To: Tunbridge Wells Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 19th October 2020
Subject: Highway Forward Works Programme – 2019/20 onwards
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2019/20.
Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2019/20 and 2020/21) and Year Three to Five (2021/22 to 2023/24) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2019/20, whilst for others it includes most of the works planned for the whole year.
This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D Casualty Reduction Measures Externally funded schemes Local Growth Fund
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Conclusion
1. This report is for Members’ information. Contact Officers:
The following contact officers can be contacted on 03000 418181
Richard Emmett Highway Manager West Kent Julian Cook Tunbridge Wells District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Emma Green Schemes Programme Manager Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer [name removed] Name Parish Extent of Works Current Status
A268 Rye Road Sandhurst Lomas Lane to Rosemullion Completed
A264 Mount Ephraim Tunbridge Wells Travel Lodge Hotel to Church Road Completed
Eridge Road Roundabout to A26 Eridge Road Tunbridge Wells Pedestrian Crossing (Summervale Completed Rd)
Junction with Hanover Rd to A26 St Completed A26 Grovesnor Road Tunbridge Wells Johns Rd
From the Roundabout Junction with A26 London Road Southborough Quarry Hill to just past the junction Completed with Bidborough Ridge
Between North Road and Little Mill Completed A262 High Street Goudhurst House
A228 Colts Hill Tunbridge Wells Maidstone Road to Alders Road Completed
A228 Badsell Road Completed Tunbridge Wells Junction with Maidstone Road Roundabout
Between Dorset Road and Boundary To be Forest Road Tunbridge Wells Road programmed early 2021
From the A228 to just north of the To be Tonbridge Road Pembury Hospital Turning programmed early 2021
From Mount Pleasant Road to To be Crescent Road Tunbridge Wells Calverley Road programmed early 2021 Surface Treatments – Contact Officer [name removed] Surfacing
Road Name Parish Extent of Works Current Status
A26 London Road to Mill Court Bidborough Ridge Bidborough Complete (Micro Surfacing)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Works ProgrammeReport | 508 KB | DownloadRead as text |
Follow Joint Transportation Board at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | Minutes of the meeting dated 20 April 2026RESOLVED : That the minutes of the Joint Transportation Board meeting dated 20 April 2026 be accepted as an accurate ... | Decided | Open |
| 13 Jul 2026 | Parking Consultation York Road and Dudley Road, Tunbridge WellsRESOLVED – That the Joint Transport Board notes the results of a public consultation proposing changes to waiting res... | Decided | Open |
| 13 Jul 2026 | Active Travel UpdateRESOLVED – The report was noted. | Noted | Open |
| 20 Apr 2026 | Minutes of the meeting dated 2 February 2026RESOLVED – That the minutes of the meeting dated 2 February 2026 be approved as a correct record. | Approved | Open |
| 20 Apr 2026 | Parish Highways Improvement Projects GrantsRESOLVED – The report was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.