RESOLVED : to (a) note the existing business continuity and risk management arrangements and the additional work undertaken since the last update in January 2012; and (b) ensure that business continuity and risk management arrangements are in place for all of the council’s major contracts when they are re-let or extended.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Report of Head of HR, IT & Customer Services Author: Penny O’Callaghan Tel: 01491 823030 E-mail: penny.o’[email protected] Cabinet Member responsible: Yvonne Constance Tel: 01235 751475 E-mail: [email protected] To: Audit and Governance Committee DATE: 20 March 2013
Business continuity and risk management update Recommendations We invite Audit and Governance Committee to note our existing arrangements and the additional work we have undertaken since our last annual update report.
Purpose of report 1. The purpose of this report is to provide committee with an update on our business continuity and risk management arrangements.
Relationship with corporate plan 2. Having effective business continuity arrangements in place will help the council in meeting its strategic objective of ‘effective management of resources’.
Background 3. The joint Business Continuity Strategy and the joint Risk Management Strategy require us to present regular reports to this committee on how we are managing our risks and to provide an update on our business continuity arrangements. We presented our last annual update to committee on 18 January 2012 with two separate business continuity reports being presented on 21 March 2012 and 26 September 2012.
Business continuity 4. In compliance with the Civil Contingencies Act 2004 and accompanying regulations, we are required to ‘assess the risk of an emergency occurring and to maintain plans for the purpose of ensuring that if an emergency occurs, the councils are able to perform their functions’. In other words, we need to ensure that we would be able to continue to deliver our services to residents in the event of a disruption.
5. We have a procedure in place which ensures that all business continuity plans are reviewed every quarter and amended where necessary. Officers also update the plans on an ad-hoc basis to ensure leavers are removed and new starters are added.
6. The plans are stored on the general drive as well as remotely in case access to the council network is restricted or unavailable during a disruption.
7. Since our last update, the Emergency Planning Unit (Oxfordshire County Council) conducted a business continuity and emergency planning simulated exercise, named Exercise Ping Pong. We reported the findings of the exercise to committee on 26 September along with confirmation that we had implemented all the recommendations made by the Emergency Planning Unit. We also provided details on the additional work we were undertaking to enhance our existing arrangements.
8. We had implemented all the recommendations made by the Emergency Planning Unit. One area we had identified as needing further work was the production of a testing and rehearsal schedule to include training of key officers. The schedule is attached as an annex for your information.
9. The joint Business Continuity Strategy is currently being reviewed and updated. We will present this at the next committee meeting.
Risk management 10. The council still has seven operational risk registers and seven risk champions, one for each service. We continue to review and update the registers every quarter in accordance with the Risk Management Strategy. We consider the risk registers to be confidential documents and therefore have not attached them to this report.
11. The strategic management board has recently reviewed the strategic risk register to ensure it is up to date, the risks remain relevant and also if any further action is required. We will review it again in April 2013 and update if necessary. There are currently four strategic risks recorded: • partnerships • joint working arrangements • housing provision • recession
12. The joint Risk Management Strategy is currently being reviewed and updated. We will present this to committee for approval at the next committee meeting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit and Governance Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.