Capital Programme update

Noted Executive 1 paper

AI summaryWaverley's Landlord Services Advisory Board noted a Q1 update on its £13.7m 2026/27 housing capital programme, which is under budget so far but flags forecast overspends on asbestos and electrical works.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQ1 capital programme update received
Money£13.7mFY2026/27 approved capital budget
What happens nextQ2 2026/27Review programme and budget allocation
Who it affectsCouncil tenantsHomes receiving planned maintenance work

What was decided

The board noted the Q1 update on the capital programme, including the financial position, achievements, risks and forward look. Report P36

Why

The report sets out Q1 progress on delivering planned maintenance, home improvements and compliance work across Waverley's council owned homes. Report P3

Officers track spend against a straight line cashflow forecast and report on overspends, underspends and mitigations to keep the programme on track. Report 2.3, 2.4

What happens next

Carry out recruitment to increase internal delivery capacity and continue progressing the procurement pipeline, including priority 2 projects. Report 6.3

Review the programme and budget allocation and recommend any changes, while beginning delivery on the windows and doors and interim roofing contracts. Report 6.2, 6.4

Aim to meet the predicted spend for Q2 once contractors are in the delivery phase. Report 2.5, 6.5

The money

  • £13,770,815 Approved capital budget for FY2026/27 Report 1.1
  • £1,268,724.49 Carry forward from FY2025/26 to be added in Q2 Report 1.1
  • £14,982,668.50 Opening capital budget after Q2 carry forward Report 1.1
  • £3,442,703 Forecast spend to date at Q1 end (straight line basis) Report 2.2, P13
  • £1,276,051 Actual capital spend to date at Q1 end Report 2.2, P13
  • £50,000 Forecast annual overspend on the asbestos programme Report P16
  • £100k Forecast annual overspend on electrical works from testing Report P16
  • £293,902.72 Additional grant to retrofit 20 more homes under Warm Homes Report 3.3

Options considered

  • Chosen: Note the Q1 capital programme update report. Standard scrutiny and assurance role for the board on landlord services delivery Report P36

Implications

  • Financial: Two forecast overspends (asbestos £50,000 and electrical works £100k) are being managed with mitigations, while water hygiene is expected to underspend and be reallocated. Report P16
  • Staffing: All teams delivering the capital programme need extra capacity, combining new specialist posts and recruitment to existing roles, with recruitment activity planned in Q2. Report 1.4
  • Risk: Delays in asbestos surveys and removals affect voids, aids and adaptations and Warm Homes; procurement delays are mitigated through regular procurement meetings. Report 4.2, P25
  • Other: New monitoring and reporting toolkit being rolled out from Q2, with more visual data sharing for officers and members. Report 1.3

Who and where

  • Tenants in Waverley owned homes receiving planned maintenance, compliance and aids and adaptations work Report P3
  • Contractors delivering voids, kitchens and bathrooms, windows and doors, boilers, retrofit and stock condition surveys Report 3.2

Timeline

  • Q1 FY2026/27: Period covered by this update, with £1,276,051 actual spend against a £3,442,703 straight line forecast Report P3, 2.2, P13
  • Q2 FY2026/27: Opening budget expected to rise by £1,268,724.49 after carry forward approval; increased spend anticipated as contractors move into delivery Report 1.1, 2.5, 2.8
  • FY2026/27: Additional £293,902.72 Warm Homes grant must be spent, covering retrofit of 20 extra homes Report 3.3

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced landlord budget for council owned homes
  • A&A: Aids and Adaptations, home modifications that help residents live independently
  • Voids: Empty council properties being prepared before reletting to new tenants
  • Warm Homes: Government funded programme retrofitting energy efficiency measures in council homes
  • Carry forward: Unspent budget from a previous financial year added to the new year's budget
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item39

Resolved

RESOLVED that the Capital Programme update be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Q1 Capital delivery programme report Waverley Borough Council

Information note to: Landlord Services Advisory Board Date: 30 July 2026 Author: Katie Reilly Tel: 01483 523544 Email: [email protected]

Information for Scrutiny and Comment This report provides an update on our progress in delivering planned maintenance, home improvements and compliance work across Waverley’s council-owned homes, during the first quarter of this financial year. The Council’s capital delivery programme is designed to ensure tenants’ homes remain safe, warm and decent. The £13.7m programme for FY2026/27 is largely divided between capital works for aids & adaptations, voids, planned works programmes (c.43%) and compliance programmes (c.33%). This is the largest capital programme that Waverley has set out to deliver in recent years and is reflective of the evolving regulatory and compliance environment for Housing and is underpinned by our commitment to deliver against the Corporate and Service strategies. Decent and Affordable Homes and the Housing Asset Management Strategy, respectively. Below, you will find details of what we have achieved in Q1 of FY2026/27, how we have spent the budget so far and what we have planned for the next quarter. The report focuses on highlights across the quarter.

1. Q1 performance at a glance

1.1Approved budget for FY2026/27 is £13,770,815. This will increase by £1,268,724.49 in Q2 due to approval of carry forward budget requests from FY2025/26, bringing the capital programme opening budget up to £14,982,668.50.

1.2The council are committed to spending this year’s budget. High value programmes have been prioritised across year one to optimise delivery.

o Priority 1 procurements are complete, with all high value contracts now in contract or at contract signing stage.

Page 1 of 4 o Priority 2 procurements are underway, for long-term joint programmes in particular and priority 3 procurements are being scoped in advance of tendering.

1.3With support from Service Improvement, we have developed a more robust monitoring and reporting capital delivery toolkit for officers. From Q2 we anticipate being able to share data and updates in a more digestible, visual format.

1.4All teams delivering the capital programme require additional staffing capacity to deliver programmes. This is a combination of new capacity with specific technical expertise, and recruitment to existing posts.

2. Financial update 2.1. The council is committed to spending HRA funding wisely and takes a data informed approach to project programming and delivery.

2.2Current position at Q1 end:

Total Approved Forecast budget Actual budget Variances and Capital works spend to date spend to date pressures / budget 26/27 rationale £13,770,815 £3,442,703 £1,276,051 Straight line cash flow forecast used

2.3We are currently tracking under budget against a straight line cashflow forecast, due to ongoing procurement activity across Q1 for contractors who will delivery against this year’s budget. Spend to date largely comes from programmes already in delivery with contractors we were already in contract with at the start of the financial year.

2.4Capital compliance highlights:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme updateReport 176 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 19 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AL
Councillor Andrew LaughtonCommittee Member, present
JK
Councillor Jacquie KeenCommittee Member, present
AM
Councillor Alan MorrisonCommittee Member, present
RB
Rod BlackmoreCommittee Member, present
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, present
DM
Dave MaddamsObserver, present
LL
Lillian LanekOfficer, present
SR
Scott RichardsonOfficer, present

All 19 on the meeting page

On this subject at Waverley

Search all
  1. Capital Programme updateThis decision
  2. General Fund Budget 2025/26, Capital Programme 2025/26 and Medium Term Financial Plan 2025/26 - 2028/29Agreed
  3. HRA Budget 2025/26, Capital Programme 2025/26Approved
  4. HRA Business Plan - Revenue Budget and Capital Programme 2023/24Decided
  5. Exe 84/21 housing revenue account business plan - revenue budget and capital programme 2022/23Approved
  6. Housing Revenue Account Business Plan - Revenue Budget and Capital Programme 2022/23Decided

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. Noted Open
30 Jul 2026 Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. Noted Open
30 Jul 2026 Annual Complaints and Service Improvement ReportRESOLVED that: · the contents of the Annual Complaints and Service Improvement Report 2025/26, including complaint pe... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies