RESOLVED : to update the committee’s work programme to include the external auditor’s progress report in June and the informal question and answer session for members on the draft statement of accounts.
Audit and Governance Committee decided this item on Wednesday 20 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : to update the committee’s work programme to include the external auditor’s progress report in June and the informal question and answer session for members on the draft statement of accounts.
Audit and Governance work programme containing Audit and Governance Committee work to be undertaken 1 March 2013 - 31 December 2013
The audit and governance work programme belongs to the council’s Audit and Governance Committee and sets out a schedule of work for the period shown above. It is a rolling plan, subject to change at each Audit and Governance Committee meeting; however, the council may allocate additional work.
You can make representations on any issue below. Please contact the officer shown below by 10am on the day the committee is due to meet.
Item title Meeting date Lead officer Why is it here? Scope Notes Business continuity Audit and Geoff Bushell The committee is To receive an update and risk management Governance Tel. (01235) charged with the on the council's update Committee 20 547689 Email: responsibility with business continuity Mar 2013 geoff.bushell@so monitoring the council's and risk management uthandvale.gov.u business continuity and arrangements. k risk management arrangements. External audit plan Audit and Steve Bishop, The council's external To consider the 2012/13 Governance Strategic Director auditor produces a plan external auditor's Committee 20 and Section 151 of the 2012/13 financial report. Mar 2013 Officer Tel. statements to be (01235) 540332 audited. Email: steve.bishop@so uthandvale.gov.u k
Page 1 of 4 Item title Meeting date Lead officer Why is it here? Scope Notes
Internal audit plan Audit and Adrianna Each year the To review the 2012/13 2013/14 Governance Partridge Tel. committee reviews the internal audit plan and Committee 20 (01491) 823544 planned audits due to approve a plan for Mar 2013 Email: be carried out by the 2013/14. adrianna.partridg council's internal audit e@southandvale. team and sets a plan for gov.uk the forthcoming year. Internal audit activity Audit and Adrianna The council audits its To review the report Governance Partridge Tel. services through the outcomes from the Committee 24 (01491) 823544 internal audit service. internal audits and Jun 2013 Email: recommend any adrianna.partridg further actions or e@southandvale. improvements. gov.uk Internal audit Audit and Adrianna The committee monitors To monitor the management report Governance Partridge Tel. the effectiveness of the management of Committee 24 (01491) 823544 internal audit each internal audit. Jun 2013 Email: quarter. adrianna.partridg e@southandvale. gov.uk Internal audit annual Audit and Adrianna Each year the council's To review internal report 2012/13 Governance Partridge Tel. internal audit team audit activity during Committee 24 (01491) 823544 produces an annual 2012/13. Jun 2013 Email: report to review adrianna.partridg activities over the e@southandvale. previous year. gov.uk
VWHDC Audit and Governance Work Programme 1 March 2013- 31 December 2013 2 Item title Meeting date Lead officer Why is it here? Scope Notes
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit and governance work programmeReport | 46 KB | DownloadRead as text |
Follow Audit and Governance Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2015 | Actions arisingRESOLVED : to retain the following items on the actions arising list: · To call the Building Control manager to a fut... | Decided | Open |
| 19 Mar 2015 | Internal audit management report quarter four 2014/15RESOLVED : to note the internal audit management report for the fourth quarter 2014/15. | Noted | Open |
| 19 Mar 2015 | Internal audit plan 2015/16RESOLVED : to approve the internal audit plan 2015/16. | Approved | Open |
| 22 Jan 2015 | Minutesto defer the approval of the minutes of the meeting held on 24 September 2014 as a correct record and to agree that t... | Deferred | Open |
| 22 Jan 2015 | Actions arisingto retain the amended procedure for monitoring systemic control weaknesses on the actions arising list for one more m... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.