Internal audit management report - fourth quarter 2013/14

Noted Finance 5 papers

Audit and Governance Committee noted this item on Wednesday 20 March 2013. Below is the council's own wording, with the papers it was decided on.

Item61

Resolved

RESOLVED : to note the report.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Audit and Governance Committee

Audit and Governance Committee Report

20 March 2013 Report of: Audit Manager Author: Adrianna Partridge Wards Affected Telephone: 01235 547615 All Telephone: 01491 823544 E-mail: [email protected] Cabinet member responsible: Councillor Matthew Barber Telephone: [phone removed] E-mail: [email protected] To: Audit and Governance Committee DATE: 20 March 2013

Internal audit management report quarter four 201 2012/2013 /2013 Recommendation

That members note the content of the report

Purpose of report 1. The purpose of this report is:

• to report on management issues within internal audit;

• to summarise the progress against the 2012/2013 audit plan up to 7 March 2013; and

• to summarise the priorities for quarter one 2013/2014.

2. The contact officer for this report is Adrianna Partridge, Audit Manager for South Oxfordshire District Council and Vale of White Horse District Council, telephone (SODC) 01491 823544 and (VWHDC) 01235 547615. Strategic objectives 3. Managing our business effectively.

Background 4. The CIPFA Code of Practice for Internal Audit in Local Government in the UK 2006 states that the head of internal audit should prepare a risk-based audit plan, which should outline the assignments to be carried out and the broad resources required to deliver the plan.

5. The CIPFA Code also states that the audit committee should approve the annual internal audit plan and monitor progress against the plan. This Committee approved the annual internal audit plan on 21 March 2012.

Management issues 6. The audit manager is currently considering options for providing adequate cover during her period of maternity leave. She will be discussing these with the head of finance and the s151 officer, with a view to the agreed arrangements being in place from July 2013.

Progress against the 2012/2013 audit plan 7. Progress against the approved audit plan has been calculated for the quarter and year to date and is summarised in appendix 1 attached.

8. Performance figures are as follows:

Target YTD Q1 Q2 Q3 Q4 12/13 12/13 12/13 12/13 Chargeable 70% 70% 71.5% 71% 68.5% 68.5% (identifiable client and/or specific IA deliverable) Non-Chargeable 8% 5.5% 5% 4.5% 4.5% 7.5% (corporate, not IA deliverable) Lost 22% 24.5% 23.5 24.5% 27% 24% (i.e. leave, study, sickness)

9. As at 7 March 2013 the status of audit work against the 2012/2013 audit plan is as follows:

Planned

Strategic, operational and financial assurance work known and approved by the Audit and Governance Committee. In progress

commence 2012/2013

Complete Planned

Draft

To PLANNED 28 21 0 5 2 Joint 25 18 0 5 2 SODC 2 2 0 0 0 VWHDC 1 1 0 0 0

Adhoc

Unplanned project work based on agreed terms of reference with the audit manager (i.e. implementation of new systems) and responsive work issued and agreed by the section 151 officer, members or senior management team (i.e. investigations).

In progress

commence Requested

2012/2013 Complete

Draft

To ADHOC 4 3 0 0 1 Joint 1 1 0 0 0 SODC 1 1 0 0 0 VWHDC 2 1 0 0 1

Follow up

Work undertaken to ensure that agreed recommendations have been implemented. The number of follow-up audits is a rolling number, all internal audit reports are followed up after six months. In progress

commence Requested

Complete

2012/2013 Draft

To

FOLLOW-UP 36 34 0 0 2 SODC 16 15 0 0 1 VWHDC 20 19 0 0 1

Priorities for 2013/2014 quarter one (April 2013 – June 2013)

10. The priority for quarter one is to: • complete 2012/2013 planned audit work and commence 2013/2014 planned audit work.

• ensure all internal audit procedures and monitoring templates are up to date; and

• complete effective handover to interim management cover.

11. Remaining 2012/2013 planned audit work can be reviewed in appendix 2.

Financial implications 12. There are no financial implications attached to this report.

Legal implications 13. None.

Risk implications 14. Identification of risk is an integral part of all audits.

ADRIANNA PARTRIDGE AUDIT MANAGER

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Follow up auditsAppendix 1 13 KB Download
PDF
Planned auditsAppendix 1 19 KB Download
PDF
Unplanned auditsAppendix 1 11 KB Download
PDF
Audit Plan Schedule 2012-13Appendix 2 24 KB Download
PDF
Internal audit management report: fourth quarter 2013/14Report 57 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 17 attended
KA
Kate ArnoldOfficer, present
MB
Councillor Mike BadcockCommittee Member, absent
SB
Sandy BayleyOfficer, present
SB
Steve BishopOfficer, present
JB
Councillor Julia BricknellCommittee Member, apologies
AC
Councillor Andrew CrawfordCommittee Member, apologies
SC
Steve CullifordOfficer, present
DH
Councillor Dudley HoddinottCommittee Member, present
SH
Councillor Simon HowellChair, present
WJ
William JacobsOfficer, present
BJ
Councillor Bob JohnstonSubstitute, present as substitute
MK
Councillor Mohinder KainthVice-Chair, present

All 17 on the meeting page

On this subject at Vale of White Horse

Search all
  1. Internal audit management report - fourth quarter 2013/14This decision
  2. Internal audit management report quarter four 2014/15Noted
  3. Internal audit plan 2015/16Approved
  4. Internal audit management report quarter three 2014/2015Noted
  5. Internal Audit activity report - second quarter 2014/15Noted
  6. Internal Audit management report - second quarter 2014/15Noted

More from Vale of White Horse Audit and Governance Committee

All decisions
MeetingDecisionOutcome
19 Mar 2015 Actions arisingRESOLVED : to retain the following items on the actions arising list: · To call the Building Control manager to a fut... Decided Open
19 Mar 2015 Internal audit management report quarter four 2014/15RESOLVED : to note the internal audit management report for the fourth quarter 2014/15. Noted Open
19 Mar 2015 Internal audit plan 2015/16RESOLVED : to approve the internal audit plan 2015/16. Approved Open
22 Jan 2015 Minutesto defer the approval of the minutes of the meeting held on 24 September 2014 as a correct record and to agree that t... Deferred Open
22 Jan 2015 Actions arisingto retain the amended procedure for monitoring systemic control weaknesses on the actions arising list for one more m... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies