The Executive has agreed to:- 1. note the Capital Outturn position for 2015/16; 2. approve the transfer of budgets totalling £989,237 as shown in Annexe 1 of the report, from the 2015/16 General Fund Capital Programme into 2016/17; 3. approve the spend of £20,000 to carry out small works at ...
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
This report does not have any direct legal implications.
Introduction
1. This report presents the outturn for the Council’s 2015/16 Capital Programme for both the General Fund and Housing Revenue Account (HRA). This report is the final Budget report for the year and builds on the position previously reported to Members through the Budget Management Process.
2. Formal approval is sought to carry some unspent budget items forward to 2016/17. These requests have arisen due to unforeseen delays in spending and these budgets will be spent in 2016/17.
3. This report contains the following Annexes:
General Fund Outturn HRA Core Capital Programme Outturn HRA New Affordable Homes Outturn HRA Stock Remodelling Outturn General Fund Capital Programme
4. Annexe 1 shows details of the 2015/16 Capital Programme Outturn, together with the proposed transfer of budgets from 2015/16 to 2016/17.
5. The original approved Programme for Waverley Capital expenditure in 2015/16 was £3,916,175. Slippage from 2014/15, several additional schemes approved during the year financed from further external funding that had been secured, and some rescheduling due to project changes and delays resulted in an overall approved Programme for the year of £3,628,455 as detailed in paragraph 7.
6. Actual expenditure in the year against these Projects was £2,392,520. Slippage requests total £989,237, as detailed at Annexe 1.
7. The following table analyses the General Fund Capital Programme movements during the year, which are shown in more detail at Annexe 1:
£ Original Capital Programme for 2015/16 3,916,175 Rescheduling from 2014/15 963,895 Supplemented by extra External Funding 966,385 Approved Rescheduling from 2015/16 into 2016/17 -2,218,000 Total Approved Programme 3,628,455
Expenditure in year 2,392,520 Proposed Rescheduling to 2016/17 989,237 Savings Achieved 246,698
8. Consultants have carried out a survey at Bowring House, which covered both the Sheltered unit and the attached Day Centre. This highlighted a number of minor works required to maintain the Day Centre. Therefore it is requested that £20,000 of the General Fund capital savings achieved is rescheduled into 2016/17 to cover the cost of these works.
Housing Revenue Account Capital Programme
9. Annexe 2 shows details of the 2015/16 HRA Core Capital Programme Outturn, together with the proposed transfer of budgets from 2015/16 to 2016/17.
10. Good progress was made in delivering the decent homes works programme despite problems gaining access to properties and tenant refusals to have the work carried out. Annexe 2 shows a total budget to be rescheduled to 2016/17 of £799,564.
11. The following table analyses the HRA Core Capital Programme movements during the year: £ Originally Approved Programme 7,530,000 Rescheduling from 2014-15 1,823,125 Approved Rescheduling from 2015/16 into 2016/17 -810,000 Total Approved Programme 8,543,125 Expenditure in the Year 6,444,465 Proposed Rescheduling 799,564 Savings in capital spend 1,299,096
New Affordable Homes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.