 20 Jul 2026 | Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... | Approved | Open |
| 20 Jul 2026 | Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... | Approved | Open |
| 15 Jun 2026 | Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.