Report to Corporate Overview and Scrutiny Housing Improvement Sub-Committee
Financial implications
There is a provision in the 2015-16 capital programme for decent homes and planned works. It is anticipated that all work will be completed within the existing budget.
Legal implications
The Decent Homes Standard was introduced by the Government in 2000 and set a ‘decency’ standard to which all social rented housing should be improved and, in some cases, allocated funding to enable that improvement.
Background
1. This report provides a summary of progress in the first two quarters of 2015/16 for the following key areas of decent homes and planned works:-
1. 168 out of a total of 230 properties have received their heating upgrade and a further 17 installations were not required. These will be replaced with alternative properties. The remaining sites are affected by access issues. Letters have been sent to the tenants advising of the benefits of the upgrade but access has still not been provided. Again, these properties will be replaced with alternatives.
External Wall Finishes
2. Surveys have been completed and instructions issued to Mears to carry out repointing work to 53 properties across the borough. 29 properties have been completed to date.
Roofing Works
3. Mears have completed 12 pitched roofs to date. Others are ongoing, including flat roofs to 3 blocks of flats (27 no.).
Kitchen & Bathroom Replacements
4. A total of 219 kitchens have been completed as at end December, with a further 57 in progress. We have completed installations to 159 bathrooms, with a further 21 in progress.
5. We have released a further 8 bathrooms and 39 kitchens to support the number of refusals experienced.
6. We are continuing to experience a high number of refusals for kitchen and bathroom replacements and are investigating reasons for refusal. The main reason for residents declining our offer to improve facilities is age related. Many residents are 85 years plus and do not want the upheaval. We are reviewing our processes and producing a promotional booklet to encourage take up and make the offer more appealing to older residents.
7. Due to higher than budgeted for unit costs, although it is anticipated that the budget will be spent, the actual numbers completed will be lower.
Electrical Testing & Upgrade Programme
8. A total of 417 properties from 562 properties have been tested and upgrading has either been completed or due for completion this financial year. Access has not being provided to the remaining 145 properties.
9. A further 404 properties had already been tested previously and just had H&S works completed at the time, as opposed to a full upgrade. Follow on upgrades have now been completed to 296 properties and 9 have since been demolished or upgraded when void. 64 are awaiting works to be scheduled and a further 35 are awaiting access from the tenants for works.
10. Legal letters have been sent to 180 tenants who have not provided access to undertake electrical testing and /or upgrade works and court action will follow if required. Windows & Doors
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Overview and Scrutiny Housing Improvement Sub-Committee at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.