That the outturn position for the year and the variances to the revised budget and forecast outturn as at quarter 3 are acknowledged; 2. That the establishment of a new Municipal Mutual earmarked reserve to hold £14,000 to provide for the possibility of having to meet a greater level of insurance claims (see note 16 of the report) is approved; and 3. That the establishment of a new Land Charges Refund earmarked reserve to hold £90,000 to provide for any refunds (see Note 17 of the report) is approved. REASON FOR DECISION: To recognise the unaudited revenue expenditure and impact on reserves for the year ending 31 March 2013. 1. That the outturn position for the year and the variances to the revised budget and forecast outturn as at quarter 3 be acknowledged; 2. That the establishment of a new Municipal Mutual earmarked reserve to hold £14,000 to provide for the possibility of having to meet a greater level of insurance claims (see note 16 of the report) be approved; and 3. That the establishment of a new Land Charges Refund earmarked reserve to hold £90,000 to provide for any refunds (see note 17 of the report) be approved. REASON FOR DECISION: To recognise the unaudited revenue expenditure and impact on reserves for the year ending 31 March 2013.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report shows the unaudited outturn expenditure on services compared to the revised budget for the year ended 31 March 2013, and the forecast outturn position as at quarter 3.
The actual outturn shows an underspend to the revised services budget of £134,000. This comprises a £132,000 improvement in revenue income and a £24,000 saving in other costs, partially offset by a £22,000 overspend on staff costs.
The actual contribution back to the General Fund is only £6,000 however, as there have been a number of transfers from revenue to earmarked reserves in order to set funds aside for specific issues that could impact the revenue budget next year. This is a remarkable achievement considering it includes the impact of the dissolution of the John Laing partnership at a cost of £292,000 and avoids the budgeted transfer of £90,000 funding from the General Fund. Officers have worked very hard throughout the year to ensure that the Council’s revenue budget was, once again, fully funded without finance from the General Fund.
LINK TO STRATEGIC COMPASS
This report supports the Value and Community quadrants of the strategic compass in particular that we manage public finances effectively.
Report status
For decision
Route to Implementation/Timetable:
Cabinet can make these decisions
Portfolio Holder Decisions I confirm that I have read the report and approve it for publication.
Signed: Councillor James Scholes Dated: 6 June 2013 BACKGROUND/INTRODUCTION
(1) This report shows the unaudited revenue actual outturn for the period ended 31 March 2013 and highlights the significant changes from the approved revised budget.
(2) The actual outturn Net Expenditure on Services shows an underspend of £134,000 on the revised budget. However, only £6,000 will be returned to the General Fund. Whilst £154,000 additional interest and £47,000 additional grants were received, this was offset by transfers to earmarked reserves totalling £329,000. The explanations for these transfers are explained below.
WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?
Summary Outturn – See Appendix B (3) Appendix B shows the overall unaudited net expenditure on services outturn position as at 31 March 2013. Total income and expenditure on services can be seen in greater detail within Appendix C, which provides further detail per service area. The approved budget was set by Council on 22 February 2012 and does not change. The revised budget is used to record virements amongst service areas and to/from reserves, whilst the forecast outturn is used to record the reporting of savings, overspends and allocations from reserves.
(4) It can be seen that the actual outturn is £134,000 below the revised budget for Net Expenditure on Services. This is a significant improvement on the quarter 3 forecast outturn, which anticipated an overspend of £188,000. The variances are detailed in the Key Variances table in Appendix D.
(5) The net interest forecast from investments increased by a further £4,000 in quarter 4, totalling £124,000 over budget for the year. This was partially due to the re-scheduling of the capital programme, leaving more funds available for investment, and partially achieving a higher average rate of interest than budgeted. There has been a decline in the interest rates available that maintain compliance with the investment strategy. The average rate has fallen from 1.99% in quarter 1 to 1.93% in quarter 4 and the market looks much more challenging as we move into 2013/14. However, considering the state of the market and the budgeted average rate of 1.72%, achieving 1.93% is still an exceptional investment performance over the year. The additional interest received has been transferred to the Strategic Plan Reserve.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.