Resolved
RESOLVED that the report be noted.
Audit and Governance Committee noted this item on Tuesday 30 June 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be noted.
1.1The purpose of this report is:
• to report on management issues
• to summarise the progress of internal audit against the 2009/2010 audit plan up to the 17 June 2009.
• to summarise the priorities and planned audit work for quarter 2 2009/2010.
1.2The Contact Officer for this report is Adrianna Partridge, Audit Manager for South Oxfordshire District Council and Vale of White Horse District Council, telephone (SODC) 01491 823544 and (VWHDC) 01235 547615.
2. Relationship with Corporate Plan
2.1This report supports the Council’s vision to build and safeguard a fair, open and compassionate community. 3. Background
3.1The CIPFA Code of Practice for Internal Audit in Local Government in the UK 2006 states that the Head of Internal Audit should prepare a risk-based audit plan, which should outline the assignments to be carried out and the broad resources required to deliver the plan.
3.2The CIPFA Code also states that the Audit Committee should approve the annual Internal Audit Plan and monitor progress against the plan. This Committee approved the annual Internal Audit Plan on the 25 March 2009.
4. Management Issues
4.1There are no management issues to report at this time, the team is at full complement and progressing well with planned audit and consultancy work.
5. Progress against the 2009/2010 Audit Plan
5.1Progress against the approved audit plan has been calculated for the quarter up to the 17 June 2009 and year to date and is summarised in Appendix 2 attached.
5.2Performance figures are as follows:
Target YTD Q1 Q2 Q3 Q4 09/10 09/10 09/10 09/10 Chargeable 71% 66% 66% - - - Non- 9.5% 11% 11% - - - Chargeable Lost 19.5% 23% 23% - - -
5.3The performance figures for Q1 take into account annual leave taken in May to clear carry-forward leave. The Audit Manager has no concerns with the team’s performance.
5.4As at the 17 June 2009, the status of audit work is as follows:
Planned Strategic, operational and financial assurance work known and approved by the Audit and Governance Committee. In progress
commence Complete Planned
Draft
To
PLANNED 38 0 (0%) 2 (5%) 8 (21%) 28 (74%) Joint 25 0 0 4 21 SODC 7 0 1 2 4 VWHDC 6 0 1 2 3 Adhoc Unplanned project work based on agreed terms of reference with the Audit Manager (i.e. implementation of new systems) and responsive work issued and agreed by the S151 Officer, Members or Senior Management Team (i.e. investigations).
In progress
commence Complete Planned
Draft
To ADHOC 3 1 1 1 0 Joint 0 0 0 0 0 SODC 1 1 0 0 0 VWHDC 2 0 1 1 0
Follow Up Work undertaken to ensure that agreed recommendations have been implemented.
In progress
commence Complete Planned
Draft
To FOLLOW - UP 21 3 0 1 17 SODC 11 3 0 0 8 VWHDC 10 0 0 1 9
6. Priorities for 2009/2010 Quarter 2 (July 2009 – September 2009)
6.1The priority for quarter 2 is: • Complete outstanding follow-up reviews. • Commence drafting the anti-fraud and corruption policy and response plan and money laundering policy.
6.2Planned audit work which is currently ongoing and has been scheduled for quarter 2 is as follows:
Joint Audits SODC Audits VWHDC Audits Bank Rec. Process Design Cornerstone – Couture Lone Working & Officer Brown Bins Cornerstone – Security Council Tax Membership Creditor Payments OWP Facilities Management VFM from CCTV FFTF Implementation Review Contract Housing and Council Tax Benefits Partnership Perf. Monitoring Pro-Active Anti-Fraud Review Records Management Rent Accounting S106 Commuted Sums Verification of BVPI VFM in Procurement
6.3Follow-up work which is scheduled for quarter 2 is as follows:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Management Report: 1st Quarter 2009/10Report | 94 KB | DownloadRead as text |
Follow Audit and Governance Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2015 | Actions arisingRESOLVED : to retain the following items on the actions arising list: · To call the Building Control manager to a fut... | Decided | Open |
| 19 Mar 2015 | Internal audit management report quarter four 2014/15RESOLVED : to note the internal audit management report for the fourth quarter 2014/15. | Noted | Open |
| 19 Mar 2015 | Internal audit plan 2015/16RESOLVED : to approve the internal audit plan 2015/16. | Approved | Open |
| 22 Jan 2015 | Minutesto defer the approval of the minutes of the meeting held on 24 September 2014 as a correct record and to agree that t... | Deferred | Open |
| 22 Jan 2015 | Actions arisingto retain the amended procedure for monitoring systemic control weaknesses on the actions arising list for one more m... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.