Waverley Borough Council
Executive, Tuesday 2 June 2026 at 7.00pm

Housing Responsive Repairs, Voids and Aids & Adaptations Contract Variation

Decided Executive 1 paper

AI summaryWaverley Executive approved varying the housing repairs contract with Ian Williams Ltd: one year extension to 1 April 2028, retrospective rate rise from 1 April 2026, and total contract value rising to £40m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedExtension, rate uplift and value cap agreed
Money£40mNew anticipated total contract value, up from £31m
What happens nextFormal enactment from 1 April 2026Contract varied under seal by Housing, Procurement and Legal
Who it affectsCouncil housing tenants and contractorApproximately 1,100 repairs, voids and adaptations per month

What was decided

The Executive varied the contract with Ian William Limited to exercise the one year permitted extension, taking it to 1 April 2028. Report P10, P11

Rates for responsive repairs, voids and aids and adaptations were increased as a retrospective adjustment effective from 1 April 2026 for the remaining contract duration. Report P11

The overall anticipated contract value was raised to £40m, and the contractor will pay residents £25 for each missed appointment. Report P12, 6.30

Why

Ian Williams has told the council the contract has been loss making since April 2022 and threatened to serve 13 weeks notice to terminate if rates were not increased. Report 6.17, 6.18, P101

Officers concluded that ending or reprocuring the contract would risk statutory service delivery, regulatory non-compliance, and higher mobilisation costs in a volatile market. Report 1.3, 1.5, 10.1, 11.1, 11.2

An independent validation by Faithorn Farrell Timms found the proposed uplift brings rates in line with current market trends and remains below the market average. Report 6.30, 6.31, 6.32, P67

What happens next

Housing, Procurement and Legal services will formally enact the contract variation under seal effective from 1 April 2026. Report P20

The Landlord Services Advisory Board and the Overview and Scrutiny Committee will receive quarterly updates on actions and outcomes under the improvement plan. Report 1.6, 14.1

A joint project group with Guildford Borough Council will produce an options appraisal on a single joint responsive repairs contract to inform the new West Surrey Council after Local Government Reorganisation. Report 8.3, 8.4, 8.5

The money

  • £40m New overall anticipated total contract value after the variation Report P12
  • £412,800 Estimated annual revenue increase in 2026/27 from uplifting five tradelines from NHF7 to NHF8 Report 6.27
  • £3.2 million per annum Current contract value covering around 1,100 responsive repairs, voids and adaptations each month Report 6.5
  • £31,000,000 Original total contract value stated in the procurement notice Report P98
  • £1.5m Estimated underspend on capital external works in 2025/26 Report 6.21
  • £5.4k per annum Social value initiatives funded by the current contract with Ian Williams Ltd Report 12.6
  • £25 per missed appointment Compensation the contractor will pay residents Report 6.30
  • £72.66 New minimum order value, calculated as £70 plus 3.8% CPI Report 6.29

Options considered

  • Rejected: Do nothing. Would expose the council to failing its statutory duty to provide decent and safe housing Report 11.1
  • Rejected: Reprocure a short term contract. Not viable given current market conditions and mobilisation costs Report 11.2
  • Rejected: De-lot the contract by removing unviable work elements. Would break continuity of the responsive repairs service Report 11.3
  • Chosen: Approve the negotiated settlement with Ian Williams Ltd as independently validated. Sustains contract viability, ensures continuity, and mitigates operational, financial and customer risks Report 11.4

Implications

  • Financial: Revenue cost to the Housing Revenue Account rises by an estimated £412,800 in 2026/27, met from within existing HRA budget and 2026/27 budget planning, with no extra corporate funding needed subject to volumes.
  • Legal: Officers consider the variation permitted under regulation 72(1)(e) of the Public Contract Regulations 2015 as it is not a substantial modification; the increase takes the contract above the Key Decision threshold so Executive approval is required under Contract Procedure Rule 15.3. Report P103, P105, P106
  • Risk: Rejecting the variation risks early contract termination, service disruption, tenant safety impacts, and loss of progress on the Improvement Plan and the RSH Quality and Safety Consumer Standard. Report 10.1, 10.2
  • Equalities: The Public Sector Equality Duty was considered and no equality and diversity implications were identified arising directly from this report. Report 12.3, 12.4, P114
  • Climate: Climate change implications were assessed at the quality evaluation stage of the tender submissions to ensure maximum sustainability. Report 12.5
  • Other: The decision supports Local Government Reorganisation transition to West Surrey Council by maintaining service continuity ahead of Vesting Day on 1 April 2027 and opens scope for a joint WBC and Guildford BC responsive repairs contract. Report 8.1, 8.2, 8.3, P76

Who and where

  • Waverley Borough Council housing tenants receiving responsive repairs, voids and aids and adaptations services Report 1.2, 6.5
  • Ian Williams Limited, the contracted provider Report 6.1, 6.6
  • The Housing Revenue Account budget
  • Overview and Scrutiny Committee and the Landlord Services Advisory Board through ongoing oversight Report 1.6, 14.1

