Responsive Repairs Joint Action Plan - Quarter 3 update

Noted Scrutiny 1 paper

Corporate Overview and Scrutiny Housing Improvement Sub-Committee noted this item on Monday 7 March 2016. Below is the council's own wording, with the papers it was decided on.

Item123

Resolved

RESOLVED to note the progress made against the action plan, but were very disappointed and concerned that this had not resulted in anticipated outcomes. The Sub-Committee endorsed a very firm approach being taken with Mears to continue to drive improvements in outcomes for Waverley and tenants.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Corporate Overview and Scrutiny Housing Improvement Sub-Committee

Financial implications

Waverley’s Responsive Repairs budget for Housing in 2015/16 is £1.79m. This represents a significant proportion of the Council’s spend on Housing and it is a high tenant priority. The Joint Action Plan is designed to continually improve both the standard and efficiency of responsive repairs work.

There are no legal implications arising directly from this report. However, the implementation of the Action Plan will impact on how the Council discharges its legal obligations to Council Housing Tenants for completing repairs as set out in the Tenancy Agreements.

Background

1. The responsive repairs service forms a vital part of Waverley’s Housing Service to its social housing tenants. It is a service that tenants rely on and it generates a high volume of transactions each year. As a result, this service plays a major part in tenants’ perceptions of Waverley’s Housing Service and overall levels of customer satisfaction.

2. To support the improvement programme, Corporate Overview & Scrutiny Committee agreed to undertake an in-depth review into the Responsive Repairs service, which was carried out by the Housing Improvement Sub-Committee between November 2014 and March 2015. To address the improvements identified as being needed, an action plan was prepared jointly by Waverley’s Property Services Team and Mears and agreed by Housing Improvement Sub-Committee in March 2015.

3. The Joint Action Plan was further reviewed by Property Services in response to the results of the Survey of Tenants and Residents (STAR) reported in May 2015. This suggested a need for improvement in six areas, and a number of new actions were added to the Joint Action Plan.

Actions Progress

4. This report provides an update on the endorsed Joint Action Plan which is annexed to this report. Progress since the last report is as follows:

Completed

Action 9: Mears can now access Waverley’s Keystone asset database for property details, enabling better sharing of information.

Action 40: Mears general manager has completed management training and other senior staff working on Waverley’s contract have been put forward for future management training.

Progressed

Action 3: Increase in the number of texts sent to tenants as appointment reminders in an effort to reduce the number of failed appointments due to no access.

Action 5a: New process for authorising variations to repair jobs agreed; supporting IT processes being developed.

Action 14: Agreement reached on moving from a 2-hour time slot to am/pm appointments. The process and supporting IT is being developed.

Action 20: Scoping workshop held on 16 February on developing the interface between Agresso (the Council’s financial system) and Orchard (the Council’s Housing system); this work will now form part of the Council’s Agresso Upgrade project.

Action 30a: Mears are continuing to report on appointments met, missed or re- scheduled.

Officers are continuing to work with Mears to improve the customer experience (5b) of the responsive repairs service, including reviewing processes to reduce the length of time to complete jobs (28) as part of our Value For Money Workshops.

Conclusion

5. Overall progress has been good with 42 of the 50 Actions (84%) implemented to date. The anticipated outcomes however have not been realised in all areas and in particular with regards to customer satisfaction with Mears. Recommendation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Responsive Repairs Joint Action Plan: Quarter 3 updateReport 107 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
PF
Councillor Pat FrostCommittee Member, present
MG
Councillor Michael Goodridge MBECommittee Member, present
AJ
Councillor Anna JamesCommittee Member, present
RS
Councillor Richard SeaborneCommittee Member, present
CS
Councillor Christopher StoreyCommittee Member, present
AW
Mr Adrian WallerCommittee Member, present
AB
Mr Alan BinfieldCommittee Member, present
TD
Terry DaubneyCommittee Member, present

On this subject at Waverley

Search all
  1. Responsive Repairs Joint Action Plan - Quarter 3 updateThis decision
  2. Housing Responsive Repairs, Voids and Aids & Adaptations Contract VariationDecided
  3. Responsive Repairs Action PlanNoted
  4. Commencement of the Responsive Repairs options AppraisalNoted
  5. Commencement of the Responsive Repairs Options AppraisalNoted
  6. Responsive repairs contract client action plan reportAgreed

More from Waverley Corporate Overview and Scrutiny Housing Improvement Sub-Committee

All decisions
MeetingDecisionOutcome
9 Jan 2017 Committee Work ProgrammeIt was agreed to move this report to later in the year, when it would be considered by the new Housing OS Committee. ... Agreed Open
7 Nov 2016 Tenant Involvement - Mid-year progress reportRESOLVED to note the good progress being made on tenant involvement, and were pleased with the energy and innovation ... Noted Open
7 Nov 2016 New Anti-Social Behaviour Powers for Housing Operations - consultation responses and updated PolicyRESOLVED to endorse the Policy subject to the incorporation of amendments to reflect the suggestions about presentati... Decided Open
7 Nov 2016 Exclusion of press and publicRESOLVED that pursuant to Procedure Rule 20, and in accordance with Section 100A (4) of the Local Government Act 1972... Decided Open
4 Jul 2016 Exclusion of press and publicRESOLVED that, pursuant to Procedure Rule 20, and in accordance with Section 100A(4) of the Local Government Act 1972... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies