Resolved
RESOLVED that the report be noted.
Audit and Governance Committee noted this item on Tuesday 30 June 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be noted.
1.1The purpose of this report is to report on the work of Internal Audit in the year ended 31st March 2009, and to advise the Committee of the Audit Manager’s opinion on the overall adequacy and effectiveness of the internal control environment.
1.2The Contact Officer for this report is Adrianna Partridge, Audit Manager for South Oxfordshire District Council and Vale of White Horse District Council, telephone (SODC) 01491 823544 and (VWHDC) 01235 547615.
2. Relationship with Corporate Plan
2.1This report supports the Council’s vision to build and safeguard a fair, open and compassionate community.
3.1Standard 10 of the CIPFA Code of Practice for Internal Audit in Local Government in the UK 2006 (CIPFA Code) states that the Head of Internal Audit (Audit Manager) must produce an annual report that:
• includes his or her opinion on the overall adequacy and effectiveness of the organisation’s control environment; • discloses any qualifications to that opinion, together with the reason(s) for the qualification; • presents a summary of the audit work from which the opinion is derived, including reliance placed on work by other assurance bodies; • draws attention to any issues the Head of Internal Audit judges particularly relevant to the preparation of the Statement of Internal Control (now Annual Governance Statement); • compares the work actually undertaken to the work that was planned and summarises the performance of the internal audit function against its performance measures and targets; and • comments on compliance with the CIPFA standards and communicates the result of the internal audit quality assurance programme.
3.2The control environment comprises the systems of governance, risk management and internal control. The key elements of the control environment include:
• establishing and monitoring the achievement of the organisation’s objectives; • ensuring compliance with established policies, procedures, laws and regulations; • ensuring risk management is embedded in the activity of the organisation, that leadership is given to the risk management process, and staff are trained or equipped to manage risk in a way appropriate to their authority and duties; • ensuring the economical, effective and efficient use of resources, and for securing continuous improvement in the way in which its functions are exercised, having regard to a combination of economy, efficiency and effectiveness; • the financial management of the organisation and the reporting of financial management; and • the performance management of the organisation and the reporting of performance management.
4. Overall Opinion
4.1The Audit Manager is satisfied that sufficient internal audit work has been undertaken to allow a reasonable conclusion to be drawn as to the adequacy and effectiveness of Vale of White Horse District Council’s risk management, control and governance processes. The Audit Manager’s opinion is based on the risk- based audits carried out during the year and other unplanned work on control systems. No reliance has been placed on the work of other assurance bodies.
4.2It is the Audit Manager’s unqualified opinion that satisfactory assurance can be placed on the Council’s risk management, control and governance processes. There is basically a sound system of internal control but there are some weaknesses which may put some system objectives at risk.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Annual Report 2008/09Report | 135 KB | DownloadRead as text |
Follow Audit and Governance Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2015 | Actions arisingRESOLVED : to retain the following items on the actions arising list: · To call the Building Control manager to a fut... | Decided | Open |
| 19 Mar 2015 | Internal audit management report quarter four 2014/15RESOLVED : to note the internal audit management report for the fourth quarter 2014/15. | Noted | Open |
| 19 Mar 2015 | Internal audit plan 2015/16RESOLVED : to approve the internal audit plan 2015/16. | Approved | Open |
| 22 Jan 2015 | Minutesto defer the approval of the minutes of the meeting held on 24 September 2014 as a correct record and to agree that t... | Deferred | Open |
| 22 Jan 2015 | Actions arisingto retain the amended procedure for monitoring systemic control weaknesses on the actions arising list for one more m... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.