Internal audit management report first quarter 2010/11

Noted Finance 1 paper

Audit and Governance Committee noted this item on Wednesday 30 June 2010. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED (a) To note the report; and (b) To invite the Constitution Advisory Group to debate how far Vale councillors can discuss matters relating to South Oxfordshire District Council , when comparing performance to the Vale.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Audit and Governance Committee

Audit and Governance Committee report

30 June 2010 Report of: Head of Finance Report no. 16/10 Author: William Jacobs Telephone: 01235 540455 Wards Affected All Telephone: 01491 823326 E-mail: [email protected] Executive member responsible: Councillor Jerry Patterson Telephone: 01235 850275 E-mail: [email protected] To: Audit and Governance Committee DATE: 30 June 2010

Internal audit management report quarter one 201 2010/2011 0/2011 Recommendation

That members note the content of the report

Purpose of Report 1 The purpose of this report is:

• to report on management issues within internal audit.

• to summarise the progress of internal audit against the 2010/2011 audit plan up to the 11 June 2010.

• to summarise the priorities and planned audit work for quarter two 2010/2011.

2. The contact officer for this report is William Jacobs, head of finance for South Oxfordshire District Council and Vale of White Horse District Council, telephone (SODC) 01491 823326 and (VWHDC) 01235 540455. Strategic Objectives 3. To assist the Council to manage its business effectively by providing an assurance framework to monitor the overall adequacy and effectiveness of the internal control environment.

Background 4. The CIPFA Code of Practice for Internal Audit in Local Government in the UK 2006 states that the head of internal audit should prepare a risk-based audit plan, which should outline the assignments to be carried out and the broad resources required to deliver the plan.

5. The CIPFA Code also states that the audit committee should approve the annual internal audit plan and monitor progress against the plan. This Committee approved the annual internal audit plan on the 17 March 2010.

Management Issues 6. Marcia Slater continues to act in a temporary supervisory capacity during the internal audit manager’s maternity leave and meets with William Jacobs, head of finance on a regular basis to discuss operational issues and he is aware of the staff resource matters as reported below which have impacted on the commencement of the 2010/2011 internal audit plan.

Progress against the 2010/2011 Audit Plan 7. During this period, Piers Nunn (auditor) left the employment of the Council. Marcia Slater has organised the recruitment process and taken responsibility for picking up the outstanding audit work from Piers Nunn, which has resulted in her doing less audit work.

8. The recruitment process has been successful and it is hoped a new auditor will start in July pending the successful completion of the recruitment checklist.

9. Progress against the approved audit plan has been calculated for the quarter up to 11 June 2010 and year to date and is summarised in Appendix 1 attached.

10. Performance figures are as follows:

Target YTD Q1 Q2 Q3 Q4 10/11 10/11 10/11 10/11 Chargeable 61.5% 56.4% 56.4% - - - (identifiable client and/or specific IA deliverable)

Non-Chargeable 8.5% 3.2% 3.2% - - - (corporate, not IA deliverable)

Lost 30% 40.4% 40.4% - - - (i.e. leave, study, sickness) 11. Due to the management issues identified above, performance has been affected. However, the team continue to diligently work to the planned audit programme and it is the head of finance’s opinion that most of the variance against target will be attributable to resource and management pressures.

12. As at 11 June 2010, the status of audit work against the 2010/2011 audit plan is as follows:

Planned

Strategic, operational and financial assurance work known and approved by the Audit and Governance Committee.

In progress

commence 2010/2011 Complete Planned

Draft

To PLANNED 57 0 1 3 53 Joint 46 0 0 1 45 SODC 6 0 1 1 4 VWHDC 5 0 0 1 4

Adhoc

Unplanned project work based on agreed terms of reference with the audit manager (i.e. implementation of new systems) and responsive work issued and agreed by the S151 Officer, members or senior management team (i.e. investigations). In progress

commence Requested

Complete

2010/2011 Draft

To

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal audit management report first quarter 2010/11Report 53 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 18 attended
SB
Steve BishopOfficer, present
TC
Councillor Terry CoxCommittee Member, apologies
AC
Councillor Andrew CrawfordCommittee Member, present
SC
Steve CullifordOfficer, present
RF
Councillor Richard FarrellVice-Chair, present
DH
Councillor Dudley HoddinottChair, present
WJ
William JacobsOfficer, present
DK
Darren KeenGuest, present
SL
Steve LawrenceOfficer, present
BM
Councillor Bill MelottiCommittee Member, apologies
JM
Councillor Janet MorganCommittee Member, present
MM
Councillor Michael MurrayCommittee Member, present

All 18 on the meeting page

On this subject at Vale of White Horse

Search all
  1. Internal audit management report first quarter 2010/11This decision
  2. Internal audit management report quarter four 2014/15Noted
  3. Internal audit plan 2015/16Approved
  4. Internal audit management report quarter three 2014/2015Noted
  5. Internal Audit activity report - second quarter 2014/15Noted
  6. Internal Audit management report - second quarter 2014/15Noted

More from Vale of White Horse Audit and Governance Committee

All decisions
MeetingDecisionOutcome
19 Mar 2015 Actions arisingRESOLVED : to retain the following items on the actions arising list: · To call the Building Control manager to a fut... Decided Open
19 Mar 2015 Internal audit management report quarter four 2014/15RESOLVED : to note the internal audit management report for the fourth quarter 2014/15. Noted Open
19 Mar 2015 Internal audit plan 2015/16RESOLVED : to approve the internal audit plan 2015/16. Approved Open
22 Jan 2015 Minutesto defer the approval of the minutes of the meeting held on 24 September 2014 as a correct record and to agree that t... Deferred Open
22 Jan 2015 Actions arisingto retain the amended procedure for monitoring systemic control weaknesses on the actions arising list for one more m... Decided Open