CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tunbridge Wells Borough Council
Cabinet, Thursday 24 February 2011 at 10.30am

Banking Tender

Decided Executive 1 paper

Cabinet decided this item on Thursday 24 February 2011. Below is the council's own wording, with the papers it was decided on.

ItemCAB177/10

Resolved

DECISION MADE: 1. That the preferred bidder shown in the exempt report on the agenda be awarded the contract for banking services and associated charges for a period of five-years from 1 April 2011; and 2. That the preferred bidder shown in the exempt report on the agenda be awarded the contract for card fulfilment services and associated charges for a period of five-years from 1 April 2011. Reasons for decision: To benefit from substantial cost savings over the next 5 years and to comply with purchasing legislation. Contact Officer: Jane Fineman , Financial Services Manager Tel: 01892 526121 ext 3154 or e-mail: [email protected]
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Executive summary

The present banking contract with HSBC expires on the 31st March 2011.

There has been a formal OJEU tender process, led by the Maidstone Procurement Department under the aegis of the Mid Kent Improvement Partnership. The tender was for a 5 year contract for Corporate Banking Services for either Tunbridge Wells Borough Council alone or jointly with Swale Borough Council.

6 bids were received and all financial and qualitative responses have been assessed in line with EU procurement regulations.

Tunbridge Wells Borough Council will be contracting alone as Swale Borough Council has not completed their assessment. This will not disadvantage either party as there were no benefits proposed by the preferred bank for contracting jointly.

Corporate Priorities

The report fully supports the Council's commitment “Prosperous” in that they reflect that the Council is well managed, proactive and deliver value for money services.

Report status

For decision

Route to Implementation/Timetable:

Cabinet agree to the acceptance of the tender.

110224/CAB012 11F - 2

Background

1. The existing banking contract with HSBC was extended for 5 years following a report to Cabinet (020822/CAB051) in August 2002; and a further extension was granted by Cabinet in September 2009 which will expire on the 31 March 2011.

2. The provision of banking services is subject to full OJEU procurement obligations as the estimated contract sum exceeds £156,442, as set out in Part A, Category 6 Service under the EU Procurement Directive.

3. A review of service requirements was undertaken prior to tendering. Process changes have allowed a reduction in the number of bank accounts from 4 to 2. Finance has also been working hard to reduce the number of cheques payments made in order to avoid the cost of printing TWBC specific cheques. The tender assumes the use of a standard cheque book.

4. The intention is for the new contract to be in place by the 1st April 2011.

5. The Mid Kent Improvement Partnership placed an OJEU notice for Corporate Banking Services on the 29th September 2010. Tenders were sought for either separate or joint bids for Tunbridge Wells and Swale Borough Councils. This was to explore whether there would be any benefits to increasing the size of the contract available and to share the costs of procurement.

6. 6 tender submissions were received on the 22nd November 2010 and subsequently, many points of clarification were resolved. All qualitative and quantitative assessments have now been completed for Tunbridge Wells Borough Council (TWBC) and a clarification meeting has taken place with the preferred bidder.

7. At this point Swale Borough Council is unable to proceed, so TWBC will be contracting alone. This of no consequence to the preferred bid as there were no benefits proposed resulting from a joint contract.

Proposal

8. It is proposed that the Council contracts with the preferred bidder for both its banking and credit and debit card fulfilment services. They scored highly in their qualitative assessment.

9. The Council stated in the tender that it could choose to award the card business separately from the banking services although there are administrative advantages of contracting them together. The prices provided by the preferred bidder were the cheapest of the 6 tenders on the basis of the forecast volumes of transactions in 2010/11 for each card type and payment method (i.e. internet, card not present, chip and pin).

110224/CAB012 11F - 3

Treasury Management Policy and Strategy

10. Contracting with the preferred bidder will not require any amendment to the Treasury Management and Policy Strategy.

Cross cutting issues

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Banking TenderReport 73 KB DownloadRead as text

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies