RESOLVED (by six votes to nil) (a) To note the progress made in developing and improving the council’s business continuity arrangements to meet the needs of shared working with South Oxfordshire District Council and the associated revised management structure; and (b) To introduce an annual reporting frequency for business continuity and risk management matters.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Report of Head of HR, IT & Customer Services Report no. 13/10 Author: Penny O’Callaghan / Geoff Bushell Tel: 01491 823030 E-mail: penny.o’[email protected] Executive Member responsible: Jerry Patterson Tel: 01865 730588 E-mail: [email protected] To: Audit & Governance Committee Date: 30 June 2010
Business continuity update Recommendations That the Audit and Governance committee:
a) notes the progress made in developing and improving business continuity arrangements to meet the needs of shared working between South and Vale and the associated revised management structure. b) considers and approves the revised reporting frequency of business continuity and risk management updates.
Purpose of Report 1. The purpose of this report is to provide committee with an update on our business continuity arrangements.
Relationship with corporate plan 2. Having effective business continuity arrangements in place will help the councils in meeting their shared strategic objective of ‘managing our business effectively’.
Background 3. In compliance with the Civil Contingencies Act 2004 and accompanying regulations, we are required to ‘assess the risk of an emergency occurring and to maintain plans for the purpose of ensuring that if an emergency occurs, the councils are able to perform their functions’. In other words, we need to ensure that we would be able to continue to deliver our services to residents in the event of a disruption. 4. Following management team’s decision to rationalise South and Vale’s approach to business continuity, we produced a joint business continuity strategy and presented it to this committee. Executive approved it on 5 February 2010. The reporting timetable brought to this committee in September 2009 requires us to provide update reports on our business continuity arrangements every six months.
Progress to date 5. Following the fourth tier management restructure, it was evident that the existing business continuity plans needed a complete update. To address this, we conducted a council wide business impact assessment (BIA). The purpose of this assessment was to differentiate between critical (urgent) and non-critical (non-urgent) organisation functions/activities, given that the council will never have sufficient resources to restore everything immediately, or it would be too costly to maintain such back-up services.
6. We involved service managers and heads of service in the BIA to ensure we had a council wide view of all our functions. Through a series of workshops we identified the critical activities of each service, the recovery resources required (people, workspaces, IT systems and equipment) and we also gathered additional data to inform each of the plans such as names of the members of the business recovery team. We also prioritised each function by assessing how quickly we would need to restore it in the event of a disruption. This assessment took into account the needs of the public and the timescale on which the service is normally delivered. For example, the assessment concluded that the council’s benefits service needed to be restored within 2 days, whereas the determination of planning applications should be recovered within 5 days, given that this is a small proportion of the normal eight week period and would not cause immediate hardship to residents.
7. Since completing the BIA we have made significant progress and have:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit and Governance Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.