DECISION MADE: 1. That the actual expenditure on capital schemes to 31 December 2010 be noted; 2. That the increases and decreases to the capital programme as set out in notes 5 to 7 and notes 9, 10, 12 and 13, be approved; 3. That the deferral of capital schemes to 2011/12 as set out in note 8 be approved; and 4. That individual Portfolio Holders work with their lead officers to submit a further report on deferred capital projects in their areas. Reasons for decision: All of the increases have already received approval in other meetings as stated or have been spent. The new process for managing the capital programme is still resolving some outstanding historical issues and will ensure they do not recur. Contact Officer: Jane Fineman , Financial Services Manager Tel: 01892 526121 or e-mail: [email protected]
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Item No. 11C Quarter 3 - Capital Management to 31 December 2011 (110224/CAB006) To: Cabinet
24 February 2011
Main Portfolio Area: Finance and Governance
Author of report: Jane Fineman, Financial Services Manager
Classification: Non-Exempt
Ward: All
Executive summary This report compares capital projects approved by Cabinet with actual capital expenditure to the 31 December 2010 and the projected outturn for the year.
The Capital Programme for the years to 2013/14 has been created through a formal application and approval process. All new schemes must be agreed by Cabinet before they can be included in the Capital Programme. In Quarter 2 Cabinet approved a total of £32,582,000 capital spending, of which £26,058,000 was due to be spent in 2010/11.
The actual expenditure to December 2010 was £1,397,000, £677,000 of this spent in Quarter 3. This expenditure has been partially offset by the reversal of a provision made in 2003/04 for £197,897 for the Skinners Academy. Therefore, year to date, the actual expenditure is £1,199,000. This report now shows that £25,041,000 is now expected to be spent in 2010/11.
This indicates that a further £1,342,000 is expected to be spent in the following 3 months, excluding the total property acquisition provision of £22,500,000.
This report seeks to obtain formal approval for the adjustments to the 2010/11 gross and net spending forecast outturn and the proposed transfer of schemes between years.
Corporate priorities
The report supports the priority of “Ensuring that we are well managed, proactive and deliver value for money services”.
Report status
For Decision.
Route to implementation/Timetable: Cabinet can make these decisions.
110224/CAB006 11C - 2
Introduction
(1)At their meeting on 10 June 2010, Cabinet approved schemes to be met from the Capital Programme for the years from 2010/11 to 2013/14.
(2)The figures approved by Cabinet were on the basis of the net cost to be met by the Council, either from reserves or from the sale of existing assets. These have been adjusted to a gross basis, showing the total proposed capital investment of £12,557,000 during that period, of which £7,733,000 was to be spent during 2010/11.
(3)Appendices A and B set out in gross and net terms the amounts approved, actual spend to December 2010 and forecasts for the year. They also show variances of actual to forecast and detail that expenditure which is re-scheduled into 2011/12.
(4)The table below shows how the approved capital expenditure has evolved, incorporating the approvals obtained up to and including the November 2010 Cabinet.
Approved Capital Spend as at £000's 30 November 2010
Original gross approvals 7,733 Depot Bore Hole - Delegated Decision 2/12/09 30 Kerbside Containers - Reduced carried forward budget (3) IT Strategy - Reduced carried forward budget (11) Southwood Road Play Area - Non Key Portfolio Holders 11/3/08 9 Total approvals as at Quarter 2 7,758
Capital Acquisitions -14 July Full Council 20,000 Speldhurst Recreation Ground - June 10 Cabinet 17 Cranbrook Scout Hut - June 10 Cabinet 4 Frittenden Memorial Hall - June 10 Cabinet 2 Hawkhurst Bowls Club - June 10 Cabinet 25 Village Hall Langton Green - 6 December 2006 approved 18 Performance Reward Grant - October 10 Cabinet 4 Heritage Partner Grants - October 10 Cabinet (20) Goudhurst Pavilion - October 10 Cabinet (50) Slippage to 2011/12 - October 10 Cabinet (1,700) Total approvals as at Quarter 3 26,058
New Budget Approvals
(5)On the 15 October 2010, Cabinet approved £9,500 for a dimmer rack lighting system for the Trinity Theatre and £2,500 for the Bidborough Bowls Club pavilion roof. These approvals require additional budget provision for 2010/11 in the Community Investment Fund (TCE).
(6) In the October 2010 Cabinet, approval was also given for £25,000 to fund a village hall extension for the Langton Green Charitable Trust. The project will not commence until 2011/12, so is reflected in the forecast for 2011/12.
110224/CAB006 11C - 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.