The Executive RESOLVED to: 1. approve the award of the proposed contract to the top-ranked bidder following completion of the procurement process; and 2. delegate authority to the Strategic Director for Transformation and Governance to complete all required contractual documentation and approve execution of the contract documentation. Reason: The current ... EXE 71/22
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1. Approve the award of the proposed contract to the top ranked bidder, following completion of the procurement process; and
2. Delegate authority to the Strategic Director for Transformation & Governance to complete all required contractual documentation and approve execution of the contract documentation.
Reason for the recommendation
Leisure Management Contract position
3.1The current 15 year leisure management contract, for our five leisure centres, expires on 30 June 2023 and the Council needs a new contractual arrangement to be in place for the 1 July 2023.
3.2A Leisure Management Contract tender Project Working Group (PWG) has been working together to ensure that all aspects of the business are involved and duly considered in the tender process.
3.3The PWG have been working with appointed consultants, SLC, to progress in accordance with the procurement timetable and ensure that each stage is completed accordingly. 3.4 The PWG are on target, with the next stages detailed below.
Next stage/activity Target date 8 Bidder Negotiation Meetings Dec 2022 – complete 9 Invitation to Submit Revised Tenders (ISRT) Jan 2023 10 ISRT submission deadline Feb 2023 11 Evaluation of Revised Tenders Feb – Mar 2023 12 Notification of outcome to bidders Apr 2023 13 Standstill period Apr 2023 14 Finalise Contract Award Apr 2023 15 Mobilisation Period May – Jun 2023 16 Contract start date 1 Jul 2023
Background
Leisure Management Contract specification
3.5As per the programme, the PWG have made the necessary amendments to the Sport England Contract template and developed a Services Specification to ensure that it meets our corporate priorities, processes and policies.
3.6The Services Specification sets out the required performance standards and reporting requirements that the operator shall meet for the operation of the services and facilities throughout the Contract period.
3.7The Specification outline includes; i. General core requirements – Strategic Objectives and Contribution to wider Strategic Priorities, Facility Management, Leisure Investment, Utilities and Environmental and Energy Management ii. Service Requirements – the Active Communities Programme, pricing, staffing and Health & Safety iii. Asset Management - Capital and Revenue Funding (Existing Facilities and new Cranleigh Leisure Centre), Building Maintenance, Climate Emergency, Environmental and Energy Management iv. Performance Management and reporting – Planning to Improve (Service Planning) and Meetings and Reporting v. Key Performance Indicators – a comprehensive set of criteria developed by the PWG to measure performance against our Contract strategic objectives.
5.0Relationship to the Corporate Strategy and Service Plan
5.1The Leisure Management Contract directly links with Waverley’s Corporate Strategy 2020-25 and our strategic priorities: Supporting a strong, resilient local economy Taking action on Climate Emergency and protecting the environment Effective strategic planning and development management to meet the needs of our communities Improving the health and wellbeing of our residents and communities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.