Resolved
Executive RESOLVED to approve the following budgets to be brought forward for Sites C and F from the estimated budget for 2021/22: Scheme/site Total budget Site C £336,000 Site F £150,000 [Housing Overview & Scrutiny Committee]
Executive approved this item on Tuesday 3 November 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Executive RESOLVED to approve the following budgets to be brought forward for Sites C and F from the estimated budget for 2021/22: Scheme/site Total budget Site C £336,000 Site F £150,000 [Housing Overview & Scrutiny Committee]
2.1It is recommended that the Executive approve the following budgets to be brought forward for Sites C and F from the estimated budget for 2021/2022:
Scheme/site Total budget Site C £336,000 Site F £150,000
3.1To ensure sufficient budget to continue delivery of pre-development, demolition and survey work required to inform and secure full planning consent.
4. Relationship to the Corporate Strategy and Service Plan
4.1This project’s relationship with the Corporate Strategy includes: o A financially sound Waverley, with infrastructure and services fit for the future o Housing to buy and rent, for those at all income levels
4.2This project’s relationship with the Housing Delivery and Communities Service plan includes: o Increased delivery of well-designed and well-built new homes o Delivery of 20 new Council homes a year o Delivery of Ockford Ridge Regeneration Scheme
5. Implications of decision
5.1Resource (Finance, procurement, staffing, IT)
Finance – the request to bring forward budget is not a supplementary budget request which reduces reserves but a re-phasing of the use of reserves.
Current Budget Site C
The current approved Site C budget and budget estimates for 2021/2022 & 2022/2023 are set out below:
Financial year Current Approved Rephased budget / estimates approved budget / (£) estimates (£) 2020/2021(B) 118,000 454,000 2021/2022 (E) 3,010,000 2,674.000 2022/2023 (E) 3,802,000 3,802,000 TOTAL 6,930,000 6,930,000
Officers have identified surveys, fees, utility disconnection and diversion and demolition works costs (confirmed and estimated) to be paid between now and March 31 2021 and request that £336k (including 10% contingency) from the estimated budget 2021/22 £3.01m is brought forward to cover these costs. The budget for 2021/2022 and future budget estimates will be reforecast as part of the budget setting process.
Current Budget – Site F
The current approved Site F budget and budget estimates for 2021/2022 and further two years are set out below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Ockford Ridge, Godalming: request to bring forward budget for Site C and Site FReport | 134 KB | DownloadRead as text |
Follow Executive at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... | Agreed | Open |
| 1 Sep 2026 | New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... | Decided | Open |
| 1 Sep 2026 | Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... | Agreed | Open |
| 1 Sep 2026 | Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... | Approved | Open |
| 1 Sep 2026 | Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.