Timeline

  • April 2022: Contract awarded to Ian Williams Limited following a Public Contract Regulations 2015 procurement Report 6.1, 6.3
  • July 2024: Executive Working Group established to address contract underperformance, producing 24 improvement actions Report 6.9
  • August 2025: Ian Williams formally requested a rate uplift and warned of break clause activation Report 6.17
  • November 2025: Internal officer project working group formed covering housing operations, legal, finance and procurement
  • November 2025 to March 2026: Formal contract negotiations between the council and Ian Williams Report 6.26
  • November 2025 to January 2026: Independent tenant satisfaction survey conducted by TLF covering Ian Williams contract performance Report 6.14
  • March 2026: Faithorn Farrell Timms commissioned to provide independent third party validation of the proposed uplift Report 6.30, P65
  • 10 March 2026: Surrey (Structural Changes) Order 2026 came into effect Report 8.1
  • 1 April 2026: Retrospective rate uplift effective and formal contract variation enacted under seal Report P11, P20
  • 31 March 2027: End of the initial five year contract term Report 6.2
  • 1 April 2027: Vesting Day for transfer of functions to West Surrey Council under Local Government Reorganisation Report 8.1, 8.2
  • 1 April 2028: New end date of the contract following the one year extension Report P10

Plain English for the jargon

  • NHF Schedule of Rates: National Housing Federation standard, itemised pricing tool for building maintenance in the social housing sector, used as the basis for the contract
  • Responsive Repairs (RR): Day to day repair works carried out for tenants, as opposed to planned capital works
  • Voids: Empty council properties that need works to bring them back into a lettable condition
  • Aids and Adaptations (A&A): Alterations to tenants' homes to support independent living, for example for disabled residents
  • HRA (Housing Revenue Account): The ringfenced account that funds council housing services from tenant rents
  • LGR (Local Government Reorganisation): The restructuring of councils in Surrey, with Waverley's functions transferring to a new West Surrey Council
  • Break clause: A contractual right allowing either party to end the contract early on notice, here 13 weeks
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 11/25

Resolved

Resolved that the contract with Ian William Limited be varied to: exercise the permitted extension for one year to 1 April 2028 increase the rates for housing responsive repairs, voids and aids & adaptations services as outlined in this report as a retrospective adjustment effective from 1 April 2026 for the ... EXE 11/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1 Title of the report – Housing Responsive Repairs, Voids and Aids & Adaptations Contract Variation

1.1The Housing Service are requesting approval of a cost variation to the Responsive Repairs (RR), Voids and Aids and Adaption (A&A) contract with Ian Williams Ltd Limited to maintain and continue to improve service delivery effective from 1 April 2026 – 31 March 2027.

1.2The Council have both statutory and regulatory requirements to ensure tenants have access to a responsive repairs service that meets our responsibilities as a social housing landlord.

1.3The current contract cost model presents increasing challenges to the ongoing financial sustainability and operational viability of Ian Williams Ltd. Market pressures, rising input costs, and the constraints of existing rates place heightened risk on the contractor’s ability to continue delivering services to the required standard over the life of the contract. Recognising and proactively addressing these risks is essential to safeguard service continuity, protect value for money, and ensure that WBC can continue to meet its regulatory and service delivery obligations to residents. Timely consideration of these issues will support contract stability, mitigate the risk of service disruption, and reinforce a collaborative and sustainable partnership approach.

1.4The cost variation increases as recommended in this report is supported by an independent third-party validation that the contract will continue to provide value for money to the council.

1.5Failure to secure approval for the recommendation poses significant risk to the council and its ability to provide safe and compliant homes in accordance with external regulation and its corporate objectives.

1.6Assurance is provided that the Landlord Services Advisory Board and the Overview and Scrutiny (O&S) Committee will be kept fully informed on a quarterly basis by the Housing Service regarding the actions taken and outcomes achieved under the improvement plan. This reporting will enable effective oversight, demonstrate progress, and ensure the contract continues to deliver value for money and improved outcomes for tenants.

Recommendation

The Executive resolves to: 2.1 Vary the contract with Ian William Limited to:

2 Title of the report – Housing Responsive Repairs, Voids and Aids & Adaptations Contract Variation

2.1.1 exercise the permitted extension for one year to 1 April 2028

2.1.2 increase the rates for housing responsive repairs, voids and aids & adaptations services as outlined in this report as a retrospective adjustment effective from 1 April 2026 for the duration of the contract.

2.1.3 increase the overall anticipated contract value to £40m.

3 Reason(s) for recommendation:

3.1To ensure continuity of the Councils statutory duty to provide responsive repairs, voids and aids & adaptations services to its tenants.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Responsive Repairs, Voids and Aids & Adaptations Contract VariationReport 1.3 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, apologies
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, apologies
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. Housing Responsive Repairs, Voids and Aids & Adaptations Contract VariationThis decision
  2. Housing maintenance - responsive repairs and voids contractAgreed
  3. Housing Responsive Repairs and Voids ContractDecided

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies