Cabinet, Thursday 24 February 2011 at 10.30am

Quarter 3 Governance Report

Decided Executive 1 paper

Cabinet decided this item on Thursday 24 February 2011. Below is the council's own wording, with the papers it was decided on.

ItemCAB173/10

Resolved

DECISION MADE: 1. That each recommendation be dealt with individually within each of the reports detailed below. REASONS FOR DECISION: Each report contains its own recommendations. Contact Officer: Paul Taylor, Director of Change and Communities Tel: 01892 526121 or e-mail: [email protected]
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Executive summary

Cabinet has for some time received a range of reports on a regular basis that, between them, paint a picture of the way in which the Council is performing and being governed. These reports are coordinated at quarterly ‘governance’ meetings of Cabinet and the covering report identify the main issues that Cabinet need to consider arising from the following reports:

Quarter 3 2010/11 Performance Report Quarter 3 2010/11 Capital Management report Quarter 3 2010/11 Revenue Monitoring Report Quarter 3 2010/11 Treasury and Prudential Indicator Management Report

Reports on Complaints and Risk Management are submitted as part of Q1 and Q4 and are therefore not included here.

Corporate Priorities

This covering report and the reports to which it relates support all of the Council’s priorities by ensuring that it is well governed, that the Council’s financial position is sound, and that key performance indicators are on track and that risks above tolerance are being proactively managed.

Report status

For decision.

Route to Implementation/Timetable:

All of the recommendations are within the budgetary and policy framework so any recommendations will be implemented after the call-in period has expired.

110224/CAB004 11A - 2

Report of Director of Change and Communities continued

Background/Introduction

1. Each quarter Cabinet consider performance reports and reports on the financial health of the Council. Every six months, Cabinet also consider reports related to complaints and Strategic Risks. These reports also get considered by the Corporate Services Select Committee, the Audit Committee and Standards Committee (where relevant).

Performance

2. Over the last quarter performance has improved within the Healthy and Confident priorities, remained the same in the Prosperous and Green priorities and only slightly worsened within the Corporate Commitments.

Prosperous Green Healthy Confident Corporate Commitments

Reds Q1 2 0 4 2 4

Greens Q1 2 2 10 3 10

Reds Q2 2 0 6 2 4

Greens Q2 2 2 8 3 10

Reds Q3 2 1* 4 0 5

Greens Q3 2 3* 10 5 9

Position Remains the Remains the Improved Improved Slight decline same same

3. Details of individual indicators by priority are shown in the appendix of the detailed .report

Business Delivery Unit

4. The Business Delivery Units projects are progressing well. Ten projects from the BDU programme have already been successfully delivered. There are currently eleven live projects being operated in the programme. Eight of these are on schedule, three are ‘amber’ and one is currently on hold.

ID PROJECTS RAG TYPE BDU CAPACITY 0002 Digital Pen GREEN BDU CAPACITY 0003 Unified debt recovery GREEN

110224/CAB004 11A - 3

BDU SAVINGS 0004 Joint Rev and Ben service GREEN BDU CAPACITY 0006 Customer profiling (MOSAIC) GREEN BDU SAVINGS 0007 NI14/”Tell us once” pilot GREEN BDU SAVINGS 0008 Committee software AMBER BDU SAVINGS 0011 Corporate scanning Not yet started BDU CAPACITY 0012 HR BPR GREEN BDU CAPACITY 0014 Urban Parishing GREEN BDU CAPACITY 0015 HR specific projects Not yet started BDU SAVINGS 0016 HR/Payroll system AMBER BDU CAPACITY 0019 Census 2011 GREEN BDU CAPACITY 0022 Project Intranet AMBER BDU SAVINGS 0023 Self Serve Parking On Hold

5. Since the start of the programme, ten projects have closed and are now in the benefits realisation phase.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 3 Governance ReportReport 193 KB DownloadRead as text

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies