RESOLVED 1. That funding of up to £40,000 is allocated from the Environmental Enhancements budget to enable the proposed street scene enhancement works to be designed and carried out. REASONS FOR DECISION To enable the interim works to declutter the street furniture area around Five Ways and the Millennium Clock in Royal Tunbridge Wells and test out samples of material for use in future schemes, throughout the town centre.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report seeks the approval of funding to enable the final design and implementation of an interim scheme of works to declutter street furniture and to install a number of samples of materials at Five Ways Tunbridge Wells to test their suitability for future enhancement schemes.
LINK TO STRATEGIC COMPASS
This proposal forms part of the Community Quadrant project to introduce a programme of environmental enhancements and work with Kent County Council to declutter and improve the appearance of street furniture.
Report status
For decision
Route to Implementation/Timetable:
The works will be commissioned in conjunction with Kent County Council’s Highway and Transportation.
Portfolio Holder Decision
I confirm that I have read the report and approve it for publication
Signed: Councillor P Barrington-King Dated: 6 June 2012 BACKGROUND/INTRODUCTION
1. In support of the draft Transport Strategy and the Strategic Compass project to improve the appearance of street furniture, proposals for public realm enhancements and shared space for the Five Ways/Millennium Clock area of Royal Tunbridge Wells are being developed. The wider shared space proposals for the Fiveways area will be the subject of a further report but, in the interim, the Locality Board has supported an initial scheme to remove street furniture at this location and install trial samples of materials to assess their suitability.
The proposed works have been developed with the input of colleagues at Kent County Council and include:
Remove all bollards from Lime Hill Road loop road, (retaining 2 no bollards adjacent to drop kerb). Remove all bollards from Mount Pleasant Road, (retaining 2 no. protective bollards at either end of benches on east side and 2 on the west side, adjacent to clock). Remove 7 no bike racks from southern ‘triangle’ area Remove and relocate 2 no. litter bins. Remove tree grilles and tree-guards from all 3 trees. Take up the two triangular sections of blue brick and lay sections of sample paving as shown. Samples to include Purbeck Cap, Purbeck Grub. Kellen Breccia Bianco and Kellen Lisco Giallo separated by bands of Kellen Lisco Nero Excavate section of Mt Ephraim Road loop road and replace with Kellen Breccia Giallo and Kellen Lavaro Geel.
An Illustration giving an indication of the effect of the de-cluttering is at Appendix B.
It should be noted that paving samples have been selected which reflect local distinctiveness, maintainability and lifetime considerations. For example Purbeck is the material used from 1793 on the Pantiles. The Kellen Giallo is intended to emulate the gravel, hoggin and buff road finishes used in the town. Similar products have been used elsewhere in recent shared space projects in the UK and Holland.
The proposals are also in line with the findings of the research carried out by the Environment, Housing and Health Overview and Select Committee where the themes of local distinctiveness, on-ongoing maintenance costs and clutter were identified
WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?
2. The report seeks approval of up to £40,000 of funding from the Environmental Enhancements budget to enable the initial scheme of work to be designed and carried out.
WHO HAVE WE CONSULTED AND HOW? (OR WHO WILL WE CONSULT FOLLOWING THE DECISION?)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.