RESOLVED : To (a) note the council’s existing business continuity arrangements and the additional work undertaken since the last update; (b) ask the officers to report back on the timescale for testing the business continuity arrangements; and (c) ask the officers to confirm that business continuity arrangements are in place for the council’s largest and most important contracts and that the officers are satisfied with the arrangements.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Report of Head of HR, IT & Customer Services Report no. 64/11 Author: Penny O’Callaghan Tel: 01491 823030 E-mail: penny.o’[email protected] Cabinet Member responsible: Yvonne Constance Tel: 01235 751475 E-mail: [email protected] To: AUDIT & GOVERNANCE COMMITTEE DATE: 18 January 2012
Business continuity and risk management update Recommendation
We invite Audit and Governance Committee to note our existing arrangements and the additional work we have undertaken since our last update reports.
Purpose of Report 1. The purpose of this report is to provide committee with an update on our business continuity and risk management arrangements.
Relationship with corporate plan 2. Having effective business continuity arrangements in place will help the councils in meeting their shared strategic objective of ‘managing our business effectively’. Our risk management arrangements underpin all strategic objectives.
Background 3. The joint Business Continuity Strategy and the joint Risk Management Strategy require us to present regular reports to this committee on how we are managing our risks and to provide an update on our business continuity arrangements. Both strategies accompany this report.
4. On 30 June 2010, committee approved our recommendation to revise the reporting frequency of business continuity and risk management updates from quarterly to annually. Business continuity 5. In compliance with the Civil Contingencies Act 2004 and accompanying regulations, we are required to ‘assess the risk of an emergency occurring and to maintain plans for the purpose of ensuring that if an emergency occurs, the councils are able to perform their functions’. In other words, we need to ensure that we would be able to continue to deliver our services to residents in the event of a disruption.
6. Last year, following the fourth tier management restructure, we conducted a council wide business impact assessment (BIA). The purpose of this assessment was to differentiate between critical (urgent) and non-critical (non-urgent) organisational functions/activities, given that the council will never have sufficient resources to restore everything immediately, or it would be too costly to maintain such back-up services.
7. We involved service managers and heads of service in the BIA to ensure we had a council wide view of all our functions. Through a series of workshops we identified the critical activities of each service, the recovery resources required (people, workspaces, IT systems and equipment) and we also gathered additional data to inform each of the plans such as names of the members of the business recovery team. We also prioritised each function by assessing how quickly we would need to restore it in the event of a disruption. This assessment took into account the needs of the public and the timescale on which the service is normally delivered. For example, the assessment concluded that the council’s benefits service needed to be restored within 2 days, whereas the determination of planning applications should be recovered within 5 days, given that this is a small proportion of the normal eight week period and would not cause immediate hardship to residents.
8. We transferred the results of the BIA into each service’s business continuity plan so in the event of a disruption all staff are aware of their responsibilities and what action they need to take.
9. Each plan is owned by the Head of Service and each has a separate plan administrator. The plan administrator co-ordinates the quarterly review of their plan and makes amendments where necessary.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit and Governance Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.